{{#Wiki_filter:-- --- ,_ g..-.. ; OPERATING DATA REPORT l DOCKET NO. 50 244 DATE March 19. 1987 COMPLETED BY 8.M N
- Andrew E. McNamara i
TELEPilONE 315-524-4446' Ext. 301 OPERATING STATUS Ginna Station
- 1. Unit Name:
R.E. GINNA NUCLEAR POWER PLANT Notes The unit was in coastdown February, 1987 mode fran 2/1 to 2/6. Shut-
- 2. Reporting Period:
1520 down for AI&O occurred at 1700
- 3. Licensed Thermal Power (MW:):
490 hours on that date and contin-
- 4. Nameplate Ih. ting (Gross MWe):
ued thru the end of the report 470
- 5. Design Electrical Rating (Net MWe):
490
- 6. Maximum Dependable Capacity (Gross MWe):
- 7. Maximum Dependable Capacity (Net MWe):
470 H. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
- 9. Power Level to Which Restricted, if Any (Net MWe):
- 10. Reasons For Restrictions, If Any:
This Month Yr. to-Date Cumulative 672.00 1.416.00 1.51.296.00
- 11. Ilours In Reporting Period
- 12. Number of flours Reactor Was Critical 137.5 881.5 116.885.47 0
0 1,687.55*
- 13. Reactor Reserve Shutdown llours 137.00 881.00 114.565.38
- 14. Ilours Generator On Line 0
0 8.5*
- 15. Unit Reserve Shutdown llours 171,240 1,259,304 160,309,353
- 16. Gross Therraal Energy Generated (MWil) 56.837 419.398 52.508.010
- 17. Gross Electrical Energy Generated (MWil)
- 18. Net Electrical Energy Generated (MWil) 53,631, 398,225 49,811,808 20.39%
62.22% 75.73%
- 19. Unit Service Factor 20.39%
62.22% 75.73%
- 20. Unit Availability Factor 16.98%
59.94% 71.57%
- 21. Unit Capacity Factor (Using MDC Net)
'22. Unit Capacity Factor (Using DER Net) 16.98% 59.94% 71.57% 0% 0% 6.88%
- 23. Unit Forced Outage Rate
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forecas t Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
- Cunmulative Total Catmencing January 1,1975 aty.
, m. 8708190260 G70228 ,rl Q PDR ADOCK 05000244 R PDR.- Jll
. AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-244 UNIT R.E. Ginna Nuclear Power Plant DATE March 19, 1987 COMPLETED BY 6 h.XFh% w Andrew E. McNamara TELEPHONE 1 (315) 524-4446 Ext. 301 at Ginna MONTH February, 1987 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1. 415 17. 2. 407 18. 3. 402 19. 4. 402 20. 5. 401 21. 6. 297* 22. 23. 7.
- 24. _
8. 9. 25. 26. 10. 11. 27. 28. 12. 29. 13. 30. 14. 31. 15. 16.
- Online net. Shutdown for AI&O at 1700 hrs.
INSTRUCTIONS on this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
m. U R R 7 a e A8 Nt n c N E 9 cxo n e( L MEi a e e 1 C t n s sl na n i U. 6 a e F t o e N9 E4 t t i DiR a c) 4 S e e n t 1 c A w4 v c i L N w-en i n uf E a c e a r o 4 t roL 4 t M r4 r 2 N s n e o r r I r d2 n f ( r t u no r 0G a n5i t c d Ii s r on t 3 M A - G C o e n a o te p 5 iR a Ga e r E. 1 &c t e ph R t R 3 eA n g ieS t e n b r ytn ) J E EY E s v i iP l e6 u e h tr OMT H N a r xr n v NA A O o D t C P e Ef EE0 1 T ND u E i f 4 P E T T E e K NI E Rn L C U L w E O P l o T D M ad O ut C nu nh AS S NO 7 8 IT 9 mju m C 1 U Cgg5u a n ri D mc Y a E R r p aSl R A c c x U Si E t R R ejy
- a la mr e, g l
a( E B du u oe W E on nt h F O h a a u t eM M A O t P l M1 2 34 i D TN 3 N e O e A M s t n n t r N T e e o W R c v p iE e O O L R D P T E U R H S 00jegO m )n T a I 3c.jg 1 i N wo};2 lp U x n E o t ( i e e e ic s t C M g r B uT r t r s li o e aF e R y 2gc c t 5 n ngr 3jg 3 e a n el a ni t m 5
- ni n u pt el a n ouif geme s qa e e pd p
-{e S aEMRROA e-RABCDEFG 2 7 e 8 t / a 7 D / d 2 le du ed ce rh o c FS o 1 N F:S I
.., NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO. 50-244 UNIT R.E. Ginna Nuclear Power Plant DATE March 19, 1987 COMPLETED BY (h h F. % h Andrew E. McNamara TELEPHONE 1 (315) 524-4446 EXT. 301 at Ginna 4 MONTH February, 1987 The unit was in coastdown mode from February 1 thru February 6; {<- on this date at 1700 hours the unit was removed from service for the Annual Refueling and Maintenance overhaul. The unit remained shutdown at the end of the report period. d 1 s ---__.___-.______._._m
GINNA STATION MAINTENANCE REPORT
SUMMARY
FEBRUARY, 1987 During the month of February st'utdown maintenance and inspections were completed. Major safety related work included: MECHANICS a. "A" and "B" Diesel Generator Annual inspection to include "A" Diesel Generator prelube inspection, "A" and "B" Diesel start compressor's inspection, "A" and "B" Diesel Generator fuel oil tank's pump out, clean, inspect, and refill with fresh oil. b. "A" and "B" Boric Acid Transfer Pumps - Inspection c. "A" and "B" Reactor Shroud Fans - Inspection d. "A" and "B" Reactor Compartment Fans - Inspection e. "A, B, C, D" Containment Recirc Fans - Inspection f.- "A" and "B" Hydrogen REcombiner Fans - Inspect, modify intake ducts - balance g. Turbine Driven and "A" and "B" Motor Driven Aux. Feedwater Pumps - Inspect, both motor driven pumps replace oil coolers h. "A" and "B" Component Cooling Water Pumps - Inspect, replace mechanical seals on "B" pump i. "A" and "B" Control Rod Drive MG Sets - Inspect j. Personnel Air Lock EWR 4492 Modification Upgrade k. Equipment Air Lock - Remove and replace for equipment access and inspect 1. "A, B and C" Charging Pumps - Minor inspection and lubrica-
- tion, "B" Charging Pump m.
"A" and "B" RHR Pumps - P.M. Inspection n. "A" and "B" Reactor Coolant Pumps Seal inspection, motors - minor inspections, "B" Flywheel / Ratchet Pawl Inspection 1 o. Inspect Fuel Transfer Equipment - replace Aux. Building I side upender sheave assembly. l l
MAINTENANCE REPORT (con't) INSULATORS a. Pressurizer Mirror Insulation - EWR 2602 b. Boric Acid Piping Insulation - EWR 3092 c. ISI Program Insulation d. Steam Generator Manway - modify mirror covers e. General Plant Work - Insulate PIPEFITTERS a. V-4005 and V-4011 major inspection and overhaul b. V-3516 major inspection and repair, actuator overhaul c. V-3517, V-3518, V-3519, V-4269, V-4270, V-890A, V-890B, a V-1815B, V-826A, V-826B, V-826C, V-826D, V-825A, and V-825B were all inspected d. RV-257, RV-434, RV-435 were tested. M.S. Safety Relief Valves - change nozzle and guides setting and test e. "A" and "B" M.P. Aux. F.W. Pumps - replace oil coolers f. V-4031 M.D. Aux. F.W.P. - replace g. AOV-846 replace internals h. Reactor Coolant, seal injection and seal return filters l were replaced i. CV Recirc Fan Cooler Plug Maintenance j. Snubbers, overhauled and tested - S/G A-1, A-2, A-3, B-4, l I and B-3 random snubbers. PS-8, AFW 26 and FW-84 M-40 l Snubber inspection performed on all snubbers k. "A" and "B" feedwater venturies were cleaned and inspected I
_ _ _ - _ _ - _ - ~ - - - - _ j,y ......i-YiO s!al9.;;M N i g h 1
- ROCHESTER GAS AND ELECTRIC CORPORATION e 89 EAST AVENUE, ROCHESTER, N.Y. 14649 0001 N:
- n'oor.s w. xoties, .,,,,,- o y l"$ 7l<KI L von GINNA STATION - March 19, 1987 i Director, Office of Management Information and Program Analysis U.S. NUCLEAR REGULATORY COMMISSION Washington, DC 20555
Subject:
Monthly. Report for February, 1987 Operating Status Information R. E. Ginna Nuclear Power Plant Docket No. 50-244
Dear Sir:
Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of February, 1987. Very ruly yours, f Y' m Roger W. Kober RWK/eeh Attachments cc: Dr. Thomas E. Murley NRC (1) S. Yy}}