J. D.Woodard Southern Nuclear bocutive Vce President Operating Company. ine.
40 tovemess Center Parkway Post Othce Box 1295 Birmingham. Alabama 35201 Tel 205.992.5006 k
SOUTHERN L COMPANY Energy to Serve YourWorld" June 12,1998 LCV-0828-E Docket Nos. 50-424 and 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555 Ladies and Gentlemen:
VOGTLE ELECTRIC GENERATING PLANT REQUEST TO REVISE TECilNICAL SPECIFICATIONS ADDITIONAL FUEL STORAGE RACKS FOR UNIT 1 FUEL STORAGE POOL RECOMMF,NDED LICENSE CONDITIONS By way ofletters LCV-0828-C c.nd LCV-0828-D, dated May 19,1998, Southern Nuclear Operating Company (SNC) provided responses to the request for additional information (RAI) received on April 10,1998. The letters also included responses to questions from the Staffin addition to the RAl.
In letters LCV-0828-C and LCV-0828-D, SNC recommended a set of commitments to become license conditions in Appendix D of Facility Operating Licenses No. NPF-68 and NPF-81. These commitments addressed spent fuel pool temperature and heat load
)
management. SNC recommends that the above-referenced commitments be superseded by
/
l commitments 1 and 2 below.
O SNC further recommends a set of commitments, regarding heavy load handling during the o
Unit I re-racking operations, to become license conditions in Appendix D of Facility MO '/
j Operating License NPF-68.
Commitments I through 4 are recommended to be incorporated in Appendix D of Facility Operating License No. NPF-68. Commitment 2 is also recommended to be incorporated in Appendix D of Facility Operating License NPF-81.
I 9906180136 990612 i
PDR ADOCK 05000424 P
PDR l
l i
t U S. Nuclear Regulatory Commission Page 2 The recommended commitments are:
- 1. The spent fuel pool heat loads will be managed by administrative controls. These controls will be placed in applicable procedures prior to transferring irradiated fuel into I
the Unit I spent fuel pool.
- 2. The UFSAR will be updated to include the heat load that will ensure the temperature limit of 170 *F will not be exceeded, as well as the requirement to perform a heat load l
evaluation prior to transferring irradiated fuel to either pool. This will be included in the next appropriate UFS AR update following the installation of the Unit I spent fuel racks.
- 3. A temporary gantry crane, with a hoist rated for 20 tons, will be erected on the l
existing fuel handling bridge rails to move the racks within O spent fuel pool area.
This commitment will be implemented prior to commencing re-racking operations.
- 4. All applicable crane, load path and height, rigging and load testing guidelines of NUREG-0612 and ANSI B30.2 will be implemented prior to and during re-racking operation:1, as appropriate.
Mr. J. D. Woodard states that he is an executive vice president of Southern Nuclear and is authorized to execute this oath on behalf of Southern Nuclear and that, to the best of his knowledge and belief, the facts set forth in this letter and enclosures are true.
Sincerely,
'N
~\\
Woodard Sworn to and subscribed before me N ay this/O d
.OC
,1998.
/
jnAA w
da bL/ )
M ommission Expires: 9-N-f8 LCV-0828-E xc: (See next page)
I l
_e l'
U. S. Nuclear Regulatory Commission Page 3 JDW/RJF '
Attachment xc:
Southern Nuclear Operating Comnany Mr. J. B. Beasley (w/o)
Mr. M. Sheibani (w/o)
SNC Document Management (w/att)
U. S. Nuclear Regulatory Commission
.Mr. L. A. Reyes, Regional Administrator (w/o)
Mr. D. H. Jaffe, Senior Project Manager, NRR (w/att)
Mr. J. Zeiler, Senior Resident Inspector, Vogtle (w/o)
LCV-0828-E 1
J