Informs That Westinghouse Rept WCAP-10551, Technical Bases for Eliminating Large Primary Loop Pipe Ruptures as Structural Design Bases for Alvin W Vogtle..., Will Be Withheld from Public Disclosure Per 10CFR2.790(b)(5)
ML20237G337
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 08/18/1987
From: Mark Miller
Office of Nuclear Reactor Regulation
To: Wieseman R
WESTINGHOUSE ELECTRIC COMPANY, DIV OF CBS CORP.
References
CAW-84-43, NUDOCS 8708240049
Download: ML20237G337 (2)


Text

_ _ _ _ _ _ - _ _ _ _ _ _ - ___ - - - - - - - - - - -

( '

' 1

+E p alc oq'o, UNITED STATES J}()

o  ! o NUCLEAR REGULATORY COMMISSION l; ;E WASHINGTON, D. C. 20555 k...../ AUG 181987 '

Docket Nos.: 50-424 and 50-425 Mr. Robert A. Wieseman, Manager

- Regulatory and Legislative Affairs Westinghouse Electric Corporation Box 355 Pittsburgh, Pennsylvania 15230

Dear Mr. Wieseman:

Subject:

Request for Withholding Infonnation from Public Disclosure (CAW 84-43)

_ By application dated May 17, 1984, Georgia Power Company submitted Westinghouse Report No. WCAP-10551, " Technical Bases for Eliminating Large Primary Loop Pipe i Ruptures as the Structural Design Bases for Alvin W. Vogtle Units 1 and 2," and requested it be withheld from public' disclosure pursuant to 10 CFR 2.790. Also enclosed was your affidavit dated September 26, 1983.

Your affadavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons: j

1. The document contains infomation which is customarily held in confidence by Westinghouse.
2. The information has been held in confidence by Westinghouse and is not available in public sources.
3. The infonnation is the result of analyses performed by expenditure of considerable time and effort to Westinghouse.

We have reviewed your application and the material based on the requirements and criteria of 10 CFR 2.790 and on the basis of your statements, have determined that the submitted infonnation sought to be withheld contains trade secrets or proprietary commercial information.

Therefore, the Westinghouse Report No. WCAP-10551 marked as withheld from public disclosure pursuant to 10 CFR 2.790(b)(proprietary will be5) and Sec of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of per-sons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, insure that the consultants have signed the 1 appropriate agreements for handling proprietary information.

8708240049 B70810 PDR ADOCK 05000424 P PDR W" -

s Robert A. Wieseman 10 l

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You should also understand that the NRC may have cause to review this determination in the future, such as if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC needs additional information from you or makes a determination adverse to the above, you will be notified in advance of any public disclosure.

Sincerely,

%\

Melanie A. Miller, Project Manager Project Directorate II-3 Division of Reactor Projects I/II cc: James P. O'Reilly, Georgia Power Company DISTRIBUTION:

Docket File NRC PDR PRC System Local PDR NSIC PDII-3 P,eading MDuncan MMiller BJYoungblood Reading EShomaker, OGC-Bethesda EJordan JPartlow SVarga/Glainas PDlIQ/kRPI/II PDIJpDRPI/II kh OSC-Bethesda DW PDII-3/DRPI/II jpNMiller/ rad MD0d ah EShomaker BJYoungblood