Core Operating Limits Report for Quad Cities Unit 1 Cycle 27 - Revised
ML21090A154
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 03/31/2021
From: Ohr K
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML21090A153 List:
References
SVP-21-018
Download: ML21090A154 (1)


Text

Exelon Generation SVP-21-018 10 CFR 50 March 31, 2021 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Quad Cities Nuclear Power Station, Unit 1 Renewed Facility Operating License No. DPR-29 NRC Docket No. 50-254

Subject:

Core Operating Limits Report for Quad Cities Unit 1 Cycle 27 - Revised

Reference:

Letter from Kenneth S. Ohr (Exelon Generation Company, LLC) to the U.S.

NRC (Regional Administrator, Region 111), "Core Operating Limits Report for Quad Cities Unit 1 Cycle 27," dated March 26, 2021 Quad Cities Nuclear Power Station Unit 1 was shutdown for Refuel Outage 26 (01 R26) on March 15, 2021. In accordance with Technical Specifications Section 5.6.5.d, enclosed is the Core Operating Limits Report (COLR) for Quad Cities Unit 1 Cycle 27. Note that this is revised from the March 26, 2021 transmittal; the new version is designated as Revision 16.

Should you have any questions concerning this letter, please contact Sherrie Grant at (309) 227-2800.

Respectfully, d

Ken Ohr Site Vice President Quad Cities Nuclear Power Station

Enclosure:

Core Operating Limits Report for Quad Cities Unit 1 Cycle 27 (Revised) cc: Regional Administrator - NRC Region Ill NRC Senior Resident Inspector - Quad Cities Nuclear Power Station