MONTHYEARML23216A0362023-08-0707 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23079A2262023-03-20020 March 2023 Form 5.1-1 Post-Examination Check Sheet (Quad Cities, 2023) IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 ML23079A2222023-02-21021 February 2023 Form 2.1-1 Examination Preparation Checklist ML23079A2192023-02-21021 February 2023 Form 1.3-1 Exam Security Agreement SVP-23-007, Licensee Post-Exam Submittal Letter (SVP-23-007, Quad Cities, 2023)2023-02-0909 February 2023 Licensee Post-Exam Submittal Letter (SVP-23-007, Quad Cities, 2023) ML23079A2282023-02-0808 February 2023 Post-Exam Review Comments (None) ML23020A4132023-01-23023 January 2023 Operator License Examination Approval - Quad Cities Nuclear Power Station, January 2023 ML23079A2072023-01-13013 January 2023 Form 2.3-4 Written Examination Quality Checklist (Quad Cities, 2023) ML23079A2042023-01-13013 January 2023 Form 2.3-2 Operating Test Quality Checklist (Quad Cities, 2023) ML23079A2032022-11-11011 November 2022 Licensee Proposed Exam Cover Letter (SVP-22-065, Quad Cities, 2023) ML23079A0842022-10-17017 October 2022 Form 3.4-1 Events and Evolutions Checklist (Quad Cities, 2023) ML23079A0432022-10-17017 October 2022 Form 2.3-1 Examination Outline Quality Checklist (Quad Cities, 2023).pdf ML23079A0272022-10-0505 October 2022 Licensee Outline Submittal Email (Quad Cities, 2023) ML22188A1752022-07-11011 July 2022 Confirmation of Initial License Examination RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21281A1242021-10-0808 October 2021 GFE Results, September 2021 IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 ML22192A2062021-07-0909 July 2021 2021 QC Ile Outline Submittal Comments ML22192A2052021-07-0909 July 2021 2021 QC Ile ES-401-9 Written Examination Review Worksheet-Final ML22192A2032021-07-0909 July 2021 2021 QC Ile ES-301-7 Operating Test Review Worksheet-Final ML22192A1922021-07-0909 July 2021 2021 QC Ile ES-201-1 ML22192A1932021-07-0909 July 2021 2021 QC Ile ES-201-3 Security Agreement-Final ML22192A1952021-07-0909 July 2021 2021 QC Ile ES-403-1 Written Exam Quality Checklist ML22192A2042021-07-0909 July 2021 2021 QC Ile ES-401-4 Rejected KAs ML22192A1962021-06-22022 June 2021 2021 QC Ile Post-Exam Submittal Letter-06-22-2021 ML22193A2862021-06-14014 June 2021 2021 QC Ile Administered RO and SRO Written Exam-Final ML22193A2872021-06-14014 June 2021 2021 QC Ile Administered RO and SRO List of Reference Handouts-Final ML22193A0932021-06-14014 June 2021 2021 QC Ile Administered RO and SRO Admin JPMs-Final ML22193A1072021-06-14014 June 2021 2021 QC Ile Administered Simulator Scenarios-Final ML22193A1052021-06-14014 June 2021 2021 QC Ile Administered Simulator and Inplant JPMs-Final ML21152A1022021-06-0202 June 2021 Operator Licensing Examination Approval ML22193A3112021-05-0505 May 2021 2021 QC Ile Proposed Simulator Scenarios ML22193A3102021-05-0505 May 2021 2021 QC Ile Proposed Simulator and Inplant JPMs ML22193A3012021-05-0505 May 2021 2021 QC Ile ES-301-6 Competencies Checklist ML22193A3082021-05-0505 May 2021 2021 QC Ile Proposed RO and SRO Admin JPMs ML22193A3002021-05-0505 May 2021 2021 QC Ile ES-301-4 Simulator Scenario Quality Checklist ML22193A3032021-05-0505 May 2021 2021 QC Ile ES-401-6 Written Exam Quality Checklist ML22193A2992021-05-0505 May 2021 2021 QC Ile ES-301-3 Operating Test Quality Checklist ML22193A3122021-05-0505 May 2021 2021 QC Ile Proposed Written Exam-RO and SRO ML22193A3222021-04-0707 April 2021 2021 Quad-Cities Ile ES-D-1 Scenario Outlines ML22193A3202021-04-0707 April 2021 2021 Quad-Cities Ile ES-301-2 RO and SRO Sim-Inplant Systems Outlines ML22193A3142021-04-0707 April 2021 2021 Quad-Cities Ile ES-201-2 Outline Quality Checklist ML22193A3192021-04-0707 April 2021 2021 Quad-Cities Ile ES-301-1 RO and SRO Admin Topics Outlines 2023-08-07
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23216A0362023-08-0707 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23079A2262023-03-20020 March 2023 Form 5.1-1 Post-Examination Check Sheet (Quad Cities, 2023) IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 ML23079A2192023-02-21021 February 2023 Form 1.3-1 Exam Security Agreement ML23079A2222023-02-21021 February 2023 Form 2.1-1 Examination Preparation Checklist SVP-23-007, Licensee Post-Exam Submittal Letter (SVP-23-007, Quad Cities, 2023)2023-02-0909 February 2023 Licensee Post-Exam Submittal Letter (SVP-23-007, Quad Cities, 2023) ML23079A2282023-02-0808 February 2023 Post-Exam Review Comments (None) ML23020A4132023-01-23023 January 2023 Operator License Examination Approval - Quad Cities Nuclear Power Station, January 2023 ML23079A2072023-01-13013 January 2023 Form 2.3-4 Written Examination Quality Checklist (Quad Cities, 2023) ML23079A2042023-01-13013 January 2023 Form 2.3-2 Operating Test Quality Checklist (Quad Cities, 2023) ML23079A2032022-11-11011 November 2022 Licensee Proposed Exam Cover Letter (SVP-22-065, Quad Cities, 2023) ML23079A0842022-10-17017 October 2022 Form 3.4-1 Events and Evolutions Checklist (Quad Cities, 2023) ML23079A0432022-10-17017 October 2022 Form 2.3-1 Examination Outline Quality Checklist (Quad Cities, 2023).pdf ML23079A0272022-10-0505 October 2022 Licensee Outline Submittal Email (Quad Cities, 2023) ML22188A1752022-07-11011 July 2022 Confirmation of Initial License Examination RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 ML22192A1952021-07-0909 July 2021 2021 QC Ile ES-403-1 Written Exam Quality Checklist ML22192A2032021-07-0909 July 2021 2021 QC Ile ES-301-7 Operating Test Review Worksheet-Final ML22192A1932021-07-0909 July 2021 2021 QC Ile ES-201-3 Security Agreement-Final ML22192A2052021-07-0909 July 2021 2021 QC Ile ES-401-9 Written Examination Review Worksheet-Final ML22192A2062021-07-0909 July 2021 2021 QC Ile Outline Submittal Comments ML22192A2042021-07-0909 July 2021 2021 QC Ile ES-401-4 Rejected KAs ML22192A1922021-07-0909 July 2021 2021 QC Ile ES-201-1 ML22192A1962021-06-22022 June 2021 2021 QC Ile Post-Exam Submittal Letter-06-22-2021 ML22193A1052021-06-14014 June 2021 2021 QC Ile Administered Simulator and Inplant JPMs-Final ML22193A2862021-06-14014 June 2021 2021 QC Ile Administered RO and SRO Written Exam-Final ML22193A2872021-06-14014 June 2021 2021 QC Ile Administered RO and SRO List of Reference Handouts-Final ML22193A0932021-06-14014 June 2021 2021 QC Ile Administered RO and SRO Admin JPMs-Final ML22193A1072021-06-14014 June 2021 2021 QC Ile Administered Simulator Scenarios-Final ML21152A1022021-06-0202 June 2021 Operator Licensing Examination Approval ML22193A2992021-05-0505 May 2021 2021 QC Ile ES-301-3 Operating Test Quality Checklist ML22193A3082021-05-0505 May 2021 2021 QC Ile Proposed RO and SRO Admin JPMs ML22193A3032021-05-0505 May 2021 2021 QC Ile ES-401-6 Written Exam Quality Checklist ML22193A3102021-05-0505 May 2021 2021 QC Ile Proposed Simulator and Inplant JPMs ML22193A3122021-05-0505 May 2021 2021 QC Ile Proposed Written Exam-RO and SRO ML22193A3002021-05-0505 May 2021 2021 QC Ile ES-301-4 Simulator Scenario Quality Checklist ML22193A3012021-05-0505 May 2021 2021 QC Ile ES-301-6 Competencies Checklist ML22193A3112021-05-0505 May 2021 2021 QC Ile Proposed Simulator Scenarios ML22193A3202021-04-0707 April 2021 2021 Quad-Cities Ile ES-301-2 RO and SRO Sim-Inplant Systems Outlines ML22193A3142021-04-0707 April 2021 2021 Quad-Cities Ile ES-201-2 Outline Quality Checklist ML22193A3162021-04-0707 April 2021 2021 Quad-Cities Ile ES-301-5 Transient and Event Checklists ML22193A3192021-04-0707 April 2021 2021 Quad-Cities Ile ES-301-1 RO and SRO Admin Topics Outlines ML22193A3222021-04-0707 April 2021 2021 Quad-Cities Ile ES-D-1 Scenario Outlines ML22193A3212021-04-0707 April 2021 2021 Quad-Cities Ile ES-401-1 and ES-401-3 2023-08-07
[Table view] |
Text
December 16, 2020 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2CONFIRMATION OF INITIAL LICENSE EXAMINATION
Dear Mr. Hanson:
In a telephone conversation on December 15, 2020, between Mr. R. Baker, Senior Operations Engineer, and Mr. A. Overbo, Initial License Training Exam Author, arrangements were made for the administration of operator licensing examinations at the Quad Cities Nuclear Power Station, Units 1 and 2 during the weeks of May 31 and June 7, 2021. In addition, the U.S. Nuclear Regulatory Commission (NRC) currently plans to make an examination validation visit to your facility the week of May 10, 2021.
As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 11 of NUREG-1021, Operator Licensing Examination Standards for Power Reactors. The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered.
To meet the above schedule, your staff agreed to provide the operating test outlines by January 19, 2020. The NRC staff provided the written examination outlines to Mr. J. Gangwish on September 10, 2020. The written examinations, operating tests, and supporting reference materials identified in Attachment 3 to ES-201, will be due by March 19, 2020. Pursuant to Title 10 of the Code of Federal Regulations, Part 55.40(b)(3), an authorized representative of the facility licensee shall approve the examinations and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or Safeguards Information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be canceled or rescheduled.
To conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests, along with any video/audio recordings of the dynamic operating tests, until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.
B. Hanson Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) Approval Number 3150-0090)), at least 60 days before the first examination date (if possible). Contact Mr. R. Baker to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB Approval Number 3150-0090) and medical certifications (OMB Approval Number 3150-0024) should be submitted at least 30 days before the first examination date. If the preliminary applications are not received at least 30 days before the examination date, a postponement may be necessary. Final signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.
Although the guidelines for receiving waiver or excusal requests is coincident with receipt of the operator license applications and medical certifications (30 days before the first examination date (preliminary) and 14 days before the first examination date (final)), the requests should be submitted as early possible in the process (see 60-day guideline above). Resolutions resulting from verbal inquiries by the licensees to the NRC are not binding. Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form 398, Personal Qualifications StatementLicensee, or as directed by Mr. R. Baker, when contacting him to determine the method of submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.
Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, Approval Number 3150-0018.
The burden to the public for these voluntary information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination or response, including the time for reviewing instructions, searching extra data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. You may submit comments on any aspect of the information collections, including suggestions for reducing the burden, to Freedom of Information Act, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by electronic mail to infocollects.resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless the document requesting or requiring the collection displays a currently valid OMB Control Number.
B. Hanson This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections, Exemptions, Requests for Withholding.
Thank you for your cooperation in this matter. Mr. A. Overbo has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact Mr. R. Baker, at 630-829-9871, or me at 630-829-9868.
Sincerely, Patricia Digitally signed by Patricia J. Pelke J. Pelke Date: 2020.12.16 10:53:36 -06'00' Patricia J. Pelke, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254; 50-265 License Nos. DPR-29; DPR-30 cc: Distribution via LISTSERV D. Fuson, Training Director
B. Hanson Letter to Bryan C. Hanson from Patricia J. Pelke dated December 16, 2020.
SUBJECT:
QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2CONFIRMATION OF INITIAL LICENSE EXAMINATION DISTRIBUTION:
Jessie Quichocho Richard Skokowski RidsNrrDorlLpl3 RidsNrrPMQuadCities Resource RidsNrrDroIrib Resource John Giessner Kenneth OBrien Jamnes Cameron Allan Barker DRPIII DRSIII Ikeda Betts Colleen Schmidt ADAMS Accession Number: ML20350B816 OFFICE RIII/DRS/OB/CE RIII/DRS/OB/CE RIII/DRS/OB/BC UnderInstruction NAME BBartlett:jw blb RBaker: RDB PPelke: PJP DATE 12/16/20 12/16/20 12/16/20 OFFICIAL RECORD COPY