Provides Present Status of Facility Diesel Generator Vendor Manual Update Project Implemented,Per Generic Ltr 83-28. Purchase Order Issued to Diesel Generator Mfg on 870619 to Update Manuals.Draft of Updated Manuals Due by 871211
ML20237G514
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 08/10/1987
From: Gallagher J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Varga S
Office of Nuclear Reactor Regulation
References
GL-83-28, NUDOCS 8708140105
Download: ML20237G514 (2)


Text

p l

PHILADELPHIA ELECTRIC COMPANY 2301 MARKET STREET P.O. BOX 8699 PHILADELPHIA. PA.19101 (215) 841 5001 JOSEPH W. G ALLAGHER JI'l#l/1",",'..

August 10, 1987 Docket Nos. 50-277 3

50-278 l

Mr. Steven A Varga, Director Division of Reactor Projects I/II i

L U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.

20555

SUBJECT:

Peach Bottom Atomic Power Station Units 2 and 3, j

Generic Letter 83-28 I

REFERENCES:

(1)

Letter, S. L. Daltroff, PECo, to R. Bernero, NRC, dated July 23,.1986 (2)

Letter, S. L. Daltroff, PECo, to R. Bernero, NRC, dated August 29, 1986

Dear Mr. Varga:

This letter provides the present status of the Peach Bottom diesel generator vendor manual update project which was implemented pursuant to the requirements of Generic Letter 83-28,

" Required Actions Based on Generic Implications of Salem ATWS Events".

A purchase order was issued to the diesel generator manufacturer on June 19, 1987 to update the manuals._ The update of the manuals will include an engineering review of all modifications performed on the diesel generators over their lifetime.

An expedited schedule has been established and a draft of the updated manuals is due for formal PECo review by December 11, 1987.

Resolution of any PECo comments and final approval wil; follow promptly.

The manufacturer has been forwarding and I

will continue to forward the appropriate service information letters to PECo.

I l

hO f

l (I

c

)

T Mr. Varga August 10, 1987 Page 2

'l 1

We will update you on the. status of other Generic Letter 83-28 tasks within two months.

If you have any questions or require additional information, please do not hesitate to contact y

us.

Very truly yours,.

cc:

Addressee

-W. T. Russell, Administrator, USNRC, Region I T. P. Johnson,' Resident Site Inspector R. E. Martin, USNRC, PBAPS-Project Manager D. L. Caphton, USNRC, Region I l

l l

l l

l l

r l

=i i

l i

.. _ _ ~

_ _. _ _ _ _ _ _ _ _. _ _ _ _.. _ _ _ _ _ _ _ _ _. _ _ _ _ _ _ _ _ _