ML20237K415
| ML20237K415 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 06/17/1987 |
| From: | AFFILIATION NOT ASSIGNED |
| To: | |
| References | |
| OLA-A-013, OLA-A-13, NUDOCS 8709040339 | |
| Download: ML20237K415 (9) | |
Text
_______ - ___
6D-- 2 ?5/3 z.? -0U/
Qwgg
~'(~
S/h/e7
- I
/0
'!3 D%? ~
DISTRIBUTION OF AUTHORIZED JOB ESTIMATES & ADVANCED JOB ESTIMATES
'87 EE26 P3 :33 Ji-
- JE/JE-Title:
SPENr Furt Rue Menimcm,oNt EPN 2.tet.124 F JE-Number:
NPG -09 I DCPP Project Manager (DCPP Project jobs only)
- 3. B. Hoch, ATTN:
J. R. Leahy g,j ny..wa " w Job Coordinators Manager C.
C'.'. CcNNEU.. 1 Job Coordinator N. N. R 0 BEY General Construction (DCPP Projects jobs only)
R. D. Etzler/J. D. Barrett
.g e
V.P. NPC J. O. Schuyler
!D Route for Information J. C. Carroll P*
Route for Information/J. E, Binder TAM /DLP/JLP/ DEN Nuclear Services File
- 5.4.2.1 O
DCPP Acet. Seg. Information W. Bunyan
__M, h o d W t4J
.R. M. LWERTY
,e e
t Yt e
( a(& '@
/
ECE VD l
i FEB 221984 i
I_
RUSSELL," BREED A l
!?89 188s 8?8?f m
- Cry 8 Ex/u%f 13 g
PDR 4 n 57 y y o C a n y, a m. E. N..fu D
I ELL,$ i, ALM 0at COCMt3510N Osdel No. 50-T]g. OLA olkiet En. No. 7 G + E s~ O la the matk ef
--b & I bomPOdj Lt#
IDENTIFIED
/
arohns
_ ntcatto _
Wmaw RfECTED
- mrg Citt b
tantracer DAff Other Witness
'bTYN MNN E fleaarter 1
i 4
4 8 9
l E d in.y...m, JOB ESTIMATE e
seer wo.
2 Summary and Cale Aation Sheet EstuMTE NO. 3PG-041
... I amwr wwuo Wirems and Overheads
' to twr vn
.11 0
3 8
4 Note: See S.f8.112.41 for currenUy apphcab6e percentages and rates, astotu ana:ptro*= % r 1000 TYPE OF COSTS og,***n sanwm marrmaet enarew g ag orma DIRECT COSTS I
- 1. Capharinstallation/ Purchase (include G.O. tabor) llll 415 U #
i 318 22 3.115 e
o R7n
- 2. Capha! Removal 8525!
6 6
- 3. CaphatTravel LJtbor 6
'*I
- 4. CapitalEscalation (Line 1 + 2 +3) x 2Dmos. xQ,J.
B 33 31 r 2 681 8
1 747 5.
TotalCaprtalDirect Costs 448 349 24 9.796 6
10.617
- 6. Maint. and Oper. (M and O) incl. Travel Labor
.6 6
8 6
6 6
- 7. M and O Escalation (Line 6 x m os. x
)
6 6
6 6
6 6
w
- 8. Contingency 6
67 6 2.046,
6 2.113
- 9. Total Authciized Direct Costs 5! 448 416 24 11.842 6
12.730 INDIRECT COSTS N
- 10. Insts!!ation (Lines 1+3+4+6) x (See Note 1)
.llll388 44
.il@$
ijil 432
/
't. Removal Line 2 x (See Note 1)
~!jij
~
![!)
6
~
)
s, s. Transp. and Work Equip. (Cap. & Maint.)(See Note 1)
!!@i!!
13.
'lotalCaprtallndirects 388 44
~ ' 585!!$
432
- 14. Tout!M and OIndirects (See Note 2) 6 6
~'.:
gS!k 6
~
- 15. Totalindirect Costs
~
i 432 388 44 OVERHEADS (3)
- 16. Gen. Engr. and Admin. Costs (Lines 5 + 13) x 17.5 M5
!!!1,934
- 17. Ad ValoremTaxes (Lines 9 + 13 + 16) x.(11 yrs. x (1) jijl 44
- 18. AFUDC Line 5 x 8.9 INi$
i
!!ll 948
- 19. Totaloverheads (See Note 2) d 2,926 GROSS FINANCIAL COST
- 20. Directs. Indirects and Overheads (Lines 9.) 15 + 19) llll##
l!ll16.088 Note 1:
Drea cosa Note 2:
x.Ok Composite Percentages: per cru swomary on.tae Est two sw a.DndG.C.physicallabor 8
LLR
- b. Other G.O. labor s
x
- a. Cap. Indrocts % =
6.ine 13 e9') x 100
=.LII
- c. Materials (M and S equip.,etc.)
L1A x.1.11 b.M and O indirects % = (Line14 + s) x 100 -
8
- d. Transportation and Work Equip.
x_
- c. Overheads % = (Line 19) + ( 9+ 13) x 100 =dL.2%
e
- 1) Calculated by CONEX based on cashflow.
(2) Expenditures to date are included in this value and are not escal ted.
(3) Based on unit 1 installation completion 6-85
JOB ESTIMATE M3
"~
.IS.?f
'a C-o, n,
u_
w,, y.,_,,
paraaruwr Eleetric orstmic t o,ve,ou Noclear Power Cenerm-6 aceuceartisi soones pocuusut cit uatt g(oca.,o,, l n T am et in.A A W v n w. 114 Ttr. til r.
3J cov=rdan Luis Obisoo
- M C' 'o'"
p iao" auw a i+=.
ilS P. E, N3i~ Y[UY3.1, R. A, CK l M.O.D. II F. I. C AT II,0.N t.Eb ~
"o 9,gt Wroposec 5tE*$'5'*l55Peucwt owuo na
= ve'a
-""a""
k.tw asacooac,inatoa M_ W. Rnhey ecsa s., 7M 4018l tem s.ve.s.cNEgMM,'n si, B40 t'*_ '"* "5**
aD"' oac8 *^5 "'
co.n..o..
,ou.
o=
m.c..
..uo.
a=
It is proposed that the existing spent fuel storage racks be replaced am gpswic au n us Es e.
nn by hijher density racks and the cooling system be modified to provide g gi m.au.
..s gftditional cooling capability. Additional oe.eite spent fuel storage
~2----------
' an.c.eu
.s will be required at Diablo Canyon because of uncertainties in the W""' c'341 M'c".(?"'3 ^ 'N e s c a.
Qdecal Government spent fuel storage and reprocessing policy.
ma m **
/
ftac PtoJ ese ALCO.s tsubat.om, augt s. e.us AATt SC iDWLL CEC LacAtlpa g-88"D" D. E. Naaf M
o m mau e
^ " " " ' * * ' " '
~ ~.u.
- pg*6 otsencrou or ointet Cost ersus g".",'g5
~'
g eoo o.
g g p p- ;
e.
Spent Fuel Storage Racks and l
12 40 67 44.49 sp e vn,1 rnn14"C sycrem 416 J1. 842
- I 22 365 10 20 General Office Engineering 448 24 r-(
)
sCr
.... fall eosts.are in $1.030s)
_AyJ.gg h
f.E.B-1 6 c
""~
~ """T6 fat
~
YW"
vow cew o.nc, costs renu uso o=ce, corrs s10,617,00' contingency 19.9T
~....c,
,mo
_.r.
... n w
erz--
""""*"8""
9870 6
6 747 6
6 3.4.
es.Am 1o se asmovto on Asanoceo ea % s2.ure ww.is e.,ii nm ri
_caras =m
.oe susuortune av vtAa e ns m
mai WSa vu..B,3.
84
,...i 85.
- 5 22.2s 2,926.00
==rev mas as cam 533 30 1.840 10.327 6
.sw e,u
. mas mca ni
- "m 773 64 2 414 12,837 6
F.*,cf** *'**
1 SOM ACCOUNTING Ust oNLY ggages ganan y
amas cues enaciuses coma enJ er.os.' en --
sat,some o suo.m unirt shed CAUut.ct carreanen e i t i i
.n un
's
{
j o 33,o,
'teoast' ascs arcs peca.s, suas esco f DA AcCOgMdTl8f0 ULs ONLY
{ Artsattsow
. aaGert ce wav emocassa assomt 9 y,,vy.
,,,,,,,,, o,g o,,c og :n4t ossict J.PJJ i APPL. 8so oVER3D% vetLD l
uteva
=c syne.av., ras, l
CfTV on Co. et Rulf 4'
.vututwT.30 FT 605 6468 roos, o,Mo. m.,c,La,g sa
'""'"N teG.stasiv pgnurr n',', gI,,,T a *
- a'c * " "
J c3_ vr*""e",1, gyj{gg
"' *'*' "'~g"
- gw.=_ m.,,. -.
=ano^'s 1 i
.x,
o1,.... m
l?
Sheet 3 NPG-041
,),
SPENT FUEL RACKS MODIFICATION This Job. Estimate is for a project which supports the long tem operation of Diablo Canyon Power Plant. This cost estimate.for the Spent Fuel Racks Modification includes the amount previously authorized and spent under VP&GM 73068, A & B and ED 2479.
PROPOSAL It is proposed that the existing Unit I and Unit 2 spent fuel storage racks be removed and replaced by high-density spent fuel storage racks to provide long-ters storage ci fuel off-loaded from the reactor., It is further proposed that the spent fuel 9001 cooling systems be modified to provide the additional
. cooling needed for the additional. stored fuel.
JUSTIFICATION 1.
Necessity e
The existing spent fuel racks are designed to store 1/3 of the core, in which is normally off-loaded during the annual refueling, and still provide sufficient storage space to off-load a full reactor core at any time, if necessary. The 1/3-core off-loaded during each refueling was intended to be shipped off-site for storage or reprocessing prior to the s) next refueling.
I C3 Additional on-site spent fuel storage will be required at Diablo Canyon because of continuing delays and uncertainties in Federal Government policy regarding implementation of programs fer off-site spent fuel y
,~
storage and reprocessing facilities. This delay will likely extend to 1998.
c.
2.
Alternatives a.
Replace existing fuel racks with high-density spent fuel racks installed before the first refueling outage.
b.
Defer installation of new high-density spent fuel racks until just i
before the second annual refueling.
c.
Install a new spent fuel pool with high density racks elsewhere on site.
d.
Install on-site dry storage casks for spent fuel.
e.
Donothing(i.e.,retainexistingr'acks).
3.
Analysis The alternatives are compared below. Table 1 compares the. costs of each alternative.
~
~
~
Sheet 4 NPG-041
~~
l s
U
,s
(.
High density racks installed before first refueling:.llation' risk Simple-H a.
installation in a dry spent. fuel pool minimizes insta and cost. The use of the existing spent fuel pool reduces the
-amount of, fuel handling and the associated risk of fuel damage and possible contamination.
b.
Deferred installation of high density racks: This requires a more i
complicated wet installation in a water-filled pool using several divers and' requiring rehandling of. the stored fuel. Installation time would be extended. inst ~t11ation costs would at least double, j
and the operation would become considerably' more complex due to diver radiation protection.
l t
Wet installation work is more complicated and imposes additional-limitations. This reduces the ability to modify the installation-in-response to unexpected problems and increases the potential for cost-l increases.
i o
Fuel stored in the pool at the time of installation would have to be h
moved several times in order to remove the existing recks and still keep the fuel submerged. 'TMs would also require heavy components m
to be moved above spent fuel which may require NRC waiver of H
existing requirements. This creates the risk of NRC approval delays as well as increased risk of fuel damage and possible contamination.
I
(.)
Several factors could increase costs more than anticipated due to C'
the deferred installation.
Rack vendors are in sharp competition now for a limited number of jobs. This is not expected to be the case.later because some vendors cannot justify retaining their current staff and may drop out of this market shortly reducing iy N
competition and increasing prices. Material prices are current C
depressed but are expected to increase.
c.
Additional spent fuel pool on site: The cost would be several times that for replacing existing racks.. Fuel handling charges would be i
much greater. It is not certain that permits could be obtained for building a new structure on site for long tem fuel storage. Since l
i l
fuel ' transfer to the new building would be necessary, additional risk of irradiated fuel damage would be created.
d.
Dry storage casks on site: The cost would be several times that for replacing existing racks. - Fuel handling and inspection costs would be much higher. Licensing risks would be created since no dry storage facility has been licensed to date.
i e.
Do nothing: The p1 ant could not be operated with a full core offload' capability after the second refueling (i.e.,24 years after
,I commercial _ operation) or until off-site receiving-facilities become available. The Federal Government is not expected to receive spent i
]
fuel for permanent disposal until 1998. This is not acceptable.
i 1
I I
1
l Sheet S NPG-041
)
I TABLE 1 SPENT FUEL RACKS MODIFICATION ALTERNATIVE COMPARISON (in $1000s) l l
ADDITIONAL l
FUEL LEVEL ANNUAL HANDLING REVENUE l
ALTERNATIVE CAPITALS 83$
COST REQUIREMENT (I)
A.
High Density Spent Fuel Racks
$ 9,745
$ 1,740 Installed Before First Refueling B.
High Density Spent Fuel Racks
$12,036
$ 2,148 With Deferred Installation C.
Additional Spent Fuel Pool On Site
$16,174
$ B0
$ 3,559 l
D.
Dry Storage Casks On Site
$16,174
$ 80
$ 3,559 m
w E.
Do Nothing
$821.100(2)
()
II)Levelized cost percentages and present worth factors from Manual of O
Engineering Economics, Revision 3 (2)Plantmustbeshutdown,plantinvestmentof$4.6billionbecomes N
&r nonproductive and potentially removed from the rate base.
o 4.
Recommendation i
Replacing the existing racks, with higher density racks will assure that continued operation of the plant will not be dependent on off-site storage of spent fuel for at least 16 years and potentially for up to the design life of the plant (depending on final rack design, future consolidation of fuel, and average time between refuelings).
Deferral of installation of the high density racks would delay this expenditure by less than one year, would necessitate a much more complicated rack removal and installation, and would increase the installed cost.
The alternate storage methods (new pool or dry casks) are several times j
sore costly and are subject to significant licensing or permit issuance
]
uncertainties.
Sheet 6-NPG-041
(-}
Doing n'othing would prevent continued plant operation with full core offload capability after two end one-half years.
Consequently it is recomended that the high density racks be installed prior to the first scheduled refueling.
5.
Schedule 1-3-84 Submit Job Estimate for Authorization 1-18-84 Job Estimate Authorization 3-30-84 CompleteDesign'(PlaceP.O.)
j i
i 3-1-85 StartConstruction(Startsiteinstallation) 6-1-85 Operating Date for Unit 1 (Installation completed beforerefueling) 11-1-85 Operating Date for Unit 2 (Installation completed N
before refueling) s.n Job Coordinator:
J. B. Hoch/H. N. Robey Department:
Nuclear Project i
Address:
45 Fremont Street, 10th Floor. Section D1 Phone:
(415)768-4038 N
?.+ t' C
l 1
l l
I I
g
\\
I NPGP9 t
B/7DCET, YEAR l 1984 FHASE SINMARY REPORT PROJECT 16 TUNC DIV YR G FEW OPECIFIC CAPITAL X
UTIL FUNC ELEC PROD NUCLEAR EPN 22-82 h ANNUAL C ITAL BBF NEN ENERGY FACILITIES YLD K
.SPFCIFIC PERATING PROG NUCLEAR PONER DEY 12/206
, -,s T
a'TLE
.1 2
~
f!A8LO CANYON POST CONL REQUIREMENTS l
MECE8617Y P{RCENT C
0 PRIORITY DESCRIPTION
~
REASON FOR PROJECT lALL DIABLO CANYON NDRK REGUIRED FOR POST
- COMMERCIAL OPERATION SC i
SPONSOR VP NUCLEAR PONER GEN 2.
COORDINATOR NSNE NUCLEAR SYSTEMS GRP l
CONTACT G8 PAGE EST ST Dh 07/01/83 ACT ST DT KST.0PER DT 02/28/86 -EST END DT k2/28/86 EdiQALATED COST (x 01000)
EEPEND!TURES SY YEARS (x $1000) afANDAYK 1,001 THROUEN AUDGET YR R EM AINIC3 3180R 155.7 1983 1984 (1) 1985 (1) 1986 YEARS afATL 4,062.0 ML 21.5 PLANNED
.0
.0
.0
.0
.1 NNTR 1,76E.0 L. AUTN 1485.7 23396.2 25367.7
.0 CTgER
.0 REQ CNG
.1-22232.1-20036 1-17.8
.1 2
707 DIR 7,999.0 Tor DIR 1485.6 1164.1 3331.6 17.8
.1
/I '*
- A 692.5 INDIA's 24.6 136.9 517.7 13.4
.1 1 301.0 OVKD5 345.7 384.4 1493.7 198.5
.I L ) 0VK 1 121.3 CROSS 1855.9 1685.3 7342.9 229.7
.t J ROSS 11,113.9 BILLING
.0
.0
.0
.0
.1 i
ULLING
.0
- ET 1855.9 1685.3 7342 9 229.7
.1 ALTERNATIVE 5 STUD!ED aor AR$0 X OF CROSS
.0 ENV!RONNENTAL
.0 M OVAL
.0 MALVAGE
.0 PRASE Q
TITLE M
-F SPENT FUEL RACK NODIFICA EPN (1) Based on SCR's 1-20.
The balance of the budget is included in an unresolved items account in EPN 2281114/EPN 228116 Phase D which will be distributed later.
00RDINATOR* MSNE NUCLEAR SYSTEMS GRP GB PAGE
- BM 2545 77 BEALE ST 5[
PREPARED BY VP EENIOR VP HCHT CCHN 5,,)?URE 1
ATE REPORT PACE 35
- --