ML20247L190

From kanterella
Jump to navigation Jump to search
Discusses Evaluation of 10CFR50.49 Vertical Conduit Runs. Util Plans to Limit Evaluations to Unit 1 Annulus Area & Will Inspect,Evaluate & Correct,If Necessary,Unit 1 Conduit & Cables Corresponding to Deficient Ones in Unit 2
ML20247L190
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 07/26/1989
From: May R
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8908010176
Download: ML20247L190 (3)


Text

,

V

~

1'

.e

' TENNESSEE VALLEY AUTHORITY OH ATTANOOGA. TENNESSEE 37401 5N 1578 Lookout Place JUL 261989 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Hashington, D.C.

20555 Gontlemen:

In the Matter of

)-

Docket No. 50-327 Tennessee Valley Authority I

'SEQUOYAH NUCLEAR PLANT (SQN) UNIT 1 - EVALUATION OF 10 CFR 50.49 VERTICAL CONDUIT RUNS

Reference:

TVA letter to NRC dated December 8, 1986, "Sequoyah Nuclear Plant (SQN) - Cable Pulling Questions:

Supplemental Responses" In the referenced letter, TVA committed to inspect all 10 CFR 50.49 vertical conduit runs and evaluate, schedule, and implement any corrective actions by the Unit 1 Cycle 4 refueling outage.

TVA has now determined, however, that it is appropriate to limit the scope of the commitment to the 10 CFR 50.49 vertical conduit runs in the Unit 1 annulus.

Based on the evaluation of the Unit 2 vertical conduit runs, it has been concluded that the potential for cable failure because of excessive static sidewall pressure in unsupported cables is limited to the annules only. After a review for Unit 2 of approximately 2,800 cables, a walkdown of 480 conduits, and calculations on 403 cables (including 129 cables in the annulus), there was only 1 conduit in the auxiliary building that was in nonconformance with the Naticnal Electrical Code's (NEC) cable support requirements and exceeded the maximum allowable sidewall pressure limits.

Despite the nonconformance, the 6 cables in that conduit were not damaged. Conversely, there were 7~ conduits containing a total of 48 cables in the Unit 2 annulus that exceeded both the NEC spacing limits and the sidewall pressure limits.

In these conduits also, no cable damage was detected.

TVA expects similar results for Unit 1 and plans to limit the evaluations to the Unit 1 annulus area.

Additionally, TVA will inspect, evaluate, and correct, if necessary, the Unit 1 conduit and cables corresponding to those identified as deficiert in Unit 2.

I)o3o

' i s908010176 890726 ADOCK 0500 7

gDR An Equal Opportunity Employer 1

.y, w

A g!t t

3. yr L

j

i '

..[N e;

.JUL 261989 n

g.

')'.'

i t

' :l

  1. fA: summary: statement of'the' revised. commitment is contained in the enclosure,

~

y Please' direct questions concerning this. issue to B. S..Schofield at

-(615)'843-6172.

'Ve.ry truly yours, TENNESSEE VALLEY AUTHORITY

$7 Mana r, Nucletr Licensing and Regulatory Affairs

. Enclosure :

cc (Enclosure):

Ms. S. C.. Black, Assi.stant Director.

for.l Projects '.

TVA Projects Division 1

U.S. Nuclear Regulatory Commission One White Flint, North

11555:Rockville' Pike' Rockville,. Maryland 20852:

Mr. B. A. Wilson, Assistant Director.

foreInspection Programs-t.TVA Projects Division

- U.S. Nuclear' Regulatory. Commission Region II-101..Marietta Street, NW,. Suite 2900 Atlanta, Georgia 30323 4

.NRC Resident ~ Inspector Sequoyah Nuclear Plant 2600 Igou Ferry Road i

Soddy Daisy,' Tennessee 37379 o

l 1

x.

~.,

y-

'e ll *

.?)

1 se '

ENCLOSURE.

a

,F,

-)

i Revised Commitment:

k j

7-For' Unit -1,- TVN w11111nspect all l10 CFR 50.49' vertical ' conduit runs' in the

.]

. annulus and will evaluate,. schedule, and. implement-any. required corrective

. action by.the lend of the Unit 1 Cycle 4 refueling outage.. Additionally, by Lthe end of the Unit 1 Cycle.4 refueling outage, TVA will inspect, evaluate,

. ar:d correct, if. necessary,- the Unit 1_ conduit and cables' corresponding to

'those! identified as' deficient in Unit 2.

l I

i 1

i e--

_