ML21022A200

From kanterella
Jump to navigation Jump to search
COVID-19 Lessons Learned and Best Practices Presentation for 1/27 ROP Public Meeting
ML21022A200
Person / Time
Issue date: 01/22/2021
From: Russell Gibbs
NRC/NRR/DRO/IRIB
To:
Russell Gibbs, NRR/DRO/IRSB, 415-8578
References
Download: ML21022A200 (11)


Text

Lessons Learned and Best Practices on Oversight of Operating Reactors During COVID-19 Public Health Emergency Russell Gibbs Office of Nuclear Reactor Regulation Division of Reactor Oversight 1

The Bottom Line Reasonable assurance of safe nuclear plant operation was achieved through satisfactory completion of inspection samples, on-site inspector presence and continued monitoring of licensee activities, and response to plant events.

2

=

Background===

  • NRC staff was required to perform extensive telework during the COVID-19 public health emergency.
  • Resident inspectors were expected to be on-site about every three business days.
  • Some inspections were either not performed or delayed due to COVID-19 restrictions.
  • Initial reactor operator exams restarted to ensure a pipeline of reactor operators.
  • Goal established to complete the minimum number of inspection samples.
  • NRC inspectors and examiners worked with licensees to ensure their personnel safety.

3

Scope/Methodology

  • Lessons learned effort focused on oversight of operating reactors and related support functions.
  • A 24-question survey was developed to identify lessons learned and best practices (March - July 2020).
  • A second survey was sent to all senior resident inspectors on IT capability.
  • Interviews were conducted with NRC Office Directors (NRR, NSIR) and Regional Administrators.

4

Recommendations Overview

  • Improve implementation of oversight during COVID public health emergency.
  • Ensure oversight program is adequately prepared for future emergencies.
  • Identify processes and actions taken during the COVID-19 PHE that can be used during normal operations to enable the NRC to become a more modern, risk-informed regulator.

Recommendations are under consideration with no decisions made 5

Near Term Recommendations IT Capability and Reliability

  • Formalize agreements with licensees to ensure inspectors have continued access to plant information.
  • Provide second computer monitor to staff.
  • Continue to educate staff and licensees about the capabilities and benefits of available IT tools.

Inspection Guidance Enhancements

  • Consider revisions to inspection procedures or guidance to indicate activities and inspection requirements can be performed either fully remotely, partially remotely, or onsite.

6

Long Term Recommendations IT Capability and Reliability

  • Improve remote access to Safeguards Information for security inspectors and designated HQ staff.

Remote Inspection Practices

  • Expand use of remote work practices for resident inspectors.
  • Evaluate the current team inspection framework to determine if changes should be made to improve efficiency and effectiveness.

Inspection Guidance Enhancements

  • Revise ROP program documents to include best practices and guidance developed since the COVID-19 PHE began.

7

Select Best Practices

  • Conducting townhalls and inspector seminars
  • Developing dashboards to monitor local and site conditions
  • Using internal information exchanges through MS SharePoint
  • Using direct lines of communication with licensee staff
  • Alternating onsite presence for team inspections
  • Using personally owned vehicles and traveling alone
  • Scheduling routine, and often daily, communications with licensees 8

Other Perspectives Summarized

  • Report relies too heavily on survey results.
  • Lessons learned should only be applied to future emergencies - not normal conditions.
  • Immediate action should be taken to expand telework for inspectors.
  • Survey questions should have focused on inspection activities that could be performed remotely versus how many hours per week inspectors telework.
  • Use of the term remote inspection causes concern for some.
  • Evaluate versus expand the routine use of telework for inspectors.

9

Next Steps

  • Coordinate results with NRC COVID-19 Coordination Team.
  • Determine which recommendations will be accepted and acted upon with focus on near-term actions.
  • Seek feedback from with industry and public to finalize approaches.
  • Evaluate effectiveness of actions taken for both emergency and non-emergency conditions (after implementation and appropriate run-time).

10

Conclusions NRC oversight of operating reactors during the COVID-19 PHE was appropriate, mostly as a result of the NRC staff and managements ability to adapt to telework and the challenges the PHE presented.

NRC inspectors, staff, and management learned a great deal in a short time and the lessons learned and best practices identified should prove highly beneficial for future emergencies that limit or prevent access to nuclear plant sites.

11