Text
_
VERMONT YANKEE NUCLEAR POWER CORPORATION RD 5, Box 169, Ferry Road, Brattleboro, VT 05301 AEPLY TO ENGINEERING 0FFICE 580 MAIN STREET DOLToN, M A 01740 l
March 20, 1989 (508)779 6711 U.S. Nuclear Regulatory Commission Washington, D.C.
20555 Attn:
Document Control Desk
References:
a)
License No. DPR-28 (D ckct No. 50-271) b)
Letter, USNRC to VYNP3, NVY 88-160, Inspection Report No. 50-271/88-200, r,ated 8/10/88 c)
Letter, VYNPC to V4NRC, FVY 88-83, Vermont Yankee Response to Inspection Report 50-271/88 ?00, Emergency Operating Procedure (EOP) inspection, dated 9/27/88
Dear Sir:
Subject:
Submittal of Vermont Yankee's Updated Procedure Generation Package (PGP)
In response to the NRC Inspection Report No.88-200 [ Reference b)), Vermont Yankee committed to submit an updated PGP, including justifications for deviations from the NRC accepted Emergency Procedure Guidelines (EPG), Revision 3.
Accordingly, the atttched document (VY PGP) contains as appendices, in part, VY Plant Specific Technical Guidelines (PSTG's), and the Justification for Deletion, Deviation or Addition (JDDA) Document required to implement the BWROG Emergency Procedure Guideline, Revision 3.
The changes to the various E0P documents were initiated prior to the performance of the NRC inspection; however, the additional concerns identified
(
in Reference b) have been addressed in the attached document.
The VY Emergency Operating Procedures are being revised to incorporate the program enhancements made in the attached document. The expected completion date of the E0P revisior, is April 30, 1989. The procedures will be issued following necesst.ry operator training which is anticipated to be completed in July 1989.
We trust this letter and attachment is responsive to your request and resolves f
all open issues associated with the August 10, 1988, E0P Inspection Report [ Reference b)]. Should you have any questions or desire any additional information on this issue, please do not hesitate to contact us.
Very truly yours, VERMONT YANKEE NUCLEAR F0WER CORPORATION W YW9 Murphyj$
j arren P Vice Pr sident (6 i
Attachment Manager of Oper t'ons
/dm cc: USNRC Regional Administrator, Region I USNRC Resident Inspector, VYNPS ob 8004040174 990320
{
\\ \\
PLH ADOCK 05000271 PDC j