MONTHYEARML20304A3152020-10-28028 October 2020 Self-report of a Violation of Reed Research Reactor'S Requalification Plan Project stage: Request ML21014A4372020-10-28028 October 2020 Reed College - Financial Assurance for Reed Institute Dba Reed College and Financial Statements for the Reed Institute June 30, 2020 and 2011 9 Project stage: Request ML21160A1792021-06-0808 June 2021 Reed College, Submitting Information Inadvertently Omitted from Letter Dated October 28, 2020 (ML21014A437) Project stage: Request ML21258A3962021-10-0404 October 2021 U. S. Nuclear Regulatory Commission Staff Review Re Reed College 2020 Financial Test for Self-Guarantee for Decommission Funding NRC Ltr Rrr 2020 Financial Self Guarantee Draft Project stage: Draft Approval 2021-10-04
[Table View] |
|
---|
Category:Letter
MONTHYEARML24018A0862024-02-0101 February 2024 Examination Confirmation Letter No. 50-288/Ol-24-02, Reed College ML24017A0312024-01-18018 January 2024 Reed College, Examination Confirmation Letter 50-288/Ol-24-01 ML23289A1562023-10-25025 October 2023 Reed College 2022 Financial Test for Self-Guarantee for Decommissioning Funding ML23263B1622023-09-20020 September 2023 Reed Research Reactor 2022-2023 Annual Report ML23163A0132023-07-18018 July 2023 Examination Result Letter No. 50-288/OL-23-03, Reed College ML23163A0122023-07-18018 July 2023 Examination Report Letter No. 50-288/OL-23-03, Reed College ML23165A2312023-06-14014 June 2023 Reed Research Reactor (Docket No. 50-288/License No. R-112) 2022 Financial Assurance Update ML23139A1322023-05-16016 May 2023 Reed Research Reactor (Docket No. 50-288/License No. R-112) 2022 Financial Assurance ML23053A2402023-03-0606 March 2023 Examination Confirmation Letter No. 50-288/OL-23-03, Reed College ML23024A1732023-02-27027 February 2023 Examination Confirmation Letter No. 50-288/OL-23-02, Reed College ML23020A9372023-01-20020 January 2023 Reed College, Letter Intended to Fulfill the 14-day Written Report Requirement of Technical Specification 6.7.2, Special Reports, Following Operation in Violation of Limiting Conditions of Operation ML22241A1382022-09-0606 September 2022 Us Nuclear Regulatory Commission Staff Review Re Reed College 2021 Financial Test for Self-Guarantee for Decommissioning Funding ML22230B8022022-08-18018 August 2022 Annual Report for Reed College (Docket 50-288, License No. R-112) for the Period July 1, 2021 Through June 30, 2022 ML22229A5632022-08-17017 August 2022 Reed Research Reactor 2021-2022 Annual Report ML22199A2932022-07-28028 July 2022 Examination Confirmation Letter No. 50-288. OL-23-01, Reed College IR 05000288/20222022022-06-15015 June 2022 Reed College - U.S. Nuclear Regulatory Commission Routine Safety Inspection Report No. 05000288/2022202 IR 05000288/20222012022-06-14014 June 2022 Cover Letter - Reed College Nuclear Regulatory Commission Inspection Report No. 05000288/2022201 (Public) ML22019A1022022-02-0707 February 2022 Examination Confirmation Letter No. 50-288/OL-22-02, Reed College ML21258A3962021-10-0404 October 2021 U. S. Nuclear Regulatory Commission Staff Review Re Reed College 2020 Financial Test for Self-Guarantee for Decommission Funding NRC Ltr Rrr 2020 Financial Self Guarantee Draft ML21242A2362021-09-0808 September 2021 Reed College Regarding U.S. Nuclear Regulatory Commission Staff Review and Approval of the Revised Reed Research Reactor Requalification Plan ML21224A2032021-08-16016 August 2021 Examination Confirmation Letter No. 50-288/OL-22-01, Reed College ML21216A4392021-08-0404 August 2021 Reed College - Reed Research Reactor, Annual Report, July 1, 2020 - June 30, 2021 ML21174A1942021-06-23023 June 2021 Revised Reed Research Reactor Requalification Plan in ML21160A1792021-06-0808 June 2021 Reed College, Submitting Information Inadvertently Omitted from Letter Dated October 28, 2020 (ML21014A437) ML21202A1792021-06-0808 June 2021 Reed College - Submitting Information Inadvertently Omitted from Letter Dated October 28, 2020 (ML21014A437) IR 05000288/20212012021-06-0303 June 2021 Reed College U.S. Nuclear Regulatory Commission Routine Safety Inspection Report 05000288/2021201 ML21028A0922021-01-27027 January 2021 Examination Confirmation Letter No. 50-288/OL-21-02, Reed College ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20304A3152020-10-28028 October 2020 Self-report of a Violation of Reed Research Reactor'S Requalification Plan ML21014A4372020-10-28028 October 2020 Reed College - Financial Assurance for Reed Institute Dba Reed College and Financial Statements for the Reed Institute June 30, 2020 and 2011 9 ML20290A6802020-10-27027 October 2020 U.S. Nuclear Regulatory Commission Staff Review Reed College 2019 Financial Assurance (Self-Guarantee)(EPID No. L-2019-LLL-0034 ML20265A3972020-09-21021 September 2020 Reed College - Response to Notice of Violation 05000288/2020201 ML20266G5442020-09-21021 September 2020 Reed College - Change of Management Staff ML20247J6032020-09-0303 September 2020 Examination Confirmation Letter No. 50-288/OL-21-001, Reed College IR 05000288/20202012020-09-0202 September 2020 Reed College - U.S. Nuclear Regulatory Commission Routine and Confirmatory Order Follow-Up Inspection Report No. 05000288/2020201 ML20216A6772020-08-0303 August 2020 Reed Research Reactor Annual Report July 1, 2019 -- June 30, 2020 (Rev. 1) ML20189A3002020-07-0808 July 2020 Completion of Required Actions Under Confirmatory Order EA-19-071 Related to U.S. Nuclear Regulatory Commission Investigation Reports 4-2016-022 and 4-2017-023 ML20175A8322020-06-23023 June 2020 Reed College - Change of Management Staff ML20162A1902020-06-10010 June 2020 Reed College - Actions Under Confirmatory Order EA-19-071 ML20136A4062020-04-27027 April 2020 Transmittal of Proposed Security Plan at Reed College ML20098F1312020-04-0202 April 2020 NRC Reed TR 20200402 Request for Rvw Officials Ellis and Sams 4.2.20 ML20108F5312020-04-0101 April 2020 Reed College, Notification of Personnel Change Update ML20010G1772020-01-14014 January 2020 Examination Confirmation Letter No. 50-288/OL-20-02, Reed College ML19317D7912019-10-30030 October 2019 Financial Assurance and Financial Statements for the Reed Institute June 30, 2019 and 2018 ML19282A3882019-10-0202 October 2019 Reed College - Requesting Termination of Quality Assurance Program Approval Form for Radioactive Material Packages No. 0949, Revision 0, Docket No.71-0949 IR 05000288/20192012019-08-16016 August 2019 Reed College - U.S. Nuclear Regulatory Commission Security Inspection Report 05000288/2019201 ML19225C1642019-07-31031 July 2019 Transmittal of Security Plan at Reed College ML19211C0072019-07-24024 July 2019 Reed College, Transmittal of Annual Report July 1, 2018 - June 30, 2019 ML19155A1752019-06-13013 June 2019 U.S. Nuclear Regulatory Commission Staff Review Reed College 2018 Financial Assurance (Self-Guarantee) Docket No. 50 288 ML23130A2532019-04-29029 April 2019 Reed College, Management Change Update 2024-02-01
[Table view] |
Text
REED COLLEGE Reed Research Reactor 3203 SE Woodstock Boulevard, Portland, Oregon 97202-8199 phone: 503/777-7222 email: reactor@reed.edu October 28, 2020 2020-002 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-001 Re: Violation of Requalification Plan Docket 50-288 This is a self-report of a violation of Reed Research Reactors Requalification Plan.
The Violation On October 12, 2020 it was discovered that two licensed operators had not fully completed the requirements of the 2019-20 requalification year. Reeds requalification year runs from July 1 to June 30.
Specifically, the two operators had missed a mandatory requalification meeting on March 30, 2020. Reed College administration had closed the campus to students in mid-March 2020 due to the pandemic and all Reed students were sent home. A requalification meeting was held on March 30, 2020 using video sharing software. The students were not on campus and it was our first virtual requalification meeting. The normal remedial action for missing a requalification meeting is having operators review the materials from the missed meeting within 30 days. This was not documented for these two operators.
Since students were no longer allowed on campus, most of Reeds licensed operators fell out of requalification due to their inability to perform their required reactivity manipulations by the end of the 2019-2020 requalification year. When the 2020-21 requalification year started on July 1, 2020, most operators, including the two operators in question, were out of requalification because they had not performed the required reactivity manipulations during the 2019-20 requalification year.
The new school year started September 31, 2020. The operators completed their reactivity manipulations under the direct observation and control of a licensed operator.
After this was documented, the two operators in question were considered to be back in requalification and they then performed licensed duties. When we discovered on October 12, 2020 that the they had missed the requalification meeting from March 2020, the two operators stopped performing licensed duties until they had completed the necessary review of the missed materials.
The Cause The cause of the violation was an error by the Reactor staff in not verifying that all of the previous years requirements had been met for all operators at the beginning of the current requalification year.
A contributing cause was the requalification database. It automatically indicates whether an operator has completed their requalification requirements for the current year, but it was difficult to review the past requalification year in a simple manner.
Another contributing cause was the disruption in our normal operations and documentation when Reed College closed the campus during the pandemic.
The Immediate Correct Action When it was discovered that the two operators stopped performing licensed duties until they had completed and documented the necessary review of the materials from the March 30, 2020 requalification meeting.
Preventing Future Occurrences SOP 63, Requalification, will be revised to specifically require that supervisory staff review the requalification status of each operator at the beginning of each requalification year, semester, and quarter.
A mandatory requalification lecture will be given on the cause of the violation.
The requalification database will be modified to make it easier to review an operators requalification status.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on: October 28, 2020 Sincerely, Jerry Newhouse Reactor Director Reed College cc Kathryn Oleson, Ph.D., Dean of Faculty Geoffery Wertz, Project Manager Greg Casto, Chief, Non-Power Production and Utilization Facility Licensing Branch Travis Tate, Chief, Non-Power Production and Utilization Facility Oversight Branch