p y
.;.s a neto,%,,,
./
UNITED STATES
~
NUCLEAR REGULATORY COMMISSION r
o.
{
WASHING TON, D. C. 20555
%,*...,/
CHAIRMAN July 28, 1989 The Honorable John Glenn, Chairman Committee on Governmental Affairs United States Senate Washington, D. C. 20510
Dear Mr. Chairman:
In accordance with the statutory obligation to respond to recommendations by the General Accounting Office (GAO) within 60 days of publication, we hereby submit our response to the recommendation-made by the GA0 in their report entitled " NUCLEAR REGULATION:
NRC's Restart Actions Appear Reasonable--But Criteria Needed."
Specific comments on the GAO recommendation are presented in the enclosure.
Sincerely, b e.L Kenneth M. Carr
Enclosure:
Response to GA0 Recommendation cc:
Senator William V. Roth, Jr.
Senator Paul S. Sarbanes Senator Earbara A. Mikulski GCSP l
FULL TEXT ASCli SCAN
6
.4 O cth q#o,.
UNITED STATES
~
A' NUCLEAR REGULATORY COMMISSION '
n
{
WASHINGTON, D. C. 20555
\\...../
CHAIRMAN July 28, 1989 The Honorable John Conyers, Jr., Chairman l
Committee on. Governmental Operations United States House of Representatives Washington, D. C.
20515
Dear Mr. Chairman:
In accordance with the statutory obligation to respond.
to recommendations by the General Accounting Office (GAO) within 60 days of publication, we hereby submit our response to the recommendation made by the GA0 in their report entitled " NUCLEAR REGULATION:
NRC's Restart Actions Appear Reasonable--But Criteria Needed."
Specific comments on the GA0 recommendation are presented in the enclosure.
Sincerely, Kenneth M. Carr
Enclosure:
Response to GA0 Recommendation cc:
Rep. Frank Horton Senator Paul S. Sarbanes Senator Barbara A. Miku.lski l
m_
-__-__-m________.m.m_.__._._-.A-_.m__
-.--._---_.-___m__m_
o UNITED STATES P *i NUCLEAR REGULATORY COMMISSION
'(
WASHINGTON,D C.20555
% ***./
CHAIRMAN July 28, 1989 i
The Honorable John B. Breaux, Chairman Subcommittee on Nuclear Regulation Committee on Environment and Public Works United States Senate Washington, D. C.
20510
Dear Mr. Chairman:
In accordance with the statutory obligation to respond to recommendations by the General Accounting Office (GAO) within 60 days of publication, we hereby submit our response.
to the recommendation made by the GA0 in their report entitled " NUCLEAR REGULATION:
NRC's Restart Actions Appear Reasonable--But Criteria Needed."
Specific comments on the GA0 recommendation are presented in the enclosure.
Sincerely, wa Kenneth M. Carr
Enclosure:
Response to GA0 Recommendation ec:
Senator Alan K. Simpson Senator Paul S. Sarbanes Senator Barbara A. Mikulski a
i
)
,4 k
UNITED STATES.
f NUCLEAR REGULATORY COMMISSION l
M WASHINGTON, D. C. 20555 o,
N
%, -...../
CHAIRMAN July 28, 1989 The Honorable Morris K. Udall, Chairman Subcommittee on Energy and the Environment Committee on Interior and Insular Affairs United States House of Representatives Washington, D..C.
20515
Dear Mr. Chairman:
1 In accordance with the statutory obligation to respond to recommendations by the General Accounting Office (GAO) within 60 days of publication, we hereby submit our response to the recommendation made by the GA0 in their report-entitled " NUCLEAR REGULATION:
NRC's Restart Actions Appear Reasonable--But Criteria Needed."
Specific comments on the GA0 recommendation are presented in the enclosure.
Sincerely, wsk.A Kenneth M. Carr
Enclosure:
Response to GA0 Recommendation cc:
Rep. James V. Hansen Senator Paul S. Sarbanes Senator Barbara A. Mikulski
s Clov n
- i..
4 UNITED STATES NUCLEAR REGULATORY COMMISSION l
o
({
WASHINGTON, D. C. 20555 l
l A%...../
CHAIRMAN July 28, 1989 The Honorable Philip R. Sharp, Chairman l
Subcommittee on Energy and Power Committee on Energy and Commerce l
United States House of Representatives Washington, D. C.
20515
Dear Mr. Chairman:
In accordance with the statutory obligation to respond to recommendations by the General Accounting Office (GAO) within 60. days of publication, we hereby submit our response to the recommendation made by the GA0 in their report entitled " NUCLEAR REGULATION:
NRC's Restart Actions Appear.
Reasonable--But Criteria Needed."
Specific comments on the GA0 recommendation are presented in-the enclosure.
Sincerely, M....%..L Kenneth M. Carr
Enclosure:
Response ;o GA0 Recommendation cc:
Rep. Carlos J. Moorhead Senator Paul S. Sarbanes Senator Barbara A. Mikulski
I 1
ENCLOSURE RESPONSE TO GA0 RECOMMENDATION Recommendation:
The GA0 stated that to ensure the safe restart of each nuclear power plant which has been shut down to correct safety and/or management problems, criteria should be developed that describe both NRC and utility actions that must be taken before allowing restart. The GA0 further stated that these criteria should be flexible enough to allow NRC to add requirements on a plant-by-plant basis giving consideration to overall design, personnel, and management. The GA0 recomended that at a minimum the criteria include review and approval of the utility's corrective action plan, inspections to ensure the actions are taken, independent review of NRC's actions, and public participation.
NRC Response:
The NRC agrees with the GAO position that specific criteria for evaluating the readiness for restart of plants shutdown to correct safety and/or management problems should be developed. The NRC staff is planning to develop such criteria in the next fiscal year based on the programs utilized in recent restart reviews for Peach 'tottom, Pilgrim, Rancho Seco, and Sequoyah, and the general guidelines issued in November 1988 and discussed in the GA0 report.
These criteria will be more specific than current guidelines, especially regar ding:
(1) independent review of NRC staff actions; (2) public partici-pation; (3)(order, confirmatory order, or confirmatory action letter); and (4) the method of establishing necessary actions by the licensee prior to restart the NRC's plan for technical review and inspection.
The criteria will also include as clear a definition as possible of those restart cases where use of these steps would be appropriate. The criteria will be flexible enough to accommodate plant-specific issues to the extent required. The new criteria will be incorporated in Part 0500 of the NRC Manual.