ML20245A215

From kanterella
Jump to navigation Jump to search
Monthly Operating Repts for May 1989 for Trojan Nuclear Plant
ML20245A215
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 05/31/1989
From: Ulmer F, Yundt C
PORTLAND GENERAL ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CPY-118-89, NUDOCS 8906210151
Download: ML20245A215 (5)


Text

.i.

{/ g. . 4.

.m amut ,(

h~

[

Portland General Electric Conipany Trojan Nuclear Plant-

- 71760 Columbia River llwy.

Rainier, Oregon 97048 (503) 556-3713 '

June 6, 1989 CPY-118-89 i-US Nuclear Regulatory Commission Document Control.-Desk

~ Washington, DC .20555 Gentlemen:

Monthly Operatina Report In accordance with the Trojan Nuclear Plant Technical

' Specifications reporting requirements, the Monthly Operating Data:

Report is submitted for May, 1989. ~l

\

Sincerely, sk C. P. Yundt General Manager fv" CPY:sp

-Attachment c: Mr. John B. Martin /

Regional Administrator, Region V US Nuclear Regulatory Commission Mr. William T. Dixon 1 Department of Energy State of Oregon Resident Inspector MOR Distribution 8906210151 890531 PDR ADOCK 05000344 R PNU u '

Portland General Electric k , Nuclear Division L TROJAN NUCLEAR PLANT p 1

lJJ . . .

Trojan Operating Report May 1989 OPERATIONS The plant began the month in Mode 6, with the reactor defueled and

. preparations for refueling in progress. Preparations were in progress for the lifting of the reactor vessel head and the commencement of refueling operations.

Fuel reload commenced on May 11. The reload was completed on May 16.

Eddy Current testing on the four steam generators was begun May 22 and continued through the end of the month.

Reactor Coolant Pump flange bolt work was commenced on April 29 and in

. progress at the end of May.

Earlier inspection of the main generator rotor bars disclosed an' unacceptable amount of copper dust and flakes. The generator has been cleaned and is being reassembled with new slot insulation and separators between bars to correct the copper dusting problem. Inspection of the high pressure turbine identified the need for extensive repairs of the diaphragms due to erosion at the blade roots. The repairs to the diaphragms are complete. Turbine

.rer.ssembly continued through the end of the month.

On April 25, in-service inspection of the reactor vessel was begun. It was.

completed on May 8. An indication was discovered in the "A" loop nozzle to

-vossel weld. Examination has determined that is within code allowable limits.

Westinghouse 1.as completed an analysis providing additional assurance that the flaw is acceptable.

l l Testing of Electrical Penetration connections comieenced on May 3. .A number of I

electrical cable wires had pulled loose from a containment electrical penetration assembly during seal replacement. Several more connections pulled-loose during testing and the scope of the work was increased to test more connections. The testing continued through the end of the month.

Flux thimble testing was conducted from May 21 to May 25. Several tMmbles have unacceptable amounts of thinning in their walls. The requiref mrrective actions are under evaluation.

The plant ended the month in Mode 5, with the reactor refueled.

MAINTENANCE

, Significant maintenance completed during this period includes:

1 Replacement of degraded cables inside containment.

Repair of the 30 inch main feed water header.

Repair of the main condenser water box joints.

d APPROVED [PlantGeneralManag[r

//, -

L Trojan Excellence- 0 Way of Doing Business

J t j- -.-

7 W .

OPERATING DATA REPORT DOCKET NO. 50-344 DATE _ June.1989 COMPLETED BY : F. J. Ulmer TELEPHONE 503-556-371'3

-Ext. 495 OPERATING STATUS

" Trojan Nuclear Plant ' Notes Line 14 cumulative.

1. Unit Neme:

May 1989 incorrectly reported as

2. Reporting Period: 686949 on March 1989 report, 3411
3. Licensed Thermal Power (MWt): should be 68694.9
4. Nameplate Rating (Gross MWe): 1216
5. Design Electrical Rating (Net MWe):

1130

- 6. Maximum Dependable Capecity (Gross MWe):

1153 1095 7.' Maximum Dependable Capacity (Net MWe):

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Gin Reasons:

N/A-

- 9. Power Level To Which Restricted,1f Any (Net MWe): N/A

10. Reasons For Restrictions,if Any: N/A .

1Ms Month Yr to Date Commistive 744 3623 '111743

11. Hours In Reporting Period .

0 2280.4 69559.4

12. Naaher Of Hours Reactor Was Critical 0 0 3387
13. Reactor Reserve Shutdown Hour 0  ??s0.4 ggnig_q
14. Hours Generster On4.ine 0 0 3249-15.' Unit Reserve Shutdown Hours 73934gggg 0 77449g5
16. Geons Tlurmal Energy Generated (MWH) 0 9610499 721goozn
17. Geons Electncal Energy Generated (MWH) ,,_,

-3069 2497839 68365909

18. _ Net Electrkal Energy Generated (MWH) 0 62.9 61.6
19. Unit Service Factor 0 62.9 64.5
20. Unit Availability Facto, _

-.4 63.0 57.2 21.' Uait Capacity Fac' tor (Using MDC Net)

-A 61.0 54.1

22. Unit Capscity Factor (Using DER Net) 0 0 13.4
23. Unit Forced Ostage Rate
24. Shutdowns Scheduled Over Next 6 Months (Type. Dete. and Duration of Eacht:
25. If Shut Down At End Of Report Period. Estimated Date of Startsp:

Late June 1989

26. Units in Test Status (Prior to Comenercial Operation): Forecast Achiewd N/A N/A INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION (Q/77)

1  ; ,; ..

  • ~

-c .

l- AVERAGE DAILY UNIT' POWER LEVEL l

c DOCKET NO: 50-344

! . UNIT: Trojan

. DATE: June.1989 COMPLETED BY:_F . J. Olme r --

V TELEPHONE: sn1 ss6.1711-

ext 495'

' MONTH 'May. 1989

' DAY AVERAGE DAILY POWER LEVEL DAY ' AVERAGE DAILY POWER LEVEL (MWe-Net) ~(MWe-Net)'

1- -4 17' -4:

2 -4 18 ,

3 -4 .19 -4

-4 -4 20. -5 5 -3 21 -5 6 -4 22 ,

-5 7 -4 23 -5 8 -4 '24 -5 9

-4 25 -4 10 -4 26 -4 i

11. -4 27 -5

~

12 >4 28 -4 13 -4 29 -4 14 -4 30 -5 15 -3 31 -5 16 -4 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

(4/77)

,' ll] 1 3 -

r 1 G 7 E 9 R 8 l U 9

1 i

t 6 5 N 4 n 5 9 s

eei (c n . 5 e 4

3 i- b 1 1

ntamF oaeI l c r

n n u 0

r Ju -

3 0

t x iDcJR t

c oTIE S o

5 T E 5- e e e 's ' .e i

v c n

t s

'rL nf ot-n

.EEYE t

s e e nois e t

i s

O MTBN e ,, u e

r r g I. tset n- S N A ADO w,e C,,R c t a

u G he ep I

T E NDEH O i t

b ;.yt) rS R i t

K IT TEPEL A ,t t e3n g hi7r n1 x r nv1e6 b

i h

CN t

L E s e n o x OU P u a

v EfEE0 -E M T

. i D C p, l O e 4 5'

.- C u f

e R

l a

u n ,

n A .

S .

N m O

I L m. sc;)n i T " - eSi s r ep C j= g cl m U 9 SeE s D 8 il E 9  :

doo s e m oe(r R 1 onnth haaut

.R E y

  • .yu - tMMAO e - - - -

W M a !ge MI2J4 O _

F 3 6

D 1 T

N N

.A S O '

  • N M "t t W T "nr eo vp O R m D

T O

P

.d' ERe ht s

U E a f

i R d n

S o x

T E N

I "L3.U:a e5g6 [6 5 1

)

n ,

e s

p n

U l i

a n e

i s

's 35[: - p c f p

x E nU o m (t i E es e s tA e (

  • eINE c

C oT l

e g

n g

u f

lf t

si r) i ao enet RisEi t

a Fe ai rll l

. 5E.0 4 nn yT t c eagort v oE nx a a p r

4 s e5$0 7 mnint pt el el aiaat nt oii( i ninu o uif sqa e e pd pt ur gemre ic t

aEMRROAOO e - - - - - T - -

3._@ 5 RABCDEIGt I 2

6 0

e 3 i, 0 p 9 8

d l

e du ed ce sh u c 9 FS )

8  : :

7 F5 7 w 2 0

1 1

8 r

ll ll! iI l!If