Text
_
MAY 5 1986 Docket No. 50-289 MEMORANDUM FOR: Harry Kister, Chief l
Projects Branch No. 1 FROM:
Allen R. Blough, Chief Reactor Projects Section IA
SUBJECT:
TMI-1 STATUS REPORT FOR THE PERIOD April 25 - May 2,1986 Enclosed is the TMI-1 weekly status report from the NRC Resident' Office at TMI-1.for the subject period. Following the repair of a steam line drain leak, the plant was returned to full power.
The NRC staff followed the power in-crease and continued to monitor routine plant operations.
TMI-1 status reports are intended to provide NRC management and the public with z
- highlights from an NRC regulatory perspective of TMI-1 activities for the pre-vious week. Subsequent inspection reports will address many of these topics in more detail.
Original signed g,
y Allen R. Blough, Chief Reactor Projects Section_1A Branch 1, DRP
Enclosure:
As stated 5
86 PD,("=kK050002e9 B B6050S R
1 PDR OFFICIAL RECORD COPY TMI WEEKLY STATUS ITEMS - 0001.0.0 11/29/80. T/ ly b
Memorandum for Harry Kister 2
cc w/ enclosure:
F. Miraglia, NRR W. Travers, NRR J. Thoma, NRR J. Partlow, IE T. Gerusky, BRP/ DER, Commonwealth of Pennsylvania R. Benko, Governor's Office of Policy,' Commonwealth of Pennsylvania TMI Alert.-
-Susquehanna Valley Alliance Friends & Family of TMI Public Document Room Local Public Document Room bec w/ enclosure:
K. Abraham, RI P. Lohaus, RI R. Starostecki, RI H. Kister, RI R. Conte, RI (20 cys)
Region I Docket Room (w/ concurrences)
Q q
RI:DRP RI:DRP RI: RP
. E r Conte Blough Kister 5/ f/86 5/E/86 5/ $'/86 0FFICIAL RECORD COPY TMI WEEKLY STATUS ITEMS - 0002.0.0 11/29/80
F ENCLOSURE TMI-1 STATUS REPORT FOR THE PERIOD April 25 - May 2,1986 1.
Plant Status As of 8:00 a.m. on May 2,1986, TMI-1 was operating at 100 percent power and at normal reactor coolant temperature and pressure.
2.
Facility Operations Summary
'At the. start of the report period, the plant was being maintained at 3-5 percent with the main turbine isolated in order to make a repair to a
~
steam line drain.. Following the completion of the repair at approximately
~
10:00 a.m. on April 25, a power escalation began. Full power was achieved at 9:50 p.m.. on April 26. The plant was maintained at full power during the remainder of the report period.
3.
Items of Special Interest Fire Protection Safety Evaluation Meeting On May 1 and 2,1986, a meeting with licensee representatives was held on site by a NRR fire protection engineer from the NRC Office of Nuclear
)
Reactor Regulation (NRR) and a Region I fire protection inspector to discuss matters associated with the 10 CFR 50 Appendix R fire protection safety evaluation report.
4.
NRC Staff Status During the Period During this report period, the NRC staff consisted of the senior resident
' inspector and three resident inspectors and was supplemented by a regional inspector while the resident inspectors were attending a Region I Resident Inspector Ccunterpart Meeting in King of Prussia, Pennsylvania.
'The NRC staff at TMI-1 was comprised of the following personnel during the
~
period:
W. Baunack, Project Engineer R. Conte, Senior Resident Inspector C. Hix, Secretary D. Johnson, Resident Inspector J.' Rogers, Resident Inspector F. Young, Resident Inspector Fire Protection Meeting A. Krasopoulos, Reactor Engineer, Region I D. Kubicki, Fire Protection Engineer, NRR OFFICIAL RECORD COPY TMI WEEKLY STATUS ITEMS - 0003.0.0 11/29/80