Forwards Digital Metal Impact Monitoring Sys Baseline Data Acquisition Summary for Vogtle Unit 1, Per Util . Rept Provides Documentation of Sys Sensitivity,Bases for Sys Settings & Simulated Loose Parts Impact Data
ML20238D547
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 09/04/1987
From: Gucwa T
GEORGIA POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
Shared Package
ML20238D550 List:
References
SL-3157, NUDOCS 8709110246
Download: ML20238D547 (2)


Text

_ _ - _ _ . _ _ . -. _ _ - _ _ _ _ .

_ Georgia Power Company

' 333 Piedmont Avenue Y Atlanta, Georgia 30308

' Telephone 404 526-6526 Maihng Address:

Post Ottice Box 4545 Atlanta, Georgia 30302 h Georgia Power Ma age Nuclear Safety

.and Licensing SL-3157 0494m l

X7GJ17-V200 September 4, 1987 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Hashington, D.C. 20555 PLANT V0GTLE - UNIT.1 NRC DOCKET 50-424 OPERATING LICENSE NPF-68 DIGITAL HETAL IMPACT MONITORING SYSTEM (DMIMS)

Gentlemen:

By letter GN-1349 dated February .24, 1987, Georgia: Power Company (GPC) provided a report describing the design, operation, and testing status of' the DMIMS. In 'that report GPC committed to provide. a supplemental report (final baseline signature report) of the necessary data collected at the 1001. power level. The enclosed Westinghouse report is submitted in accordance with that commitment. The. report contains the following information:

1. documentation of system sensitivity in accordance with Regulatory Guide 1.133,
2. bases for recommended system settings, 3.- simulated loose parts impact data and other background information to allow GPC personnel to evaluate suspected impacts, and
4. illustration and tabulation of accelerometer signals at the 1001.

power level for verification of the signal train integrity and .

detection of signal degradation.  !

Letter GN-1349 provided discussions of procedures which provide instructions to plant personnel for operation of the DMIMS. The following procedure will be used in addition to the ones already described:

M Procedure 54084-C, "DMIMS Data Analysis and Comparison", provides instructions for engineering response to an alarm generated by the DMIMS. This procedure also provides instructions for audio monitoring every 7 days as a backup to daily surveillance and i background noise comparison every 92 days as recommended in f Opl Regulatory Guide 1.133.

B709110246 870904 PDR ADOCM 05000424 P PDR- , _ ___ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

'E b b' Ii g3S ggy S0-ogygg

T 3 i

GeorgiaPower A i

U. S. Nuclear Regulatory Commission -l September 4, 1987  ;

Page:Two i

~This submittal . completes GPC's licensing- commitments regarding DMIMS, Please contact this office if you have any questions.

Sincerely, i

gn=

L. T. Gucwa JH/im

Enclosure:

DMIMSl Baseline Report c: Georaia Power Company Mr. R. E. Conway w/o enclosure Mr. J, P. O'Reilly w/o enclosure Mr._G._Bockhold, Jr. w/o enclosure Mr. J. F. D'Amico w/o enclosure Mr. C. H. Hayes w/o enclosure GO-NORMS w/o enclosure Sputhern Company Services Mr. R. A. Thomas w/o enclosure Mr. J..A. Bailey w/o enclosure Shaw.' Pittman. Potts & Trowbridae Mr. B. H. Churchill, Attorney-at-Law w/o enclosure <

Troutman. Sanders. Lockerman & Ashmore Mr. A. H. Domby, Attorney-at-Law w/o enclosure U, S. Nuclear Reaulatorv Commission Dr. J. N. Grace, Regional Administrator w/o enclosure Ms. M. A. Miller, Licensing Project Manager, NRR (2 copies) w/ enclosure Mr. J. F. R6gge, Senior Resident Inspector-0perations, Vogtle w/ enclosure Georaians Aaginst Nuclear Enerav Mr. D. Feig w/o enclosure Ms. C. Stangler w/o enclosure 0494m