ML20247G894

From kanterella
Jump to navigation Jump to search
Forwards Special Team Insp Repts 50-317/89-200 & 50-318/89-200 on 890227-0331.Executive Summary Also Encl. Deficiencies Discussed
ML20247G894
Person / Time
Site: Calvert Cliffs  
Issue date: 05/23/1989
From: Varga S
Office of Nuclear Reactor Regulation
To: Creel G
BALTIMORE GAS & ELECTRIC CO.
Shared Package
ML20247G899 List:
References
NUDOCS 8905310103
Download: ML20247G894 (9)


See also: IR 05000317/1989200

Text

-

-_

_

-

_ _ _ - _ _ _

.

,

c

'%q

j

'.[<

[k

UNITE D STATES

j

q

NUCLEAR REGULATORY COMMISSION

,

,/'.

.

WASHINGTON, D. C. 20555

g . .w. . + *#

May 23, 1989

)

I

Docket Hos. 50-317

and 50-318

Mr. George C. Creel

Vice President, Nuclear Energy

P. O. Box 1535

Lusby, Maryland 20667

Dear Mr. Creel:

SUBJECT: cal. VERT CLIFFS SPECIAL TEAM INSPECTION (50-317/89-200 AND

50-318/89-200)

This letter forwards the report and executive sumary of the special team

inspection (STI) conducted by Mr. C. J. Haughney and other NRC personnel from

February 27 through March 31, 1989. The activities involved are authorized by

NRC Operating License Nos. DPR-53 and DPR-69 for Calvert Cliffs Nuclear Power

Plant, Units 1 and 2.

At the conclusion of the inspection, the team discussed

the findings with you and with members of your staff identified in Attachment A

of the enclosed inspection report.

The STI included two groups, an operations and maintenance group and a

managerent group. The operations and maintenance group examined selected

activities in the areas of operations, maintenance, quality control, surveil-

lance testing, and corrective action. The management team perfonned a review

of management effectiveness at Calvert Cliffs.

The team determined that the plant was staffed by competent, knowledgeable

people who executed their duties in a professional manner and were capable of

operating the plant safely. However, the team also identified a number of

deficiencies in the areas inspected that warrant management attention. These

deficiencies-included:

licensee maintenance procedures that did not contain

sufficiently detailed instructions to ensure siaintenance activities were

performed correctly or documented adequatcly, tte near absence of written

instructions for quality control activities, and numerous instances of untimely

and incomplete corrective actions for identified problems. The team concluded

that management's operating style, which placed primary emphasis on power

production, was a major contributor to the increased number of operational

events at the facility.

Two documents are enclosed with this letter. The executive sumary provides an

overview of the inspection team's findings in each area reviewed. The

inspection report provides a more detailed explanation of the team's findings.

We request that you respond, in writing, within 30 days of receipt of this

/

letter identifying actions taken or planned to be taken to address the 14

m

specific unresolved items identified in the enclosed inspection report and

y

separately listed in Appendix C to the report. There are also many other

8

'

i

(

k

O

7

G

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

___

-_.

_ _ _ _ _ _

n

,,

,

.

Mr. George C.- Creel

-2-

May 23, 1989

.

weaknesses identified in the executive sumary and in the inspection report

that will also need your careful review and evaluation.

For these items, we

suggest that following your evaluation of needed corrective actions, you

arrange a meeting with the Calvert Cliffs Assessment Panel. At this meeting

you should be prepared to discuss both your current Performance Improvement

Plant (PIP) and any revision: to that plan, which are necessary to address the

i

identified weaknesses.

Some of the items identified by the team may be potential enforcement findings.

Any enforcement actions will be identified by Region I in separate correspond-

l

ence.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosures

will be placed in the NRC Public Document Room.

I

Mr. C. J. Haughney (questions concerning this inspection, please contact me or

Should you have any

!

301-492-0967) of this office.

Sincerely,

/

Steven A. Varga, Director

Division of Reactor Projects I/II

Office of Nuclear Rcactor Regulation

Enclosures:

1.

Executive Summar3

2.

Inspection Report 50-317/89-200,50-318/89-200

cc w/ enclosures: See next page

1

g

%t? pff6 W

IOFC :RSIB:

NRR :RSI8:DL

4RR:SI DRIS:NRR: SIB:

NRR:DI

R

RR:

P ITII:NRR

l.__..:....

.....:._____L

..:..

......:....

__:. .

... __:.

........:__ ..___

'NAME :JCunnr

s, $ :SGuthrie ,

J

in

CHau

mes

a a

____: ___....

_ _ _ _ _ _ _ _ . . . . . . . .g _ _9

.:..

______:_______.....:

.....:..........g..:.....__...

05/7t/89
05/%'J8

DATE :05/23/89

05/C/89
05

Y89

05/@89

7

_

.

.

.

.

> '-

'

r,.

,,

i

Mr. George C. Creel

-3-

May 23, 1989

.

cc w/ enclosures:

Edward A. Crooke, President

Roland Fletcher

Utility Operations

Center for Radiological Health

baltimore Gas and Electric Company

Department of Environment

1

P.O. Box 1475

2500 Broening Highway

Ba!timore, Maryland 21203

Baltimore, MD 21224

'

Mr.' William T. Bowen, President

Calvert County Board of

Conrnissioners

Prince Frederick, Maryland 20768

D. A. Brune, Esquire

>

General Counsel

Baltimore Gas and Electric Company

,

P.O. Box 1475

Baltimore, Maryland 21203

Nr. Jay E. Silberg, Esquire

Shaw, Pittman, Potts and Trowbridge

4

.1800 M Street, NW

Washington, DC 20036

Mr. W. J. Lippold, General Supervisor

Technical Services Engineering

1

Calvert Cliffs Nuclear Power Plant

MD Rts 2 & 4

P.O. Box 1535

'

Lusby, Maryland 20657

Resident Inspector

c/o U.S. Nuclear Regulatory Cossnission

.

P.O. Box 437

Lusby, Maryland 20657

l

<

i

Department of ' Natural Resources

Energy Administration, Power Plant

.

1

Siting Program

l

. ATTN: Mr. T. Magette

i

i

J

l

Tawes State Office Building

!

l

Annapolis, Maryland 21204

Regional Administrator, Region I

f

U.S. Nuclear Regulatory Commission

,

'

-

475 Allendale Road

King of Prussia, Pennsylvania 19406

Institute of Nuclear Power Operations

'

1100 circle 75 Parkway

Atlanta, Georgia 30339

'

l

lL_ __ _

--

_

_ _ _ _ _ _ _

__

. _ _ _ _ _ _ _ _ _ - _ _ _ _

_

'

lt

- i .;

'

>

-

-4-

May 23 1989

l'

.Mr. George'lC., Creel

<

_7

.

.;

Distribution:

~

Docket Files 50-317/318

,

-rDRIS R/F

RSIB R/F-

+ BGrimes

'0CM-(5)

SSECY :

1

=tVStello,

iJTaylorJ

' HThompson

-

i1Blaha

>JFouchard,~GPA-

.."-

jRNewlin, GPA

,

MCallahan, GPA/CA

<CHaughney

JDyer-

Elmbro

vdKonklin-

'JCummins-

sSGuthrie

. Inspection Team

.yTMurley

JSniezek-

FMiraglia.

JPartlow

y

--BBoger?

SVarga

. #.

SMcNeil

RCapra.

LJAllan, RI

KAbraham... RI

, /TMartin, EDO

'

s WKennedy,-EDO

$BClayton, EDO

eWKane,.RI

PTMartin.'.RI

SCollins, RI

-

"JWiggins, RI

'LTripp, RI'

,

VPritchett, RI

diEichenholz, SRI

s

Regional. Administrators

iRegional Division Directors

ACRS'(3)

OGC (3)

.

l

IS Distribution

1

_ . - . . _ _ _ _ _ _ _ _ . .

- _ _ - _ _ _

._-____-..______=_-__ ____ _ -

.

-.

- - _ _ _ - -

.

.

.

-

,

'

o

..

.-

'

i

!

ENCLOSURE 1

l

EXECUTIVE SUMMARY

INSPECTION REPORT 50-317/89-200. 50-318/89-200

CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2

)

i

From February 27 through March 31, 1989, a team of 12 NRC inspectors performed

a special team inspection at Calvert Cliffs Nuclear Power Plant, Units 1 and 2.

The intent of the inspection was to determine the causes of recent events and

what was perceived as a general decline in the level of performance at the

Calvert Cliffs plant. The inspection team consisted of two groups, the

operations and maintenance group and the management group. The operations and

maintenance group conducted inspections in the areas of operations,

maintenance, quality control, surveillance testing, and corrective action. The

management group evaluated the effectiveness of Calvert Cliffs management

personnel in managing the safe operation of the plant.

Operations

The team observed many strengths in the operations area with respect to

conduct, professionalism, qualification, and procedure compliance. These

strengths were particularly evident during the team's observation of cosiplex

high-visibility activities such as plant startups and shutdowns. During the

J'

5-week period of the inspection there were three instances (not observed

directly by the team) in which operating personnel erred, resulting in a near

'

loss of the main condenser or inadvertent actuations of the engineered safety

feature actuation system (LSFAS). The licensee described these errors as

cognithe mistakes or attributed them to human error in dealing with

procedures. The team, however, was concerned that such activities wem not

always conducted in the deliberate, step-by-step manner required to avoid such

errors.

The team identified programmatic weaknesses in the ama of administ:ative

controls. The licensee's procedures applicable to the control of plant

y

operating and surveillance test procedure changes.wem fragmented and failed to

t

fully implement technical specification mquirements. Tre team found that

,

)

instrumentation maintenance personnel were using an inventory of pressum

L

gauges for measuring and test equipment (M&TE) that were used to support

<

L

safety-related surveillance tests, but that no controlling procedure was

i

l

available, and there was no method of recall for gauges found to be out of

calibration. Even after the team identified the problem, the licensee did not

take timely corrective action to confom to their existing M&TE program. In

addition, the team found that the licensee's tamporary modification program was

confusing, failed to assure the proper review of all modifications by the Plant

Review Committee before their installation into the plant, and was not under

sufficient management oversight to minimize the number of temporary modifica-

l

tions installed. The licensee required temporary modification tracking system

.

'

was not being maintained in a current manner.

These administrative control weaknesses appeared to te the tusult of a gradual

decline in procedure quality because of multiple revisions and failum on the

part of the licensee's staff to insist on correct and workable procedums.

ES-1

- - _ _ -

-

s

E

,

,

.

.

The team observed many strengths in the qualifications and professionalism of

the operations staff.

Communications between operations and maintenance

j

personnel appeared to be effective. However, the team observed less effective

communication between the engineering and operations staffs.

Interviews with

operators indicated little confidence in the qualifications of many of the

systems engineers and their ability to assist the operators,

q

J

6

It appeared to the team that the licensee was making a serious effort to change

operator attitudes regarding following procedures, conducting deliberate

operations, and emphasizing safety.

Procedure adherence appears to continue

as a problem (several examples of procedure adherence errors occurred during

and after the inspection period). The present cadre of experienced operations

personnel can become more effective at ensuring operational safety, if proce-

dures are improved and procedural adherence is routinely required and practiced.

Maintenance

On the positive side, the team found that (1) craftsmen appeared to be

experienced, knowledgeable, and capable; and (2) the maintenance organization

was developing new improved maintenance procedures.

On the negative side, the work instructions used for performing the vast

majority of site maintenance activities did not contain adequate details to

ensure that the activities were being performed correctly, or to provide

meaningful acceptance criteria and hold points for quality control (QC)

inspectors. The instructions were so incomplete that craftsmen were required

to use their judgment in performing nearly every maintenance step, regardless

of the work process complexity.

Also, the licensee's procedure for controlling vendor technical manuals was not

being followed in that not all technical manuals received on site were being

sent to document control; and engineering reviews of the technical manual

changes were not being completed in a timely manner. The inspection team

identified 51 technical manuals (dating back to 1984) that had not been

reviewed. Also, the meaning, extent, and scope of the required engineering

review for vendor manuals was not clearly defined.

In lieu of an approved procedure, the licensee's instructions for issuing weld

rod were provided by memorandum. There were also instances observed where

there was inadequate control of the welding process.

Quality Control (OC)

The inspection team found that QC personnel were not effective in performing

the required independent inspection function, primarily because they had not

been provided with adequate written instructions, an essential tool for

performing this function.

In addition, these QC inspectors did not appear to

have technical skills equivalent to many of the maintenance personnel, a

situation that left them on a very unequal footing when attempting to con-

structively monitor the craft's work practices.

Deficiencies in the OC

inspection area included failure to perform all required inspections, lack of

ES-2

_ _ - _ - _ _ - _ - _ _ _ - _ - _ _ _ _ _ _ _ - _ _

.

.

-

'fs

sn

.

.

4

criteria for the QC inspector to ensure that inspections were performed

correctly, and indications of an adversarial relationship between QC inspectors

and craft personnel.

The team concluded that more licensee management attention is required in the

QC area to ensure that adequate instructions are available, and that required

independent inspections are performed correctly.

Surveillance Testing

The team found that the overall technical expertise of licensee personnel

involved with surveillance testing activities was acceptable. However, several

examples of personnel errors, which occurred during the period of this inspec-

tion, indicated that this area needed increased attention. Licensee personnel

'

appeared to perfom many routine or repetitive surveillance test activities

without properly using the associated procedures. Such activities were not

always perfomed in a well-controlled and deliberate manner and sometimes

resulted in unnecessary challenges to safety systems.

The surveillance testing program appeared to be fragmented, and

responsibilities for implementing the surveillance program were diffuse.

Various types of implementation inconsistencies and a lack of clearly defined

authority contributed to a weakness regarding surveillance program control and

to difficulty in readily evaluating program effectiveness. Several factors,

including inconsistent and incomplete use of calibration stickers, the absence

of a master calibration schedule, and no verification of instrumentation

calibration status, contributed to there being no mechanism in existence to

l

verify that the calibration control program for permanently installed equipment

t'

was properly maintained and implemented.

The team also found that several surveillance procedures were of poor quality,

in that they contained numerous technical and administrative errors. Only two

groups were found to be using a fomal procedure writer's guide.

In addition,

the licensee was not adequately evaluating vendor manual recommendations for

incorporation into surveillance procedures, was not appropriately utilizing the

l

mechanism for administratively changing surveillance procedures, and was not

,

initiating permanent procedure changes in a timely manner.

The team also found that, although several progrannatic changes and station

directives had been implemented recently, the continuing occurrence of plant

events and the findings of this inspection team indicated that those changes

had not been uniformly effective in addressing the fundamental deficiencies

.

'

!

that encumbered the surveillance test prograia.

, corrective Action

The team found that the licensee had systems in place that could have been used

to ensure timely and effective corrective actions. However, the team felt that

the licensee had failed to effectively or fully utilize these systems.

Inadequate responses to identified concerns and deficiencies have been a

continuing problem for this licensee.

The team's review of Quality Assurance Program implementation found that t.he

quality audits and program evaluations were thorough.and effective in

i

ES-3

-

i

.

-

-

.,

,

,,.

.-

.

identifying specific areas in need of corrective action, and that the QA

auditors were capable and knowledgeable in a wide variety of disciplines.

In

addition, technical support personnel, including some system engineers,

appeared to be knowledgeable and aware of specific concerns involving their

systems. However, in many cases the licensee had not taken adequate or timely

corrective and preventive actions in response to significant QA audit findings

and reconsnendations, had not been timely or thorough in the determination of

root causes and safety significance of identified deficiencies, and had not

fully developed or utilized the integrated corrective action program (ICAP)

data base for trending equipment failures.

Management Effectiveness

By their actions and by aspects of their operational decisions, management

demonstrated to the plant staff an operating style that placed primary emphasis

on power production, with less attention to the safety aspects of plant opera-

tion. This style appeared to be at least partly based on a misplaced over-

confidence in the ability of their highly skilled and experienced operating and

maintenance crews to keep the plant operating safely without significant

reliance on engineering reviews or substantial involvement by QA or QC. In

addition, some plant workers interpreted an austerity pragram instituted in

the early 1980s as a message to "do more with less." The team felt that these

underlying themes may have inadvertently spurred the plant's highly skilled

workers to use their own judgment to solve problems and to take seemingly minor

shortcuts in order to achieve production goals. Unfortunately, the eventual

result of theso types of actions has been declining plant performance.

Management failed to recognize and respond to changes in the nuclear industry,

in the regulatory environment, and within their own organization. Having

remained relatively isolated from the progress in programs, procedures, and

systems throughout the industry and in the evolving nuclear regulatory arena,

the team concluded that many of the practices, systems, and controls in place

at the facility required upgrading.

The licensee staff at all levels generally lacked an understanding of the

unique'and demanding requirements for success in the complex project management

matrix organization that was in place at the facility. Project management

suffered from the lack of a shared information base, the lack of a site-wide

integrated planning and scheduling system, and the diffusion of accountability

and project ownership throughout the organization. The specialized managerial

and leadership skills required for success in the complex project matrix

organization were found to be deficient. The team concluded that the licensee

had not recognized that virtually every site activity was a project requiring

shared resources, shared goals, negotiation, c3 ordination, conflict management,

and communication.

The team concluded that senior site management had not been effective in

defining the organization's broad goals, performance expectations, and cperat-

ing philosophy. Site middle management tended to filter rather than translate

goals into measurable ar.d understandable perforriance expectations for the work

force.

ES-4

-

.__-__--__ _ - -

.

<,3.

.

-i

,,

.

.

Management et all levels had been ineffective in incorporating safety and

<

.

quality into their activities, choosing instead to respond to the ongoing

emphasis on production.

The work force has been effective at supporting power

production without benefit of adequate procedures systems, or programs, or

clearly defined work priorities and performance expectations.

The tram was concerned that unless all levels of the organization understand

t?iat quality and safety must be central to their activities and take priority

over power production, that the increased number of operational events of the

recent past could be expected to continue.

.

I

4

?

'

,

(

.

,

.

l

.

ES-5

7

_ _ _ _ _ _ - _ - - _ _ _ _ _ _ _ _ _ _ _ -

8