ML21095A181

From kanterella
Jump to navigation Jump to search
Dashboard Report 4-1-2021
ML21095A181
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 04/01/2021
From:
NRC/NRR/VPOB
To:
Gaslevic J
References
Download: ML21095A181 (4)


Text

VOICES DASHBOARD REPORT - VOG3 Note: This pie chart accounts for the completion of each ITAAC. If no UIN or ICN has been received for a given ITAAC it is counted as not received. Once a UIN has been received, it will be counted as UIN Under Review or UIN accepted. If the UIN requires resubmittal, the ITAAC counts as not received. Once an ICN is received it will be counted as ICN Under Review or Verified as Completed. If an ICN is not accepted, the count reverts back to Not Received, or UIN Accepted as applicable.

Review Time Total ICNs Currently In Review Under 14 1

14 to 28 0

Over 28 2

Total 3

Review Time Total UINs Currently In Review Under 14 0

14 to 28 0

Over 28 0

Total 0

Review Time ICNs Under Disposition Under 14 0

14 to 28 0

Over 28 0

Total 0

1 April 1, 2021 The 2 ICNs currently shown as red for Over 28 days are ITAAC 664 and 666, for which NRC inspections are not scheduled until April 2021 and remain in an under-review status.

Under disposition is an interim status assigned to an ICN when staff identify a potential lack of information. The under disposition status will be applied while the issue is under discussion with the licensee until a final status of verified or insufficient information is determined.

2 April 1, 2021

Days in Review charts provide the number of days in review on average for each ICN or UIN closed in a given month.The number above each month's entry reflects the total number of UINs or ICNs closed in that month.

Note: Months with no completed reviews will display without data.

Note: Months with no completed reviews will display without data.

3 April 1, 2021

81%

19%

Vogtle Unit 3: NRC ITAAC Inspection Plan Status Completed ITAAC Inspection Plans ITAAC Inspection Plans Not Complete Dated April 2, 2021 NOTE: "ITAAC Inspection Plans Not Complete" include long-term inspections in progress and construction and test activities not ready for inspection.

123 126 129 138 135 138 144 146 152 155 169 178 180 184 67 70 73 75 78 82 88 89 90 90 0

0 0

2 0

0 2

0 0

0 3

2 2

2*

0 20 40 60 80 100 120 140 160 180 200 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Vogtle Unit 3: ICNs Received and NRC Inspection Status Total ICNs Received (targeted and non-targeted ITAAC)

Total ICNs Received for Targeted ITAAC NRC ITAAC Inspection Incomplete for ICNs Submitted (at the time of the report)

Dated April 2, 2021

  • Note: Two inspections from December remained incomplete in March due to the decision to incorporate scheduling efficiencies with other associated activities and avoid extra travel during the public health emergency.