VIRGINIA ELECTRIC AND POWER CoMPANY RICHMOND, VIRGINIA 23261 March 10, 2021 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555 Gentlemen:

Serial No.21-096 NAPS/RAP Docket Nos. 50-338, 339 License Nos. NPF-4, NPF-7 VIRGINIA ELECTRIC AND POWER COMPANY {DOMINION ENERGY VIRGINIA)

NORTH ANNA POWER STATION UNITS 1* AND 2 CATEGORY 1 STRUCTURES - SETTLEMENT MONITORING PROCEDURE REVISION As required by Atomic Safety and Licensing Appeal Board Decision ALA~-578, this letter is to notify you that a revision has been made to periodic test procedure 0-PT-112, Category 1 Structures..: Settlement Monitoring, and 0-PT-115, Survey of Settlement Monitoring Points.

Periodic test procedures 0-PT-112 and 0-PT-115 were revised to *change the test frequency from 184 days to 12 months. The frequency for the associated i"echnical Requirements Manual Surveillance Requirements, TSR 3.7.7.1 and.TSR 3.7.7.2, were similarly changed.

If you have any. questio'ns, please contact Marcus A. Hofmann at (540) 894-2100.

Very truly yours, Fred Mladen Site Vice President Commitments made in this letter: None cc:

Regional Administrator United States Nuclear Regulatory Commission Region II Marquis O,ne Tower 2~5:.P,eachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 NRC Senior Resident Inspector North Anna Power Station

'