Forwards Vols 1 & 2 to Book 1 & Vol 2 to Books 2,3 & 4 to Independent Design & Const Assessment. Assessment Concludes That Facility safety-related Sys & Structures Complies W/Licensing Commitments & Technically Adequate
ML20245A069
Person / Time
Site: Limerick Constellation icon.png
Issue date: 04/18/1989
From: Kemper J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20245A071 List:
References
NUDOCS 8904250035
Download: ML20245A069 (2)


Text

- _ . _ __ - .

j

.p

[*'_,;+

PHILADELPHIA ELECTRIC COMPANY 2301 M ARKET STREET P.O. BOX 8699 PHILADELPHIA A. PA.19101 1215)641 4500 i

, _ Ja n . = % . 1 APR 181989 l U. S. Nuclear Regulatory Corrmission Docket No. 50-353 Attn: . Document Control Desk Washington, DC 20555 i

Subject:

Limerick Generating Statlon, Unit 2 Independent Design and Construction Assessment Gentlemen: ,

i Enclosed for your information is the Design Assessment Report for Limerick Generation Station (LGS), Unit 2 documenting the results of the Independent Design Assessment (IDA) portion of the Independent Design and Construction Assessment (IDCA) performed by Stone and Webster Engineering Corporation for Philadelphia Electric Company (PEco). The assessment concludes "that the Limerick 2. design of safety-related svstems and .

structures compiles with Ilcensing commitments and is technically adequate."

However, this conclusion is based upon satisfactory completion of remaining committed project actions e.ad resolution of six open items.

Also enclosed is the IDCA Assessment Summary Report which provides an overall sunnary of this activity. These reports, Volumes II and I, respectively, complement. Volume'III, the Construction Assessment Report, submitted on February 10, 1989. Together, these reports conclude that the design and construction process employed for Limerick 2 is an acceptable.

process. This conclusion is also contingent upon the items described above for the Design Assu sment Report conclusions.

PECo's preliminary review of.this report, along with our understanding of the issues identified, Indicates that the IDCA has provided additional

. confidence that Limerick Unit 2 will soon be ready to be licensed and placed in operation.

Inspection Report 50-353/88-203 dated April 4, 1989, requested PECo to address the findings of the NRC IDA tear,in a written response to the In-spection report. PECo is currently preparing such a response for Unit 2 and expects to submit that response no later than May 5, 1989 FBr 22882n 838 A

PDC f

w t .

Please let me know if you have any questions regarding this submittal or require additional information.

Sincerely,

,k $ /C!~.

u

Enclosures:

Volune I (1 book)

Volume II (4 books)

ERG /dk/041789 Copy to: T. J. Kenny, LGS Senior Resident Inspector W. T. Russell, Region I Administrator R. J. Clark, LGS Project Manager i