MONTHYEARCP-202400424, (Cpnpp), Core Operating Limits Report (Colr), Unit 2 Cycle 22, (ERX-24-001, Revision 0)2024-11-0404 November 2024 (Cpnpp), Core Operating Limits Report (Colr), Unit 2 Cycle 22, (ERX-24-001, Revision 0) IR 05000445/20240032024-10-30030 October 2024 Integrated Inspection Report 05000445/2024003 and 05000446/2024003 IR 05000445/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000445/2024404 and 05000446/2024404 (Public) IR 07200074/20244012024-10-10010 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200074/2024401 Public 05000445/LER-2024-002-01, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions2024-10-0303 October 2024 Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions 05000446/LER-2024-001-01, Unit Two, Recurring Reactor Scrams Associated with Main Feedwater System Modifications2024-09-30030 September 2024 Unit Two, Recurring Reactor Scrams Associated with Main Feedwater System Modifications CP-202400335, License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel2024-09-12012 September 2024 License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel ML24031A6322024-09-11011 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4), Final Safety Analysis Report Update Schedule (EPID L-2023-LLE-0023) - Letter ML24243A0152024-09-0303 September 2024 – Notification of Comprehensive Engineering Team Inspection (05000445/2025012 and 05000446/2025012) and Request for Information ML24194A1332024-08-28028 August 2024 Issuance of Amendment Nos. 190 and 190, Respectively, Revision to Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24228A2252024-08-22022 August 2024 Relief to Use Later Code Edition for Inservice Inspection Program ML24179A0772024-08-20020 August 2024 Issuance of Amendment Nos. 189 and 189, Respectively, Extension of Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24232A2412024-08-19019 August 2024 Information Request, ISFSI Security IR 2024401 ML24232A2262024-08-19019 August 2024 Information Request, Security IR 2024404 IR 05000445/20240052024-08-15015 August 2024 Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2024005 and 05000446/2024005) CP-202400294, (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202400319, (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-13013 August 2024 (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality ML24177A2692024-08-0707 August 2024 Issuance of Amendment Nos. 188 and 188, Respectively, Revision to Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program CP-202400315, (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-0505 August 2024 (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality IR 05000445/20240022024-07-31031 July 2024 Units 1 and 2 - Integrated Inspection Report 05000445/2024002 and 05000446/2024002,and Independent Spent Fuel Storage Installation Inspection Report 07200074/2024001 IR 05000445/20244032024-07-16016 July 2024 Security Baseline Inspection Report 05000445/2024403 and 05000446/2024403 (Full Report) ML24187A0372024-07-15015 July 2024 Withdrawal of Requested Licensing Action Exemption from Select Requirements of 10 CFR Part 55, Operators Licenses ML24192A1862024-07-10010 July 2024 Notification of Inspection (NRC Inspection Report 05000445/2024003 and 05000446/2024003) and Request for Information ML24185A1382024-07-0202 July 2024 Inservice Inspection Request for Information CP-202400253, (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 52024-06-26026 June 2024 (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 5 IR 05000445/20244012024-06-26026 June 2024 MC&A Program Inspection Report 05000445-2024401 and 05000446-2024401 Public-Final CP-202400235, (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 02024-06-18018 June 2024 (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 0 IR 05000445/20240122024-06-17017 June 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000445/2024012 and 05000446/2024012 ML24120A3632024-06-10010 June 2024 Issuance of Amendment Nos. 187 and 187, Respectively Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants 05000445/LER-1924-002, (Cpnpp), Unit 1, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions2024-06-0303 June 2024 (Cpnpp), Unit 1, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions CP-202400205, (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval2024-05-30030 May 2024 (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval CP-202400175, (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator2024-05-16016 May 2024 (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator 05000446/LER-2024-001, (Cpnpp), Unit 2, Two Recurring Reactor Scrams Associated with Main Feedwater System Modifications2024-05-13013 May 2024 (Cpnpp), Unit 2, Two Recurring Reactor Scrams Associated with Main Feedwater System Modifications 05000445/LER-2024-001, Re Potential Loss of Safety Function Due to Inoperability of Both Trains of Uninterruptible Power Supply Heating, Ventilation & Air Conditioning2024-05-0606 May 2024 Re Potential Loss of Safety Function Due to Inoperability of Both Trains of Uninterruptible Power Supply Heating, Ventilation & Air Conditioning ML24120A3032024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-SpottedBird, L, Kiowa Indian Tribe ML24120A2912024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Cooper, D, Apache Tribe of Oklahoma ML24120A2902024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Bunch, J, United Keetoowah Band of Cherokee Indians CP-202400153, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2024-04-29029 April 2024 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters ML24120A3042024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Sylestine, R, Alabama-Coushatta Tribe of Texas ML24107B1012024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Cernek, J, Coushatta Tribe of Louisiana ML24120A3022024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Pierite, M, Tunica-Biloxi Tribe of Louisiana ML24120A2922024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Dotson, Delaware Nation ML24120A3052024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Woommavovah, M, Comanche Nation ML24120A2952024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Johnson, L.J., Seminole Nation of Oklahoma ML24120A3072024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Yargee, W, Alabama-Quassarte Tribal Town ML24120A2932024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Garza, Jr, Juan, Kickapoo Traditional Tribe of Texas ML24120A3002024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Morrow, R K, Thlopthlocco Tribal Town ML24120A2942024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Gonzalez, B, Caddo Nation ML24120A3012024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Parton, T, Wichita and Affiliated Tribes ML24120A2972024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Martin, R, Tonkawa Tribe of Oklahoma 2024-09-30
[Table view] Category:License-General License Notification
MONTHYEARML20350B8122020-12-11011 December 2020 CP2021301-Corp Notification Ltr-jck, Comanche Peak Nuclear Power Plant - Notification of NRC Initial Operator Licensing Examination 05000445/2021301 and 05000446/2021301 2020-12-11
[Table view] |
See also: IR 05000445/2021301
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD
ARLINGTON, TX 76011-4511
December 11, 2020
Mr. Ken Peters
Senior Vice President and Chief Nuclear Officer
Attention: Regulatory Affairs
Vistra Operations Company LLC
P.O. Box 1002
Glen Rose, TX 76043
SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT -NOTIFICATION OF NRC
INITIAL OPERATOR LICENSING EXAMINATION 05000445/2021301 AND
05000446/2021301
Dear Mr. Peters:
In a telephone conversation on November 19, 2020 between Mr. Jordan Ruby, Examination and
Simulator Supervisor and Mr. John Kirkland, Chief Examiner, arrangements were made for the
administration of operator licensing examinations at Comanche Peak Nuclear Power Plant
during the week of August 9, 2021.
As agreed during the telephone conversation, your staff will prepare the examinations based on
the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power
Reactors, Revision 11. The NRCs regional office will discuss with your staff any changes that
might be necessary before the examinations are administered.
To meet the above schedule, it will be necessary for your staff to furnish the operating test
outlines by March 8, 2021. The written examination outline was provided to your staff on
November 19, 2020. The written examinations, operating tests, and supporting reference
materials identified in Attachment 3 to ES-201 will be due by May 24, 2021. Pursuant to Title
10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the examinations, and tests before they are
submitted to the NRC for review and approval. All materials shall be complete and ready-to-
use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Delays in
receiving the required materials, or the submittal of inadequate or incomplete materials, may
cause the examinations to be cancelled or rescheduled. In addition, your support for on-site
validation of the examinations is required during the week of July 5, 2021.
To conduct the requested written examinations and operating tests, it will be necessary for your
staff to provide adequate space and accommodations in accordance with ES-402, and to make
the simulation facility available on the dates noted above. In accordance with ES-302, your staff
K. Peters 2
should retain the original simulator performance data (e.g., system pressures, temperatures,
and levels) generated during the dynamic operating tests along with any video and audio
recordings of the dynamic operating tests until the NRC takes its licensing action on all of the
applications and any adjudicatory actions on any hearing demands are complete. Appendix E
to NUREG-1021 contains NRC policies and guidelines that will be in effect while the written
examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator waiver or excusal requests (if any) (Office of Management
and Budget (OMB) approval number 3150-0090) at least 60 days before the first examination
date (if able). Mr. Kirkland, Chief Examiner, should be contacted to determine the method for
submission of the waiver and/or excusal requests. Preliminary reactor operator and senior
reactor operator license applications (OMB approval number 3150-0090) and, medical
certifications (OMB approval number 3150-0024) should be submitted at least 30 days before
the first examination date. If the preliminary applications are not received at least 30 days
before the examination date, a postponement may be necessary. Final, signed applications
certifying that all training has been completed and requesting any waivers or excusals, as
applicable, should be submitted at least 14 days before the first examination date.
Although the minimum guidelines for receiving waiver or excusal requests is 30 days before the
first examination date (preliminary) and 14 days before the first examination date (final), the
requests should be submitted as early in the process as possible (see the 60-day guideline,
above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding.
Submittals addressing waivers and/or excusals should be in writing (i.e., on NRC Form 398, or
as directed when Mr. Kirkland is contacted to determine the method for submission). The
NRCs final decision on whether to grant a waiver or excusal will be documented on the final
(not preliminary) NRC Form 398 submitted for the applicant and will not be provided until the
final application is submitted to the NRC.
Paperwork Reduction Act Statement
This letter contains mandatory information collections that are subject to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)
approved these information collections (approval number 3150-0011). Send comments
regarding this information collection to the Information Services Branch, Office of the Chief
Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office
of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and
Budget, Washington, DC 20503.
The burden to the public for these mandatory information collections is estimated to average
400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> per examination including the time for reviewing instructions, searching existing data
sources, gathering and maintaining the data needed, and completing and reviewing the
information collection. You may submit comments on any aspect of the information collection,
including suggestions for reducing the burden, to the FOIA, Privacy and Information Collections
Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by
electronic mail to INFOCOLLECTS.RESOURCE@NRC.GOV; and to the Desk Officer, Office of
Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and
Budget, Washington, DC 20503.
K. Peters 3
Public Protection Notification
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request
for information or an information collection requirement unless the requesting document
displays a currently valid OMB control number.
This letter will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Thank you for your cooperation in this matter. Mr. Ruby has been advised of the policies and
guidelines referenced in this letter. If you have any questions regarding the NRCs examination
procedures and guidelines, please contact me at 817-200-????.
Sincerely,
/RA/
John Kirkland, Chief Examiner
Operations Branch
Division of Reactor Safety
Dockets: 50-445; 50-446
Licenses: NPF-87; NPF-89
ML20350B812
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: JKirkland Yes No Publicly Available Sensitive NRC-002
OFFICE SOE:OB
NAME JKirkland
SIGNATURE /RA/
DATE 12/11/20