1. REQUISITION NUMBER PAGE OF SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30 NMSS-21-0033 1 16

2. CONTRACT NO. 3. AWARD/ 4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION 31310020A0003 EFFECTIVE DATE 31310021Q0017 ISSUE DATE 31310021F0007 02/10/2021
7. FOR SOLICITATION a. NAME b. TELEPHONE NUMBER (No collect calls) 8. OFFER DUE DATE/LOCAL TIME INFORMATION CALL: BANU GOLDFEIZ ET
9. ISSUED BY CODE NRCHQ 10. THIS ACQUISITION IS X UNRESTRICTED OR SET ASIDE:  % FOR:

WOMEN-OWNED SMALL BUSINESS U.S. NRC - HQ SMALL BUSINESS (WOSB) ELIGIBLE UNDER THE WOMEN-OWNED Acquisition Management Division HUBZONE SMALL SMALL BUSINESS PROGRAM NAICS: 541519 BUSINESS EDWOSB Mail Stop: TWFN-07B20M SERVICE-DISABLED Washington DC 20555-0001 VETERAN-OWNED 8(A)

SIZE STANDARD: $150.00 SMALL BUSINESS

11. DELIVERY FOR FOB DESTINA- 12. DISCOUNT TERMS 13b. RATING TION UNLESS BLOCK IS 13a. THIS CONTRACT IS A MARKED 30 RATED ORDER UNDER
14. METHOD OF SOLICITATION SEE SCHEDULE DPAS (15 CFR 700)

X RFQ IFB RFP

15. DELIVER TO CODE NRCHQ 16. ADMINISTERED BY CODE NRCHQ Nuclear Regulatory Commission U.S. NRC - HQ Nuclear Regulatory Commission Acquisition Management Division Washington DC 20555-0001 Mail Stop: TWFN-07B20M Washington DC 20555-0001 17a. CONTRACTOR/ CODE 152858358 FACILITY 18a. PAYMENT WILL BE MADE BY CODE NRC PAYMENTS 1 OFFEROR CODE AEGIS.NET INC NRC PAYMENTS Attn: Mario Hyland NRC@fiscal.treasury.gov P.O. BOX 3897 MERRIFIELD VA 221163897 TELEPHONE NO. 7038936020707 17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED SEE ADDENDUM
19. 20. 21. 22. 23. 24.

ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT GSA Contract #: GS35F0125S The purpose of this BPA Call is to acquire contractor IV&V support services for all NMSS Mission Information Technology (IT) wherein IV&V support services are necessary.

Accounting Info:

2021-X0200-GHLS-50-50D099-6110-34-2-156-252A-34 156-6110-GHLS Period of Performance: 04/16/2021 to 04/15/2022 (Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)

See schedule $9,996,941.10 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED.

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN X 29. AWARD OF CONTRACT: OFFER COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER REF.

DATED . YOUR OFFER ON SOLICITATION (BLOCK 5),

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED. HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED DOMONIQUE MALONE 03/30/2021 AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (REV. 2/2012)

PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212

2 of 16

19. 20. 21. 22. 23. 24.

ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT 32a. QUANTITY IN COLUMN 21 HAS BEEN RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED 36. PAYMENT 37. CHECK NUMBER CORRECT FOR COMPLETE PARTIAL FINAL PARTIAL FINAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY 41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 42a. RECEIVED BY (Print) 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE 42b. RECEIVED AT (Location) 42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS STANDARD FORM 1449 (REV. 2/2012) BACK

31310020A0003/31310021F0007 Page 3

31310020A0003/31310021F0007 B - Supplies or Services/Prices B.1 BRIEF PROJECT TITLE AND WORK DESCRIPTION (a) The title of this project is: Office of Nuclear Material Safety and Safeguards (NMSS) IV&V Support Services (b) Summary work description: The objective of this BPA Call is to acquire contractor IV&V support services for all NMSS mission Information Technology (IT) wherein IV&V support services are necessary. Specifically, NMSS needs IV&V support services to ensure accurate capture and implementation of user needs as well as operational and governance support where independence is required in the functional areas of: system development; product review and testing; technology assessments, feasibility studies and alternative analyses; investment governance support; and Federal Information Security Modernization Act (FISMA) compliance.

B.2 TYPE OF CONTRACT (JULY 2020)

The contract type for this award is Labor-Hour.

B.3 CONSIDERATION AND OBLIGATION-TASK ORDERS (a) The ceiling of this order for services is 9,996,941.10.

(b) This order is subject to the minimum and maximum ordering requirements set forth in the contract.

(c) The amount presently obligated with respect to this order is . The obligated amount shall, at no time, exceed the order ceiling as specified in paragraph (a) above. When and if the amount(s) paid and payable to the Contractor hereunder shall equal the obligated amount, the Contractor shall not be obligated to continue performance of the work unless and until the Contracting Officer shall increase the amount obligated with respect to this order, in accordance with FAR Part 43 - Modifications. Any work undertaken by the Contractor in excess of the obligated amount specified above is done so at the Contractor's sole risk and may not be reimbursed by the Government.

(d) The Contractor shall comply with the provisions of FAR 52.232 Limitation of Funds, for incrementally-funded delivery orders or task orders.

Page 4

31310020A0003/31310021F0007 C - Description/Specifications C.1 STATEMENT OF WORK Please See Attachment 1 -Performance Work Statement Page 5

31310020A0003/31310021F0007 D - Packaging and Marking D.1 PACKAGING AND MARKING (a) The Contractor shall package material for shipment to the NRC in such a manner that will ensure acceptance by common carrier and safe delivery at destination. Containers and closures shall comply with the Surface Transportation Board, Uniform Freight Classification Rules, or regulations of other carriers as applicable to the mode of transportation.

(b) On the front of the package, the Contractor shall clearly identify the contract number under which the product is being provided.

(c) Additional packaging and/or marking requirements are as follows: N/A.

D.2 BRANDING The Contractor is required to use the statement below in any publications, presentations, articles, products, or materials funded under this contract/order, to the extent practical, in order to provide NRC with recognition for its involvement in and contribution to the project. If the work performed is funded entirely with NRC funds, then the contractor must acknowledge that information in its documentation/presentation.

Work Supported by the U.S. Nuclear Regulatory Commission (NRC), Office of Nuclear Material Safety and Safeguards, under Contract/order number 31310020A0003/31310021F0007.

Page 6

31310020A0003/31310021F0007 E - Inspection and Acceptance E.1 INSPECTION AND ACCEPTANCE BY THE NRC (SEP 2013)

Inspection and acceptance of the deliverable items to be furnished hereunder shall be made by the NRC Contracting Officers Representative (COR) at the destination, accordance with FAR 52.247 F.o.b. Destination.

Page 7

31310020A0003/31310021F0007 F - Deliveries or Performance F.1 PLACE OF DELIVERY-REPORTS The items to be furnished hereunder shall be delivered, with all charges paid by the Contractor, to:

a. Name: Joel Bristor (1 electronic copy)

Joel.Bristor@nrc.gov BPA Call Contracting Officers Representative (COR)

F.2 PERIOD OF PERFORMANCE ALTERNATE This contract shall commence on 4/16/2021 and will expire on 4/15/2022. The term of this contract may be extended at the option of the Government for an additional 7-years, from 4/16/2022 to 4/15/2029.

The Anticipated Base Period: is 4/16/2021 - 4/15/2022 The Anticipated Option Periods are as follows:

Option Period 1: 4/16/2022 - 4/15/2023 Option Period 2: 4/16/2023 - 4/15/2024 Option Period 3: 4/16/2024 - 4/15/2025 Option Period 4: 4/16/2025 - 4/15/2026 Option Period 5: 4/16/2026 - 4/15/2027 Option Period 6: 4/16/2027 - 4/15/2028 Option Period 7: 4/16/2028 - 4/15/2029 Page 8

31310020A0003/31310021F0007 G - Contract Administration Data NRC Local Clauses Incorporated by Full Text G.1 REGISTRATION IN FEDCONNECT (JULY 2014)

The Nuclear Regulatory Commission (NRC) uses Unison Softwares secure and auditable two-way web portal, FedConnect, to communicate with vendors and contractors. FedConnect provides bi-directional communication between the vendor/contractor and the NRC throughout pre-award, award, and post-award acquisition phases.

Therefore, in order to do business with the NRC, vendors and contractors must register to use FedConnect at https://www.fedconnect.net/FedConnect. The individual registering in FedConnect must have authority to bind the vendor/contractor. There is no charge for using FedConnect. Assistance with FedConnect is provided by Unison Software, not the NRC. FedConnect contact and assistance information is provided on the FedConnect web site at https://www.fedconnect.net/FedConnect.

G.2 ELECTRONIC PAYMENT (DEC 2017)

The Debt Collection Improvement Act of 1996 requires that all payments except IRS tax refunds be made by Electronic Funds Transfer. Payment shall be made in accordance with FAR 52.232-33, entitled Payment by Electronic Funds Transfer-System for Award Management.

To receive payment, the contractor shall prepare invoices in accordance with NRCs Billing Instructions. Claims shall be submitted through the Invoice Processing Platform (IPP)

(https://www.ipp.gov/). Back up documentation shall be included as required by the NRCs Billing Instructions.

NRCAR Clauses Incorporated By Full Text G.3 2052.215-71 CONTRACTING OFFICER REPRESENTATIVE AUTHORITY. (OCT 1999)

(a) The contracting officer's authorized representative (hereinafter referred to as the COR) for this contract is:

Page 9

31310020A0003/31310021F0007 Name: Joel Bristor Email: Joel.Bristor@nrc.gov Phone: 301-415-0299 (b) Performance of the work under this contract is subject to the technical direction of the NRC COR. The term "technical direction" is defined to include the following:

(1) Technical direction to the contractor which shifts work emphasis between areas of work or tasks, authorizes travel which was unanticipated in the Schedule (i.e., travel not contemplated in the Statement of Work (SOW) or changes to specific travel identified in the SOW), fills in details, or otherwise serves to accomplish the contractual SOW.

(2) Provide advice and guidance to the contractor in the preparation of drawings, specifications, or technical portions of the work description.

(3) Review and, where required by the contract, approval of technical reports, drawings, specifications, and technical information to be delivered by the contractor to the Government under the contract.

(c) Technical direction must be within the general statement of work stated in the contract. The COR does not have the authority to and may not issue any technical direction which:

(1) Constitutes an assignment of work outside the general scope of the contract.

(2) Constitutes a change as defined in the "Changes" clause of this contract.

(3) In any way causes an increase or decrease in the total estimated contract cost, the fixed fee, if any, or the time required for contract performance.

(4) Changes any of the expressed terms, conditions, or specifications of the contract.

(5) Terminates the contract, settles any claim or dispute arising under the contract, or issues any unilateral directive whatever.

(d) All technical directions must be issued in writing by the COR or must be confirmed by the COR in writing within ten (10) working days after verbal issuance. A copy of the written direction must be furnished to the contracting officer. A copy of NRC Form 445, Request for Approval of Official Foreign Travel, which has received final approval from the NRC must be furnished to the contracting officer.

(e) The contractor shall proceed promptly with the performance of technical directions duly issued by the COR in the manner prescribed by this clause and within the COR's authority under the provisions of this clause.

(f) If, in the opinion of the contractor, any instruction or direction issued by the COR is within one of the categories as defined in paragraph (c) of this section, the contractor may not proceed but shall notify the contracting officer in writing within five (5) working days after the receipt of any instruction or direction and shall request the contracting Page 10

31310020A0003/31310021F0007 officer to modify the contract accordingly. Upon receiving the notification from the contractor, the contracting officer shall issue an appropriate contract modification or advise the contractor in writing that, in the contracting officer's opinion, the technical direction is within the scope of this article and does not constitute a change under the "Changes" clause.

(g) Any unauthorized commitment or direction issued by the COR may result in an unnecessary delay in the contractor's performance and may even result in the contractor expending funds for unallowable costs under the contract.

(h) A failure of the parties to agree upon the nature of the instruction or direction or upon the contract action to be taken with respect thereto is subject to 52.233 Disputes.

(i) In addition to providing technical direction as defined in paragraph (b) of the section, the COR shall:

(1) Monitor the contractor's technical progress, including surveillance and assessment of performance, and recommend to the contracting officer changes in requirements.

(2) Assist the contractor in the resolution of technical problems encountered during performance.

(3) Review all costs requested for reimbursement by the contractor and submit to the contracting officer recommendations for approval, disapproval, or suspension of payment for supplies and services required under this contract.

(4) Assist the contractor in obtaining the badges for the contractor personnel.

(5) Immediately notify the Security Branch, Division of Facilities and Security (SB/DFS) (via e-mail) when a contractor employee no longer requires access authorization and return of any NRC issued badge to SB/DFS within three days after their termination.

(6) Ensure that all contractor employees that require access to classified Restricted Data or National Security Information or matter, access to sensitive unclassified information (Safeguards, Official Use Only, and Proprietary information) access to sensitive IT systems or data, unescorted access to NRC controlled buildings/space, or unescorted access to protected and vital areas of nuclear power plants receive approval of SB/DFS prior to access in accordance with Management Directive and Handbook 12.3.

(7) For contracts for the design, development, maintenance or operation of Privacy Act Systems of Records, obtain from the contractor as part of closeout procedures, written certification that the contractor has returned to NRC, transferred to the successor contractor, or destroyed at the end of the contract in accordance with instructions provided by the NRC Systems Manager for Privacy Act Systems of Records, all records (electronic or paper) which were created, compiled, obtained or maintained under the contract.

(End of Clause)

Page 11

31310020A0003/31310021F0007 H - Special Contract Requirements NRC Local Clauses Incorporated by Full Text H.1 GOVERNMENT FURNISHED EQUIPMENT/PROPERTY (a) The NRC will provide the contractor with the following items for use under this contract:

1. NRC Standard Laptops
2. []
3. []

Include an asterisk (*) if the item also applies to paragraph (b) below.

(b) The equipment/property listed below is hereby transferred from contract/agreement number:[], to contract/agreement number:[]:

1. []
2. []
3. []

(c) Only the equipment/property listed above in the quantities shown will be provided by the Government. The contractor shall be responsible and accountable for all Government property provided under this contract and shall comply with the provisions of the FAR Government Property Clause under this contract and FAR Subpart 45.5, as in effect on the date of this contract. The contractor shall investigate and provide written notification to the NRC Contracting Officer (CO) and the NRC Division of Facilities and Security, Physical Security Branch of all cases of loss, damage, or destruction of Government property in its possession or control not later than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after discovery. The contractor must report stolen Government property to the local police and a copy of the police report must be provided to the CO and to the Division of Facilities and Security, Office of Administration.

(d) All other equipment/property required in performance of the contract shall be furnished by the Contractor.

H.2 ANNUAL AND FINAL CONTRACTOR PERFORMANCE EVALUATIONS Annual and final evaluations of contractor performance under this contract will be prepared in accordance with FAR Subpart 42.15, "Contractor Performance Information," normally at or near the time the contractor is notified of the NRC's intent to exercise the contract option. If the multi-year contract does not have option years, then an annual evaluation will be prepared N/A (the Order will have options).. Final evaluations of contractor performance will be prepared at the expiration of the contract during the contract closeout process.

The Contracting Officer will transmit the NRC Contracting Officers Representatives (COR) annual and final contractor performance evaluations to the contractor's Project Manager, unless Page 12

31310020A0003/31310021F0007 otherwise instructed by the contractor. The contractor will be permitted thirty days to review the document and submit comments, rebutting statements, or additional information.

Where a contractor concurs with, or takes no exception to an annual performance evaluation, the Contracting Officer will consider such evaluation final and releasable for source selection purposes. Disagreements between the parties regarding a performance evaluation will be referred to an individual one level above the Contracting Officer, whose decision will be final.

The Contracting Officer will send a copy of the completed evaluation report, marked "Source Selection Information, to the contractor's Project Manager for their records as soon as practicable after it has been finalized. The completed evaluation report also will be used as a tool to improve communications between the NRC and the contractor and to improve contract performance.

The completed annual performance evaluation will be used to support future award decisions in accordance with FAR 42.1502 and 42.1503. During the period the information is being used to provide source selection information, the completed annual performance evaluation will be released to only two parties - the Federal government personnel performing the source selection evaluation and the contractor under evaluation if the contractor does not have a copy of the report already.

H.3 AWARD NOTIFICATION AND COMMITMENT OF PUBLIC FUNDS (a) All offerors will receive preaward and postaward notices in accordance with FAR 15.503.

(b) It is also brought to your attention that the contracting officer is the only individual who can legally obligate funds or commit the NRC to the expenditure of public funds in connection with this procurement. This means that unless provided in a contract document or specifically authorized by the contracting officer, NRC technical personnel may not issue contract modifications, give formal contractual commitments, or otherwise bind, commit, or obligate the NRC contractually. Informal unauthorized commitments, which do not obligate the NRC and do not entitle the contractor to payment, may include:

(1) Encouraging a potential contractor to incur costs prior to receiving a contract; (2) Requesting or requiring a contractor to make changes under a contract without formal contract modifications; (3) Encouraging a contractor to incur costs under a cost-reimbursable contract in excess of those costs contractually allowable; and (4) Committing the Government to a course of action with regard to a potential contract, contract change, claim, or dispute.

H.4 KEY PERSONNEL. (JAN 1993)

(a) The following individuals are considered to be essential to the successful performance of the work hereunder:

Page 13

31310020A0003/31310021F0007

  • The contractor agrees that personnel may not be removed from the contract work or replaced without compliance with paragraphs (b) and (c) of this section.

(b) If one or more of the key personnel, for whatever reason, becomes, or is expected to become, unavailable for work under this contract for a continuous period exceeding 30 work days, or is expected to devote substantially less effort to the work than indicated in the proposal or initially anticipated, the contractor shall immediately notify the contracting officer and shall, subject to the concurrence of the contracting officer, promptly replace the personnel with personnel of at least substantially equal ability and qualifications.

(c) Each request for approval of substitutions must be in writing and contain a detailed explanation of the circumstances necessitating the proposed substitutions. The request must also contain a complete resume for the proposed substitute and other information requested or needed by the contracting officer to evaluate the proposed substitution. The contracting officer and the project officer shall evaluate the contractor's request and the contracting officer shall promptly notify the contractor of his or her decision in writing.

(d) If the contracting officer determines that suitable and timely replacement of key personnel who have been reassigned, terminated, or have otherwise become unavailable for the contract work is not reasonably forthcoming, or that the resultant reduction of productive effort would be so substantial as to impair the successful completion of the contract or the service order, the contract may be terminated by the contracting officer for default or for the convenience of the Government, as appropriate. If the contracting officer finds the contractor at fault for the condition, the contract price or fixed fee may be equitably adjusted downward to compensate the Government for any resultant delay, loss, or damage.

NRCAR Clauses Incorporated By Full Text Page 14

31310020A0003/31310021F0007 I - Contract Clauses NRC Local Clauses Incorporated by Full Text FAR Clauses Incorporated By Reference 52.227-14 RIGHTS IN DATA-GENERAL. (MAY 2014) 52.237-3 CONTINUITY OF SERVICES. (JAN 1991)

FAR Clauses Incorporated By Full Text I.1 52.217-8 OPTION TO EXTEND SERVICES. (NOV 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 1 day of the expiration of the contract..

(End of clause)

I.2 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT. (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within any time prior to the expiration of the contract; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 1days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 8 years, 6 months.

(End of clause)

I.3 52.232-19 AVAILABILITY OF FUNDS FOR THE NEXT FISCAL YEAR. (APR 1984)

Funds are not presently available for performance under this contract beyond the term of the base period of performance. The Government's obligation for performance of this contract beyond that date is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise for performance under this contract beyond the obligated ceiling, until funds are made available to the Contracting Officer for performance and until the Contractor receives notice of availability, to be confirmed in writing by the Contracting Officer.

(End of clause)

Page 15

31310020A0003/31310021F0007 J - List of Documents, Exhibits and Other Attachments Number Attachment Title Date of Number Pages Performance Work Statement_NMSS 1 03/18/2021 60 IVV_STAQS_Final 2 PRS Final 03/18/2021 4 2 QASP_Final 03/18/2021 10 4 NMSS IVV Price Schedule xlsx 03/18/2021 1 Page 16