Supplemental Deficiency Rept CP-86-19 Re Class 1E Instrument Installations.Initially Reported on 880129.Corrective Actions Rescheduled for Completion by Fuel Load for Unit 1. Schedule for Unit 2 Remains Unchanged
ML20247N794
Person / Time
Site: Comanche Peak  
Issue date: 06/02/1989
From: William Cahill, Walker R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CP-86-19, TXX-89367, NUDOCS 8906060028
Download: ML20247N794 (1)


Text

,.

'l. ' L' p

==

l P9 Log # TXX-89367 l

l 1

C File # 10110 l

r Z

909.5 1UELECTRIC '

wmiam J. CahiH, Jr.

Esecutive Vice President U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446

' INSTRUMENTATION INSTALLATIONS SDAR: CP-86-19 (SUPPLEMENTAL REPORT)

Gentlemen:

On January 29, 1988. TU Electric letter. logged TXX-88146, provided notification that the deficiency involving Class 1E instrument installations was reportable under the provisions of 10CFR50.55(e). Our latest report on this issue, logged TXX-88851 was submitted December 15, 1988. This report is submitted to update the corrective action completion schedule.

Unit 1 corrective actions have been rescheduled for completion by fuel load for Unit 1.

The schedule for Unit 2 remains unchanged.

Sincerely, h.

VY f.

f William J. Cahill, Jr.

By:

@f Roger DY Walker Manager Nuclear Licensing GLB/ddm c - Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3)