Monthly Operating Repts for Apr 1998 for Vogtle Electric Generating Plant,Units 1 & 2
ML20247F384
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/30/1998
From: Hargis T, Woodard J
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LCV-1169-D, NUDOCS 9805190318
Download: ML20247F384 (7)


Text

- - _ _ _ _ -

l J. D.Woodard Southern Nuclear Exccutive Vice President Operating Company. loc.

40 invemess Center Parkway l

Post Office Box 1295 Birminghem. Alabama 35201 Tel 205.992.5080 SOUTHERN h COMPANY Energy to Serve nurWorld" May 11, 1998 LCV-1169-D Docket Nos.

50-424 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555 Gentlemen:

VOGTLE ELECTRIC GENERATING PLANT MONTHLY OPERATING REPORT-APRIL 1998 Enclosed are the April 1998, monthly operating reports for Vogtle Electric Generating Plant (VEGP) Units 1 and 2. These reports are submitted in accordance with the Technical j

Specification 5.6.4.

{

Sincerely, k

(

J.

Woodard CKM/JLL Enclosures El-VEGP Unit 1 Monthly Operating Report - April 1998 E2-VEGP Unit 2 Monthly Operating Report - April 1998 cc:

Southern Nuclear Onerating Comnany Mr. J. B. Beasley, Jr.

Mr. M. Sheibani NORMS

... [, Oi 3 U. S. Nuclear Reculatory Commission Mr. L. A. Reyes, Regional Administrator Mr. D. Jaffe, Senior Project Manager, NRR Mr. J. Zeiler, Senior Resident Inspector, Vogtle l

b

!,/

l 9005190318 990430 L

DR ADOCK O 4y4

l-

. i L

1' ENCLOSURE 1

[

VOGTLE ELECTRIC GENERATING PLANT - UNIT 1 MONTiiLY OPERATING REPORT FOR APRIL 1998 TABLE OF CONTENTS I

OPERATING DATA REPORT and CilALLENGES to PORV and SAFETY VALVES Page El-1 UNIT SHUTDOWNS and NARRATIVE REPORT Page El-2 4

f' L

l L.-.~--.--..-__---

  • OPERATIN3 DATA REPORT Dicket No.:

50-424 Unit Name:

VEGP UNIT 1 Date:

May 4,1998 Completed By:

T.S. Hargis Telephone:

(706)826-3469 Opatating. Status

1. Reporting Period:

Apr-98

2. Design Electrical Rating (Net MWe):

1169

3. Maximum Dependable Capacity (Net MWe):

1162 This Month Year To Date Cumulative

4. Number Of Hours Reactor Was Critical:

719.0 2879.0 83,851.0

5. Hours Generator On Line:

719.0 2879.0 82,553.8

6. Unit Reserve Shutdown Hours:

0.0 0.0 0.0

7. Net Electrical Energy Generated (MWHe);

843.831 3.398,911 90,861,223 CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAJETY VALVES Date Tag No.

Event Description N/A N/A N/A l

i E1-1 l

l

' UNIT SHUTDOWNS Docket No.:

50-424 Unit Name:

VEGP UNIT 1 Date:

May 4,1998 Completed By:

T.S. Hargis Telephone:

(706)826-3469 Reporting Period:

Apr-98 Type Method of F: Forced Duration Shutting Cause/ Corrective Actions

{

S: Scheduled No.

Date (Hours)

Reason (1)

Down (2)

Comments NA NA NA NA NA NA NA (1) REASON:

(2) METHOD:

A - Equipmert Failure (Explain) E - Operator Training /Ucense Examination

1. Manual
4. Continuation B Maintenance or Test F-Adrrunistrative
2. Manual Trip / Scram
5. Other C - Refueling G - Operational Error (Explain)
3. AutomaticTrip/ Scram D - Regulatory Restriction H - Other (Explain)

CAUSE/ CORRECTIVE ACTION / COMMENTS:

NARRATIVE REPORT March 0100:00 Unit 1 at 100% power with no operating problems.

March 3123:59 Unit 1 at 100% power with no operating problems.

l l

E1-2

l

/

l..

n o

L i

l ENCLOSURE 2 VOGTLE ELECTRIC GENERATING PLANT-UNIT 2 MONTHLY OPERATING REPORT FOR APRIL 1998 TABLE OF CONTENTS OPERATING DATA REPORT and CHALLENGES to PORV and SAFETY VALVES

. Page E2-1 UNIT SHUTDOWNS and NARRATIVE REPORT Page E2-2 L

l k

l t

I

._----a

l,*

OPERATIN3 DATA REPORT Docket No.:

50-425 Unit Name:

VEGP UNIT 2 l

Date:

May 4,1998 Completed By:

T.S. Hargis Telephone:

(706) 826-3469 OperatingEtatus -

1. Reporting Period:

Apr-98

2. Design Electrical Rating (Net MWe):

1169

3. Maximum Dependable Capacity (Net MWe)'.

1167 This Month Year To Date Cumulative

4. Number Of Hours Reactor Was Critical:

281.4 1865.8 70.689.6

5. Ho. '. Generator On Line:

254.9 1838.9 69.998.2

6. Una Heserve Shutdown Hours:

0.0 0.0 0.0

7. Net Electrical Energy Generated (MWHe):

243,439 2,036,632 77.623,358

{

CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAFETY VALVES Date Tag No.

Event Description l

NA NA NA I

i I

E2-1 l

}

UNIT SHUTDOWNS Docket Nz.:

50-425 Unit Name:

VEGP UNIT 2 l'

Date:

May 4.1998 1

)

Completed By:

T.S. Hargis Telephone:

(706)826-3469 l

Reporting Period:

Apr-98 t

I Type Method of F: Forced Duration Shutting Cause/ Corrective Actions s: scheduled No. '

Date (Hours)

Reason (1)

Down (2)

Comments 98-1 3/8 S

457.5 C

4 SEE BELOW 98-2 4/20 S

5.1 B

1 SEE BELOW 98-3 4/21 F

15 B

1 SEE BELOW (in REASON:

(2) METHOD:

j A - Equipment Failure (Erplein) E - Operator Training 4.icense Examination

1. Manual
4. Continuation B -Maintenance or Test F - Admin 6strative
2. Manual Trip / Scram
5. Other C - Refueling G -Operational Error (Explain)
3. Automatic Trip / Scram D Regulatory Restriction H - Other (Explain)

CAUSE/ CORRECTIVE ACTION / COMMENTS:

EVENT 98-1 CAUSE.

Scheduled Refueling Outage CORRECTIVE ACTION:

Guide Tube Support Pin Replacement.

J CRITICAL PATH WAS:

Completed S/G Eddy Current Testing on 2 & 3. Reloaded fuel, installed upper intemals and reinstalled reactor vessel head. Tensioned head and completed reassembly. Began heatup and mode ascension from mode 5 to mode 1. Performed appropriate functional testing in each mode, raised power after entering mode 1, and closed breaker.

EVENT 98-2 CAUSE.

Turbine Overspeed Trip Test CORRECTIVE ACTION:

Turbine test completed and unit retumed to service.

EVENT 98-3 CAUSE.

Repair ground in voltage regulator CORRECTIVE ACTION:

Ground repaired and unit retumed to service.

NARRATIVE REPORT April 01 00:00 Unit 2 defueled April 08 04:01 Unit 2 entered mode 6.

April 14 04:21 Unit 2 entered mode 5.

April 1615:11 Unit 2 entered mode 4.

April 17 05:20 Unit 2 entered mode 3.

April 19 03:00 Unit 2 entered mode 2.

April 19 06:34 Unit 2 reactor critical.

April 19 22:56 Unit 2 entered mode 1.

April 20 02:29 Unit 2 generator tied to grid.

April 20 14:37 Unit 2 turNne tripped for overspeed test.

April 2019:41 Unit 2 generatortied to grid.

f April 21 17:03 Unit 2 turbine tripped to take generator offline to repair ground in voltage regulator.

April 21 18:33 Unit 2 generator tied to grid.

r f

April 25 06:32 Unit 2 retumed to 100%.

April 30 23 59 Unit 2 at 100% cower with no operatino problems l