Attachment 6 OBDI 202 - IOLE Process Rev 3 PROPOSED OUTLINE COMMENTS Facility:

River Bend Station First Exam Date:

February 8, 2021 Written Exam Outline Comment Resolution 1 NRC Generated 2 No additional comments Administrative JPM Outline Comment Resolution 1

Loss of Feedwater Heating event.

Applicant must utilize AOP-7 and AOP-24 to determine placement on the Power to Flow Map. CRS must actions taken IAW AOP-24. What specifically makes this at the SRO level?

Those are supplemental actions only taken by or directed by the CRS. Only immediate actions taken by ROs 2

All Admin JPMs are new will need to evaluate when draft submittal is received N/A Control Room / In-Plant System JPM Outline Comment Resolution 1 No Comments Simulator Scenario Outline Comments Comment Resolution 1 Scenario 1, skipped an event number fix 2 Scenario 1, Need basis for CT-1 Will provide with draft submittal 3

Scenario 2, CT-2 needs better bounding criteria. Prefer not to have do X prior to exiting procedure Y Working with ops to determine better bounding criteria 4

Scenario 3, CT-1 needs to be determined what the criteria will be to determine if the threshold is met or not.

Working with OPS to determine 5 Scenario 2, CT-2 see comment 3 Working with ops to determine better bounding criteria