ML20267A173

From kanterella
Jump to navigation Jump to search
One Pager on Alternate Review Process Licensing Review Versus Inspections
ML20267A173
Person / Time
Issue date: 09/22/2020
From: Deanna Zhang
NRC/NRR/DRO/IQVB
To:
Zhang D
References
Download: ML20267A173 (2)


Text

ARP LICENSE REVIEW & INSPECTION1 September, 2020 LICENSE REVIEW INSPECTIONS (Submittal Review & Audits) (Vendor & Licensee)

System Design Information:

  • System Architecture
  • System Requirements Specification
  • Equipment Qualification Results
  • D3, Redundancy, Independence, Determinism Sufficiency of System Development Processes: Appendix B Implementation of Processes:
  • BTP 7-14 (B.3.1) Review of Plans
  • Design changes
  • Crediting of SPM as applicable
  • Design outputs for implementation and
  • PSAI resolutions or commitments to address testing lifecycle phases PSAIs
  • Factory Acceptance Tests
  • Site Acceptance Tests Sufficiency of Vendor Oversight Plan for: Appendix B Implementation of VOP:
  • Verification and Validation (during Detailed Implementation, V&V, and FAT)
  • Configuration Management
  • Verifying oversight of vendor activities
  • Design Activities performed during those phases meet
  • Implementation Activities requirements for design control (e.g.,
  • Integration Activities design changes, independent V&V)
  • Testing Activities
  • Verify that documentary evidence exists to
  • Installation Activities ensure that the procured system conform to procurement requirements
  • Verifying that appropriate corrective actions were taken to address any deficiencies identified during oversight activities of the vendor
  • Verifying that the licensee performed required external audits on the vendor for activities performed during the above phases Compliance Findings:
  • Inspection Findings Against Appendix B to Finding
  • GDCs s
  • Appendix B (e.g., QA Plan, VOP Summary)

Not in Scope2 Not in Scope

  • Implementation of software and hardware
  • Sufficiency of Design
  • Design output documentation and detailed V&V
  • Conformance with IEEE 603 & 7.4-3-2 results for lifecycle phases after detailed
  • Vendor Oversight Plan Sufficiency (which software and hardware design may be audited during the LAR review to
  • Resolution of Non-Conformances support the VOP summary review)
  • Factory Acceptance Test Results 1

The scope and findings are presented in general terms to reflect intended differences in the license review approach and inspections using the alternate review approval process, which is currently being piloted. It is not intended to be formal NRC guidance or criteria needed to make a license finding under 10 CFR Part 50 and conducting associated inspections under Appendix B to 10 CFR Part 50.

2 These items would be subject to detailed license review and audit under the traditional review process.