Category 3 Public Meeting Summary Replacement Energy Cost Estimates for Nuclear Power Plants: 2020-2030
ML20336A181
Person / Time
Issue date: 11/30/2020
From: Pamela Noto
NRC/NMSS/DREFS/RASB
To:
Noto, Pamela
References
20201293
Download: ML20336A181 (3)


Text

U.S. Nuclear Regulatory Commission Public Meeting Summary November 30, 2020

Title:

Replacement Energy Cost Estimates for Nuclear Power Plants: 2020-2030 Meeting Identifier: 20201293 Date: November 18, 2020 Location: Webinar and Teleconference Category: Category 3 Purpose of the Meeting: To present updated information on replacement energy forecasts for short-and long-term shutdowns of U.S. nuclear electricity generating units to facilitate public comment on a draft NUREG for forecasting replacement energy costs.

General Details: The meeting was attended by 12 members of the public and 13 members of Nuclear Regulatory Commission (NRC) staff via Webinar and/or teleconference.

Summary of Presentation: The NRC staff presented the modeling approach, including the assumptions and methodology, that were used to forecast replacement energy costs for nuclear power plant outages within the U.S. The staff also presented an example of the results of the replacement energy cost estimates and provided an opportunity for the public to ask questions.

Summary of Public Feedback: No questions or feedback were received during the meeting.

Action Items/Next Steps:

The Federal Register notice requesting formal comment on draft NUREG-2242, Replacement Energy Cost Estimates for Nuclear Power Plants:2020-2030, will be issued by the end of the calendar year. The NRC staff will review and evaluate formal comments received on the draft NUREG to inform the development of the final NUREG for Commission review and approval.

Additional Information:

Meeting notice and agenda: ADAMS Accession No. ML20307A345 NRC staff presentation: ADAMS Accession No. ML20322A003 Predecisional - draft NUREG-2242: ADAMS Accession No. ML20304A556

Summary ML20336A181

  • concurrence via e-mail OFFICE NMSS/REFS/RASB RES/DRA/AAB NMSS/REFS/RASB/TL NMSS/REFS/RASB NAME PNoto*

ASharp*

FSchofer*

CBladey*

DATE 11/18/2020 11/18/2020 11/18/2020 11/30/2020

Enclosure MEETING ATTENDANCE PUBLIC MEETING ON REPLACEMENT ENERGY COST ESTIMATES FOR NUCLEAR POWER PLANTS: 2020-2030 WEBINAR WEDNESDAY, NOVEMBER 18, 2020; 9:00 A.M. - 11:00A.M. (EASTERN DAYLIGHT TIME)

Name Affiliation Pamela Noto NRC Amy Sharp NRC Fred Schofer NRC Glenna Lappert NRC Kevin Coyne NRC Antonio Gomez NRC Jill Shepherd NRC Tina Ghosh NRC Tamara Bloomer NRC Jeff Rikhoff NRC Donald Palmrose NRC Christina England NRC Aaron Sanders NRC Jana Bergman Curtiss-Wright John Conly Certrec Corp Juanita Haydel ICF Kenneth Collison ICF Lisa Matis Tetra Tech Russell Thompson TVA Shane Grotewiel Ameren Victoria Dennis TVA Shane Goodwill Cameron Robert Sweeney IBEX Edward Davis Pegasus Jonathan Johnson TVA