MONTHYEARML24310A2262024-11-0606 November 2024 NEI Preliminary Perspectives on NRC Draft Noak Microreactor White Paper ML24303A2212024-10-29029 October 2024 NEI SDP Realism Presentation for October 30, 2024 Public Meeting ML24291A0062024-10-17017 October 2024 NEI Slide Presentation: ACRS Regulatory Policies and Practices - Draft White Paper on Nth-of-a-Kind (Noak) Micro-Reactor Licensing and Deployment Considerations - Sc - October 17, 2024 ML24267A0032024-09-25025 September 2024 NEI Slides for ROP Public Meeting Sept 2024 ML24263A2592024-09-17017 September 2024 06 Jim Slider NEI September 2024 NRC Ai Public Workshop 09-17-2024 ML24249A2012024-09-0909 September 2024 NEI Presentation - Sept 9 Public Meeting - Flooding DGs - Final ML24249A1152024-09-0505 September 2024 Power Uprate September 5, 2024 Public Meeting Slides ML24243A1612024-08-30030 August 2024 Slide Presentations for High Burnup (Hbu) Workshop V ML24228A2102024-08-20020 August 2024 2024 NEI Early Warning System (EWS) Presentation - NEI Slides ML24229A0012024-08-19019 August 2024 NEI - Spent Fuel Management: Safety and Efficiency Improvements Through Technology and Performance Margins - NRC PIRTs Public Meeting Rev. 8.15.2024 Final ML24218A1832024-07-30030 July 2024 NEI 7-30-24 Trial Use RG 1.247 Path Forward Final ML24197A0652024-07-17017 July 2024 SDP Realism Public Meeting NEI Presentation ML24172A1952024-06-27027 June 2024 NEI Slides for 06-27-2024 Public Meeting Structures as IROFS at Fuel Cycle Facilities ML24178A0372024-06-26026 June 2024 NRC Power Uprate Review Preparation June 26, 2024 Public Meeting Slides ML24164A1972024-06-17017 June 2024 Public Meeting Slides - NRC Staff Comments and Observations on NEI 10-01, Rev 2 Industry Guideline for Developing a Plant Parameter Envelope in Support of an Early Site Permit ML24130A1972024-05-0909 May 2024 NEI Presentation Slides on Rapid and Large-Scale Nuclear Reactor Deployments for Remote Industrial Applications - May 14 2024 Public Meeting ML24129A1382024-05-0808 May 2024 NEI Slides on Centralized Inspections for May 9, 2024 Public Workshop ML24114A1142024-04-18018 April 2024 NEI Supplemental Information on NRC Comments on NEI 20-07, Draft Revision E - April 18 Meeting (Non-Proprietary) ML24103A1532024-04-12012 April 2024 NEI Supplemental Information on NRC Comments of NEI 20-07 Rev E (Non-Proprietary) - Slides ML24092A3132024-04-0303 April 2024 Public Mtg_2024-04-03 Pre-submittal Meeting with the Nuclear Energy Institute (NEI) to Discuss an Update to NEI 03-12, Security Plan Template (Revision 8)_NEI Slides ML24088A2252024-03-26026 March 2024 NEI Slides for Centralized Inspections March 2024 ROP Public Meeting ML24075A2092024-03-14014 March 2024 NEI Advanced Reactor Di&C Task Force Slides - Accident Monitoring Instrumentation ML24075A2102024-03-14014 March 2024 NEI Alan Campbell Slides - Non-Safety-Related with Special Treatment – Digital Considerations ML24082A1792024-03-14014 March 2024 RIC-2024 TH18 True Slides ML24086A5342024-03-14014 March 2024 RIC 2024 TH23 Slides - the Industry’S Innovation Imperative ML24067A2592024-03-13013 March 2024 RIC-2024 W14 Slides - NEI-BHoltzman an Industry Perspective on Advanced Reactor Construction Oversight ML24067A0062024-03-0808 March 2024 1 - NRC - Workshop3 - Non-LOCA Release Fractions Feedback - Final ML24067A0072024-03-0808 March 2024 2 - NRC - Workshop3 - Non-LOCA - FFRD - Final ML24067A0092024-03-0808 March 2024 3 - NRC - Worshop3 - CR Dose Presentation - Final ML24067A0102024-03-0808 March 2024 4 - NRC - Workshop3 - EQ Presentation - Final ML24067A0122024-03-0808 March 2024 6 - NRC - Workshop3 - Best Estimate Dose ML24067A0132024-03-0808 March 2024 7 - NRC - Workshop3 - Closing Remarks ML24067A2882024-03-0808 March 2024 1 (Revised)-NRC_Workshop3_Non-LOCA Release Fraction Feedback-Final ML24043A1162024-02-13013 February 2024 3- EQ Presentation Workshop 2 ML24043A1192024-02-13013 February 2024 1- Impacts on RG 1.183 for Workshop2 ML24043A1202024-02-13013 February 2024 2- CR Dose Presentation Workshop 2 ML24016A2372024-01-17017 January 2024 NEI Environmental Reviews Slides Public Meeting 1-17-24 ML24010A0202024-01-11011 January 2024 Public Meeting on SLR Efficiencies - NEI Presentation ML24008A0442024-01-0909 January 2024 NEI - Slides for NRC Workshop 1 on Revision to RG 1.183 R1 - Final - ML24008A044 ML23342A0262023-12-14014 December 2023 December 14, 2023, Presentation on NEI 23-01 Operator Cold Licensing Training Plan for Advanced Nuclear Reactors ML23347A1782023-12-13013 December 2023 12-14 NEI EPRI Presentation NRC Public Meeting 16-03 R1 ML23303A1922023-10-30030 October 2023 NEI Slides for SLR Public Meeting - Oct 31 2023 ML23324A2392023-10-24024 October 2023 S1P6 - Hilary Lane - NRC AMT Workshop - Oct. 2023 ML23261C3792023-09-27027 September 2023 NEI 22-04 Pre-Submittal Meeting with NRC - September 27, 2023 ML23258A1992023-09-20020 September 2023 NEI 99-02 Draft Rev. 8 Update for Sept 2023 ROP Public Meeting ML23242A0782023-08-30030 August 2023 Hbu Workshop IV Industry Presentation: Drive to Deploy ATF with Increased Enrichment and Higher Burnup ML23242A1662023-08-30030 August 2023 The Future of Nuclear Power: 2023 Baseline Survey (Slides) ML23230A0142023-08-22022 August 2023 Industry Slide Presentation for 8-22-23 Meeting on ARCAP-TICAP and DG-1404 Guidance Documents ML23228A0042023-08-18018 August 2023 NEI Slides for Public Meeting to Discuss Possible Efficiencies on the Subsequent License Renewal Review - August 18, 2023 ML23191A0162023-07-11011 July 2023 NEI Comments on Risk-Informed Process for Evaluation (RIPE) DORL TSG - 7/11/23 Public Meeting Slides from NEI 2024-09-09
[Table view] |
Text
Industrys COVID Lessons Learned Cheryl Gayheart, SNC Jean Fleming, PSEG Jim Slider, NEI April 21, 2021
©2021 Nuclear Energy Institute
Contents Scope Sources Key Learnings Identified Recommendations
©2021 Nuclear Energy Institute 2
Scope of this Discussion Our focus is on the industrys experience in responding to and supporting NRC inspections and compliance, not on NRC licensing activities Much of our experience arises from the NRCs widespread use of remote and hybrid inspections since March 2020 Our knowledge of the NRCs experience is limited to what we have observed and what the NRC has shared with industry, and how industry responded
©2021 Nuclear Energy Institute 3
Sources Regional Utility Group (RUG) meetings ROP Task Force meetings NSIAC meetings NEIs Inspection Modernization Team
©2021 Nuclear Energy Institute 4
Key Learnings Collaboration Remote Work Technology Processes New Normal
©2021 Nuclear Energy Institute 5
Collaboration The COVID-19 public health emergency brought out the best in industry and the NRC:
- Cooperation in protecting plant staff and inspectors from infection
- Mutual appreciation for the vital roles both sides play in protecting public health, safety, security and the environment, and in assuring the provision of safe, reliable electricity
- Adapting to novel and changing conditions, including mandatory remote work
- Collaboration in solving emergent problems quickly and efficiently
©2021 Nuclear Energy Institute 6
Remote Work COVID lessons learned are primarily about adapting to telework Universal telework dramatically changed how we communicate, how we get work done, and how we use technology to support our work and relationships Universal telework:
- Is changing workplace culture
- Has been a boon to many employees, a bane to some, and a challenge to all
- Has highlighted what can and cant be done virtually
- Caused a reassessment of who needs to be onsite and how often
©2021 Nuclear Energy Institute 7
Technology The PHE accelerated and promoted the adoption of communications and information-sharing technologies that were already entering our workplaces
- Electronic information exchange/filesharing services
- Remote access to plant data and information systems
- Video recording or live-streaming
- Virtual meeting/presentation platforms The technology imperative highlighted challenges in the industrys and NRCs electronic interfaces, cyber security requirements and privacy policies A common report: technology facilitates inspector access to licensees virtual meetings, documents, and information systems
©2021 Nuclear Energy Institute 8
Processes Widespread teleworking has broadened our understanding of where things must be done
- Key elements of the inspection process can be done anywhere Document retrieval Document review/inspection prep Inspector Q&A Entrance meetings Exit meetings
- Planned interactions between inspectors and licensee personnel (such as interviews) can be done through video conferencing
©2021 Nuclear Energy Institute 9
New Normal The COVID experience has overturned assumptions about the benefits and costs of expecting support staff to be onsite
- Health and safety risks of being onsite
- Flexibility of telework expands the available workforce and reduces demand for onsite resources (such as office space, in-processing, security screening, etc.)
- Efficiencies of telework mean greater productivity, job satisfaction Many, possibly most, licensees are considering reducing their onsite population by enabling/encouraging support staff to telework
©2021 Nuclear Energy Institute 10
Recommendations Establish guiding principles for modernizing the inspection program (ours are shown on the following slide)
Begin by applying those principles to the use of remote inspection techniques Work with industry and other external stakeholders to identify impediments and solutions to the use of remote inspection techniques Continue to explore the baseline inspection program to identify additional opportunities to improve inspection efficiency and effectiveness through the use of technology
©2021 Nuclear Energy Institute 11
Guiding Principles
- 1. Maintain NRC effectiveness
- 2. Maintain NRC independence
- 3. Ensure Resident Inspectors access
- 4. Recognize necessity of some onsite activities
- 5. Be flexible in application of remote techniques
- 6. Leverage information technology
- 7. Embrace efficiencies where they are found
- 8. Use remote techniques where doing so enhances efficiency
- 9. After effectiveness is assured, optimize efficiency
- 10. Consider pros and cons for both NRC and licensees
©2021 Nuclear Energy Institute 12
Conclusions Telework is part of the new normal for NRC and industry It offers benefits and efficiencies to our plant support workers The way we support NRC inspections has changed and these changes will continue after COVID passes We are eager to work with the NRC to ensure the NRC can utilize remote methods and gain efficiencies through technology
©2021 Nuclear Energy Institute 13