Forwards Replacement Page to NRC Second Status Rept Re Settlement Agreement,Correcting Date for Followup Meeting Referrred to in Text of Rept,Filed on 890428
ML20245L456
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 05/01/1989
From: Rutberg J
NRC OFFICE OF THE GENERAL COUNSEL (OGC)
To: Bright G, Cole R, Frye J
Atomic Safety and Licensing Board Panel
References
CON-#289-8559 OLA, NUDOCS 8905080044
Download: ML20245L456 (2)


Text

&W. 5$ 'If$fffb UNITED STATES j.4 4 g NUCLEAR REGULATORY COMMISSION E WASHINGTON, D. C. 20555

g, . ;
  • % , , , , , / MAY 01 1989

~89 MAY -3 All :15 in % -

t 00cx% 4 it ; d BMNCH John H. Frye, III, Chairman Glenn 0. Bright Administrative Judge Administrative Judge  !

Atomic Safety and Licensing Atomic Safety and Licensing Board Panel Board Panel U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Washington, D.C. 20555 Richard F. Cole Administrative Judge  !

Atomic Safety and Licensing '

Board Panel U.S. Nuclear Regulatory Commission '

Washington, D.C. 20555 l

In the Matter of PHILADELPHIA ELECTRIC COMPANY (Peach Bottom Atomic Station Units _2 and 3)

Dear Administrative Judges:

On April 28th, 1989, the Staff filed a document before the Atomic Safety and Licensing Board titled "NRC STAFF SFCOND STATUS REo0RT CONCERNING SETTLENENT AGREEMENT." Unfortunately, the date for the follow-up meeting referred to in the text of the Status Report is incorrectly shown. The follow-up meeting was held on April 28, 1989. Attached is a replaceinent page which we are asking you to insert in the copies you received. We regret any inconvenience that may have teen caused by tris error.

Sincerely, ,

k j 't '

ph utberg eputy Assistant General Counsel for Hearings

Attachment:

As Stated cc w/

Attachment:

Service List i

G b30Y l

I.

l April 28, 1989 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of PHILADELPHIA ELECTRIC COMPANY ) Docket Nos. 50-277 OLA 50-278 OLA (Peach Bottom Atomic Station l Units 2 and 3) )

NRC STAFF SECOND STATUS REPORT CONCERNING SETTLEMENT AGREEMENT I. INTRODUCTION On March 27, 1989, the Atomic Safety and Licensing Board issued a Memorandum and Order in which it, among other things, directed the NRC staff to file a monthly report indicating the status of the Staff's review of the settlement agreement between Philadelphia Electric Company (PE) and the Commonwealth of Pennsylvania. The Staff herein provides its second status report. I II. STATUS REPORT In a follow up to the staff's March 29, 1989 letter to the Commonwealth and PE, the staff met on April 18, 1987 with representations of the parties to pursue resolution of the concerns previously identified by the staff. A follow up meeting was held on April 28, 1989.