ML20244E631

From kanterella
Jump to navigation Jump to search
Staff Requirements Memo Re Commission 890602 Briefing on Status of Tech Spec Improvement Program for Improving Operational Safety at Nuclear Power Plants
ML20244E631
Person / Time
Issue date: 06/16/1989
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Parler W, Stello V
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO), NRC OFFICE OF THE GENERAL COUNSEL (OGC)
References
REF-10CFR9.7 M8890602, NUDOCS 8906210026
Download: ML20244E631 (2)


Text

.

e#

0 g

UNITED STATES IN RESPONSE, PLEASE y'

NUCLEAR REGULATORY COMMISSION REFER TO:

M890602 S

,j W ASHIN GTON, D.C. 20555 e-q j

^%

  • ...+

OF FICE OF THE June 16, 1989 SECRETARY MEMORANDUM FOR:

Victor Stello, Jr.

Executive Director for Operations William C.

Parler, Genera Counsel FROM:

Samuel J. Chilk, Secreta :Ng y

SUBJECT:

STAFF REQUIREMENTS - BRIFF{NG ON STATUS OF l

TECHNICAL SPECIFICATIONS IMPROVEMENT PROGRAM, 9:30 A.M.,

FRIDAY, JUNE 2,

1989, COMMISSIONERS ' CONFERENCE ROOM, ONE WHITE.

FLINT NORTH, ROCKVILLE, MARYLAND (OPEN TO PUBLIC ATTENDANCE)

The Commission was briefed by the staff on the status of the i

technical specifications improvement program for improving operational safety at nuclear power plants.

The Commission encouraged the staff to continue working with industry toward adopting a uniform standard for performing safety evaluations under the 10 CFR 50.59 regulation.

The Commission also cautioned the staff not to divert the present high caliber staff working on the technical specification improvement program to cover " brush fires" and thereby sacrifice the momentum developed in this important safety enhancement program.

Commissioner Carr requested the staff to provide the number of technical specification changes submitted by licensees and the number approved by the staff under the line-item improvements review program.

(EDO)

(SECY Suspense:

7/21/89)

Commissioner Rogers requested the staff to continue efforts to develop and implement the risk based technical specification program and to consider ways to link such a program at power plants.

The staff offered to brief the Commission'on this program at a later date after tha program is sufficiently developed.

l (EDO)

(SECY Suspense:

TBD) l 7

Qf0 8906210026 890616 PDR 10CFR f '

PDC PT9.7

(

Subsequent to the meeting, the Commission requested the staff, in coordination with OGC, to address if a licensee's implementation of the new standard technical specifications involves a significant hazards evaluation.

(EDO/OGC)

(SECY Suspense:

9/29/89) cc:

Chairman Zech Commissioner Roberts Commissioner Carr Commissioner Rogers Commissioner Curtiss GPA PDR - Advance DCS - P1-24 5

- - - - - - - - - - - - - - - - - - - - - -