31310020D0003/31310020F0101 Page 2 Section B - Supplies or Services/Prices was revised as follows.
Summary of Clause Changes:
Clause titled CONSIDERATION AND OBLIGATIONCOST-PLUS-FIXED-FEE ALTERNATE I is incorporated as follows:
CONSIDERATION AND OBLIGATIONCOST-PLUS-FIXED-FEE ALTERNATE I (a) The total estimated cost to the Government for full performance of this contract is
$1,913,447 of which the sum of represents the estimated reimbursable costs, and of which represents the fixed-fee.
(b) There shall be no adjustment in the amount of the Contractor's fixed fee.
(c) The amount currently obligated by the Government with respect to this contract is of which the sum of represents the estimated reimbursable costs, and of which represents the fixed-fee.
(d) It is estimated that the amount currently obligated will cover performance through 01/31/2021.
(e) This is an incrementally-funded contract and FAR 52.232 Limitation of Funds applies.
(f) In accordance with FAR 52.216 Fixed Fee, it is the policy of the NRC to withhold payment of fee after payment of 85 percent of the fee has been paid in order to protect the Governments interest. The amount of fixed-fee withheld from the contractor will not exceed 15 percent of the total fee or $100,000, whichever is less. Accordingly, the maximum amount of fixed-fee that may be held in reserve is Clause titled PRICE/COST SCHEDULE is incorporated as follows:
PRICE/COST SCHEDULE
31310020D0003/31310020F0101 Page 3 Section J - List of Documents, Exhibits and Other Attachments was revised as follows.
1 - List of Documents, Exhibits and Other Attachments was added and reads as follows.
Attachment Number Title Date 1
NRC FORM 187 12/21/2020