MONTHYEARML20247F9911989-09-12012 September 1989 Order Authorizing Dismantling of Facility & Disposition of Component Parts,Per 880108 Application as Supplemented by 890131 & 0414 Ltrs ML20206N0241988-11-21021 November 1988 Settlement Agreement.* Agreement Made & Entered Into on 881121 Between Intervenor & Licensee Re 880108 Application for Amend to License R-101 Re Decommissioning & Removal of Reactor.Related Documentation & Certificate of Svc Encl ML20206N0171988-11-21021 November 1988 Joint Motion for Dismissal of Hearing Procedure.* Requests That Board Accept 881121 Settlement Agreement & Apps a & B, Dismiss Hearing Procedure & Return Request for Amend to License R-101 to NRC for Further Processing ML20205F5411988-10-25025 October 1988 Memorandum & Order.* Grants Addl Extension of 21 Days from Svc Date of Order for Stay of Proceedings,Per 881017 Joint Motion.Served on 881026 ML20205D6661988-10-17017 October 1988 Joint Motion to Stay Proceedings for Addl 21 Days & Order Thereon.* Univ of California Wishes to Have Matter Resolved by Settlement If Possible.Certificate of Svc Encl ML20154P4501988-09-27027 September 1988 Corrected Memorandum & Order (Granting Joint Motion to Stay Proceedings 30 Days).* Terms of Paragraph 8 of 880916 Joint Motion Shall Control in Event Settlement Not Achieved.Served on 880927 ML20154P3061988-09-22022 September 1988 Memorandum & Order (Granting Joint Motion to Stay Proceedings 30 Days).* Board Accepts That Terms of Paragraph 8 of Stipulation in 880916 Joint Motion Shall Control If Settlement Not Achieved.Served on 880923 ML20154G6981988-09-16016 September 1988 Joint Motion to Stay Proceedings for Addl 30 Days & Order Thereon.* Intervenor & Licensee Jointly Move for Stay of Proceedings,Including Intervenor Time to File Suppl Petition for Leave to Intervene.W/Certificate of Svc ML20154G6461988-09-13013 September 1988 Notice of Appearance of Counsel for Licensee.* Notifies That Author Will Appear on Behalf of Licensee in Proceeding. Certificate of Svc Encl ML20151N5721988-07-29029 July 1988 Notice of Reconstitution of Board.* Hf Hoyt Will Replace Sj Wolfe,Chairman & Go Bright & Ja Carpenter,Members.Served on 880801 ML20196A4141988-06-22022 June 1988 Order (Granting Licensee & Petitioner Joint Motion to Stay Proceedings).* Joint Motion Granted & Proceedings Stayed for 90 Days Unless Stay Earlier Dissolved as Provided in Paragraph 8 of Stipulation.Served on 880622 ML20197D9611988-05-25025 May 1988 Memorandum & Order (Interest of City of Berkeley).* City of Berkeley Established Interest/Standing in Proceeding & Requested to File Suppl to Petition to Intervene Listing Contentions for Litigation within 30 Days.Served on 880525 ML20154E5571988-05-10010 May 1988 Establishment of Aslb.* Board Constituted of Sj Wolfe, Chairman & Go Bright & Ja Carpenter,Members.Served on 880516 ML20154E2971988-05-0202 May 1988 NRC Staff Response to City of Berkeley Petition to Intervene & Request for Hearing.* City Upon Submission of Admissible Contention Satisfies Stds for Intervention & Should Be Granted Party Status,Per 10CFR2.714(b).W/Certificate of Svc ML20154E4991988-04-12012 April 1988 Petition to Intervene in License Amend Proceedings,Request for Hearings & Further Relief.* Requests Hearing & Seeks Leave to Intervene & Relief Re Proposed Issuance of Amend to License R-101,per 10CFR2.206(a) & 714 1989-09-12
[Table view] Category:ORDERS
MONTHYEARML20247F9911989-09-12012 September 1989 Order Authorizing Dismantling of Facility & Disposition of Component Parts,Per 880108 Application as Supplemented by 890131 & 0414 Ltrs ML20205F5411988-10-25025 October 1988 Memorandum & Order.* Grants Addl Extension of 21 Days from Svc Date of Order for Stay of Proceedings,Per 881017 Joint Motion.Served on 881026 ML20154P4501988-09-27027 September 1988 Corrected Memorandum & Order (Granting Joint Motion to Stay Proceedings 30 Days).* Terms of Paragraph 8 of 880916 Joint Motion Shall Control in Event Settlement Not Achieved.Served on 880927 ML20154P3061988-09-22022 September 1988 Memorandum & Order (Granting Joint Motion to Stay Proceedings 30 Days).* Board Accepts That Terms of Paragraph 8 of Stipulation in 880916 Joint Motion Shall Control If Settlement Not Achieved.Served on 880923 ML20196A4141988-06-22022 June 1988 Order (Granting Licensee & Petitioner Joint Motion to Stay Proceedings).* Joint Motion Granted & Proceedings Stayed for 90 Days Unless Stay Earlier Dissolved as Provided in Paragraph 8 of Stipulation.Served on 880622 ML20197D9611988-05-25025 May 1988 Memorandum & Order (Interest of City of Berkeley).* City of Berkeley Established Interest/Standing in Proceeding & Requested to File Suppl to Petition to Intervene Listing Contentions for Litigation within 30 Days.Served on 880525 1989-09-12
[Table view] |
Text
_ _ _ _ _ _ _ _ _ _ _ ___ __
, ( . .
[ .:'e if .
UNITED STATES,0F, AMERICA NUCLEAR REGULATORY C0FEISSION In the Matter of THE UNIVERSITY OF Docket No. 50-224
-CALIFORNIA, BERKELEY (Thc Berkeley TRIGA )
ResearchReactor) )
ORDER AUTHORIZING DISMANTLING OF FACILITY AND DISPOSITION OF COMPONENT PARTS _
By application dated January 8,1988, as supplemented on January 31, 1989 and April 14, 1989, the University of California, Berkeley (the licensee) requested authorization to dismantle the TRIGA research reactor facility, License No. R-101, located on the licensee's campus in Berkeley, California'and to dispose of the component parts, in accordance with the plan submitted as part of the application. A " Notice of Proposed Issuance of Orders Authorizing Disposition of Component Parts and Terminating Facility License" was published in the FEDERAL REGISTER on March 10, 1988 (53 FR 7823). The City of Berkeley filed a " Petition To Intervene In License Amendment Proceeding, Request for
. Hearings and Further Relief." The city and the licensee held discussions, arrived at a settlement agreement and filed a " Joint Motion For Dismirsal Of Hearing Procedure" with the Atomic Safety and Licenstr4g Board. The Board issued ar, Order on January 5,1989 to dismiss the proceeding.
1 1
F Cf ,
PhC 1 J
- o. .
.- i j
l The Nuclear Regulatory Comission (the Comission) has reviewed the application in accordance with the provisions of the Commission's rules and regulations and has found that the dismantling and disposal of component parts in accordance with the licensee's dismantling plan will be in accordance with the regulations in 10 CFR Chapter I, and will not be inimical to the comon defense and security or to the health and safety of the public. The basis of these findings is set forth in the concurrently issued Safety Evaluation by the Office of Nuclear Reactor Regulation.
The Comission has prepared an Environmental Assessment and Finding of No Significant Impact for the proposed action. Based on that Assessment, the Comission has determined that the proposed action will not result in any significant environmental impact and that an environmental impact state-ment need not be prepared.
Accordingly, the licensee is hereby ordered to dismantle the TRIGA reactor facility covered by License No. R-101, as amended, and dispose of the component parts in accordance with its dismantling plan and the Commission's rules and regulations.
After completion of the dismantling and disposal, the licensee will submit a report on the radiation survey it has performed to confirm that radiation and surface contamination levels in the facility area satisfy the values specified in the dismantling plan and in the Commission's guidance. Following an inspection by representatives of the Comission to verify the radiation and contamination levels in the facility, consideration will be given to issuance of a further order terminating Facility License No. R-101. l 1
I
~ . _ _ _ - _ - _ . - - _ _ . . . _ _ _ . . -
M ; y; m.*
- e l b -' l l
l For further details with respect to this action, see: (1)thelicensee's application for authorization to dismantle the facility, dispose of component parts, and terminate Facility License No. R-101, dated January 8,1988, as .
supplemented;-(2) the Comission's Safety Evaluation; and (3) the Environmental Assessment and Finding of No Significant Impact. All of these items are avail-able for public inspection at the Commission's Pcblic Document Room, 2120 L Street, N.W., Washington, D. C. Copies of items (2) and (3) may be obtained upon request addressed to the U. S. Nuclear Regulatory Commission, Washington, D. C. 20555, Attention: Director, Division of Reactor Projects - III, IV, Y and Special Projects.
Dated at Rockville, Maryland this 12th day of September 1989.
FOR THE NUCLEAR REGULATORY COMMISSION VE YDivision Gary}M. Hol an, Acting Director of Reactor Projects - III, IV, Y and Special Projects Office of Nuclear Reactor Regulation
(