_ _ _ _,
TDLEDO
%ms EDISON' EDISON PLAZA j
300 MADISON AVENUE TOLEDO. OHIO 43652 0001 Do'cket Number 50-346 License Number NPF-3 Serial Number 1-887 June 29, 1989 bhited States Nuclear Regulatory Commission Do:ument Control Desk Vashington, D. C.
20555 Subj ect : Response to Nuclear Regulatory Commission (NRC) Systema,ic Assessment of License Performance (SALP) Board Report (?nspection Report Number 50-346/88001)
Gentlemen:
The NRC issued the SALP 7 Report for the Davis-Besse Nuclear Power Station (DBNPS) on April 25, 1989. This report covers the period of January 1, 1988, through February 28, 1989. On May 30, 1989, the NRC presented this report to Toledo Edison in a public meeting held at the Davis-Besse site.
Toledo Edison Company has reviewed the SALP 7 Report and discussed the specifics of the SALP ratings in a management meeting held at the NRC Region III offices in early Hay. Toledo Edison has no further comments to provide.
The Company believes the SALP 7 report reflects continued improvement in performance at Davis-Besse. Ongoing efforts vill assure that the improving trend continues.
Should there be any questions, please contact Mr. R. V. Schrauder, Nuclear Licensing Manager, at (419) 249-2366.
Very truly yours,
/[A,
EBS/dlm 1
cc P. M. Byron, DB-1 NRC Senior Resident Inspector j
t A. B. Davis, Regional Administrator, NRC Region III l
T. V. Vambach, DB-1 NRC Senior Project Manager
'8907070130 890629
/