NRC 2019 Annual Assessments Fermi-2 Nuclear Power Plant For Audio, please dial: 888-843-6164 Passcode: 2755515 To contact the operator or ask a question at the end of the presentation, dial *1
Host Néstor J. Féliz Adorno Branch Chief Division of Reactor Projects Branch 4
Purpose Discuss Fermi-2 Nuclear Plants performance in 2019 Discuss the COVID-19 response as it relates to the oversight of Fermi-2 Nuclear Plant
About the NRC The NRC licenses and regulates the Nations civilian use of radioactive material to achieve the following goals:
- Safety - Ensure adequate protection of public health and safety and the environment
- Security - Ensure adequate protection of the secure use and management of radioactive materials
Reactor Oversight Process (ROP)
Safety/Security Significance
ROP Action Matrix Licensee
Response
Regulatory
Response
Degraded Performance Multiple/Repetitive Degraded Cornerstone Unacceptable Performance Increasing:
Safety Significance Inspection Management Involvement Regulatory Action
Fermi-2 Resident Inspectors Thomas Briley Senior Resident Inspector Thomas Taylor Resident Inspector
2019 Annual Assessment Fermi-2 The plant operated safely Licensee Response Column All performance indicators were Green 15 Green inspection findings
2019 NRC Inspections Fermi-2 3906 hours0.0452 days <br />1.085 hours <br />0.00646 weeks <br />0.00149 months <br /> of direct inspection 15 regional inspections 5 major team inspections Design Bases Assurance Inspection (Teams)
Force-on-Force Testing Biennial Problem Identification and Resolution Inspection Cyber Security Inspection Special Inspection
NRC Response to COVID-19 Maintained mission critical functions Monitored plant activities Maintained emergency response capabilities Risk-informed "eyes on" inspections through residents and regional inspections Expanded use of telework Coordinated actions with industry on best practices For more information visit:
https://www.nrc.gov/about-nrc/covid-19/reactors/
NRC Plans for 2020 NRC plans baseline inspections at Fermi-2 Nuclear Plant for the remainder of 2020.
NRC Social Media Channels Facebook:
https://www.facebook.com/nrcgov/
Twitter:
https://twitter.com/nrcgov YouTube:
http://www.youtube.com/user/NRCgov Flickr:
http://www.flickr.com/photos/nrcgov/
LinkedIn https://www.linkedin.com/company/u-s--nuclear-regulatory-commission/
Meeting Feedback
- 1. On Any Device or Computer:
- Go to the Public Meeting Schedule at (www.nrc.gov/pmns/mtg?do=recent30days)
- Locate this meeting using the sorting buttons and click on the Meeting Feedback Form link.
Note: Meetings are sorted by date and time. Use Last to get to todays date.
- or -
- 2. Scan QR Code with smart device
Questions In order to ask a question please dial *1 Public Affairs Prema Chandrathil Public Affairs Officer 630-829-9663 Prema.Chandrathil@nrc.gov Viktoria Mitlyng Senior Public Affairs Officer 630-829-9662 Viktoria.Mitlyng@nrc.gov NRC Response to COVID-19: https://www.nrc.gov/about-nrc/covid-19/reactors/