ML20237F618

From kanterella
Jump to navigation Jump to search
Discusses 870721 & 23 Info Provided to E Reis Re Status of Equipment Qualification & SPDS Actions to Be Taken by Util in Preparation of Testimony to Be Given Before Aslab
ML20237F618
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 07/23/1987
From: Nerses V
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
NUDOCS 8708130099
Download: ML20237F618 (3)


Text

_ __ _

e I

Docket No. 50-443 July 23, 1987 Memorandum For:

File tdfNrses,ActingDirector,ProjectDirectorateI-3, From:

A Office of Nuclear Reactor Regulation, NRC

Subject:

Information provided Ed Reis, OGC-Bethesda, On the Status of Certain Licensing Actions On July 21 and 23, 1987, I informed Ed Reis of the status of certain licensing actions to be taken by Public Service Company of New Hampshire (PSNH).

This information regarding the status of certain EQ and SPDS actions was to be used in preparation of his testimony to be given before the Atomic Safety and Licensing Appeal Board.

l Specifically, I noted to Ed Reis that no formal follow-up audit has as yet been performed of the PSNH EQ files.

However, while I was at the Seabrook site on July 22 and 23, 1987, I reviewed the EQ files that the NRC found in their audit of February 1986 to contain deficiencies and found that i

these deficiencies were corrected with the following qualifi-cation.

The staff noted that in file number 113-03-01 PSNH should update to include the test information that was provided during the audit justifying use of the Okonite cable in Seabrook's design basis events. Also in file number 236-11-06, the staff noted that PSNH agreed to add clarifying test report dtta to the equipment summary evaluation.

Since I did not have the staff's actual comments on these specific files it was not possible to directly verify that the appli-cant incorporated these items into the files.

However, in each case I found information in the revised EQ files that corresponded to the subject matter (e.g.,

test information, test report data) and to a period of time subsequent to the audit that would lead me to believe PSNH did incorporate the staff comments.

Before reviewing the files, I had reviewed the documents (SSERs 5 and 6, Meeting Summary of the 2/86 EQ audit, EQ testimony before the ASLB on 9/19/86, certain PSNH letters to the NRC on EQ matters, Region I Inspection Report 50-443/86-20) pertaining to the deficiencies in order to ascertain that these deficiencies were in fact corrected.

The deficiencies pertaining to the EQ files that I verified were corrected are identified in the meeting summary of the I

870B130099 870723 PDR ADDCK 05000443 P

PDR

e a.

Page 2.

'(

f 2/86'EQ au'dit (copy attached) and supplemented by Table 3.1-of SSEP. 5 as modified in a table on page 7 of the testimony of J. M. Salvo, G. S. Thomas and N. K. Woodward on NECNP con-tention I.B.2 presented to the-ASLB on September 19,-1986 (the table is attached).

Regarding the rearrangement of the containment isolation status indicator lights, I informed Ed Reis that that the. rearrangements were completed.

"I"""(Iobserved the I

rearrangements, I noted that:the status indicator light matrix contained certain blank designations which did not light up.

This arrangement was not satisfactorily readable from the prime SPDS location.

It was.not easily determinable-that the non-lighted display was one of the blank designa-tions or.whether it was an actual failure of a component r.eeded in the containment isolation function.- The correction was to have the total display light up if there was no com-failure in the isolation function mode; therefore,;

ponent as a result of a dark individual display it required operator action to ascertain what failed.

l e

k l

l J i '

' *7-

,,,-.A 6

DISTRIBUTION:

PDI-3 R/F' VV3 (SeeketInks0 6 NRC PDR Local'POR-SVarga BBoger-MRushbrook '-

Y ter,ey f/./. I'/ 6 5's OGC-Bethesda Mw.e 4

I

+.

6

._______________j

f..

g**%

UNITED STATES o

e NUCLEAR REGULATORY COMMISSION g & j J' %

y WASHINGTON, D. C. 20555

%.';;)/

E APR 1 1 av

\\

Docket Nos.:

50-443

~

and' 50-444 APPLICANT:

Public Service Company of New Hampshire (PSNH)

FACILITY:

Seabrook Station, Unit 1 and 2 l

SUBJECT:

MEETING

SUMMARY

l During the period February 24 through February 27, 1986, the NRC staff and its consultants f)om EG&G Idaho audited 12 equipment qualification (EO) files of Seabrook Station Unit 1.

All files were for equipment located in a harsh environment. As a result.of the audit, the staff and its consultants made the following observations and coments at an exit interview held at the Seabrook

. site on February 27,1986 (List of Attendees attached.)

1.

A cursory review of the Seabrook master list indicates that there are approximately 38 items remaining to be qualified. All equipment within the scope of 10 CFR 50.49 must be qualified prior to the issuance of an operating license.

-2.

During the plant walkdown it was discovered that there are three jumper wires and a teminal block in a Limitnrque motor operator (file no.

173-05-02) that could not be identified. This problem is noted in IE Information Notice 86-03. The applicant should review the entire Seabrook program to assure that similar circumstances do not exist i

for other Limitorque motor operators. Provide information on all corrective actions that have been or will be' taken in order to maintain qualifications.

3.

The staff is not in agreement with the way the Arrhenius equation was used to calculate post-accident operability time. The applicant must j

provide acceptable justification or recalculate post-accident operability

.l time using only the portion of the test profile that represents the 1

post-accident period. This correction should be made fnr the entire Seabrook environmental qualification program, l

i I

4.

During the plant walkdown it was discovered that an ASCO solenoid valve had two different equipment identification numbers attached to it. This situation can serve as a ma,ior source of confusion that could produce adverse affects on plant safety.

Therefore, the applicant must review the Seabronk program to assure that this situation does not exist with other equipment, j

The following comments are specific to individual EQ files as indicated.

i However, the applicant must update all files to incorporate these comments

)

where applicable.

1 g w g s,i n q-y ci

.,t!

p o

3 I <

(File number 113-03-01, Okonite Cable)

This file should be updated to include the test information that was provided l

during the audit,iustifying use of this. cable in Seabrook's design basis 1

events.

(File number 174-15-01, Transamerica Level Transmitter 1 Applicant agreed to add information to this file.iustifying the use of a test sequence different from that specified in IEEE 323-1974.

l (File number f13-06-01, Brandrex Cable)

'l i

Applicant agreed to add a statement to specify that submergence qualification l

is not required.

(File number 236-11-06, Reliance Motor)'

Applicant agreed to add clarifying test report data to the equipment summary evaluation.

(File number 248-37-01, limitorque Motor Operator)

There are three internal wires and a terminal block that cannot be identified in the operator that was inspected during the plant walkdown. All of the components that cannut be identified must be replaced with qualified components.

(File number NSSS-220-02, ASCO Solenoid Valvel The valve that was inspected during the plant walkdown had two different equipment identification numbers on it. This situation must be rectified.

In addition to the six file numbers noted above, the following were also audited:

File number 113-19-01, ITT-Suprenout Cable File number 118-03-01, Conax Conduit Seal Assembly File number 173-05-02, Rotork Motor Operator File number 252-16-02, Barton Transmitter File numver 252-30-01, Endevco Accelerometer and Charge Converter File number 600-02-01, Weidmiller Terminal Block Our evaluation of the applicant's EQ program, including the results of the audit will be provided as input to a future SER Supplement.

In a letter dated May. 5,1983 from G. W. Knighton, NRC, to R. J. Harrison, Public Service Company of New Hampshire, the staff provided guidance on staff requirements for environmental qualification of mechanical equipment.

The following is a reiteration of that guidance:

For mechanical equipment, the staff review will concentrate on materials which are sensitive to environmental effects, for example, seals, gaskets, lubricants, fluids for hydraulic systems, diaphragms, etc.

A review and evaluation should be performed by the applicant that includes the following :

(1)

Identification of safety-related mechanical equipment located in harsh environment areas, including required operating time.

(2) Identification of non-metallic subcomponents of this equipment.

(3) Identification of the environmental conditions this equipment must be qualified for. The environments defined in the electrical equipment program are also applicable to mechanical equipment.

(4) Identification of non-metallic material capabilities.

(5) Evaluation of environmental effects.

The list of equipment identified should be submitted.

From this list the staff will select approximately three items of mechanical equipment for which documentation of their environmental qualification should be provided for review. Also, the results of the review should be provided for all mechanical equipment in harsh environment areas and corrective actions identified. Justification for interim operation must be submitted prior to fuel load for any mechanical equipment whose qualification cannot be established.

Victor Nerses, Project Manager PWR Project Directorate #5 Division of PWR I.icensing-A a

~,

Mr'. Robert J. Harrison

-Public Service Company of New Hampshire Seabrrok Nuclear Power Station 4

cC*

Thomas Dignan, Esq.-

E. Tupper Kinder, Esq.*

John A. Ritscher, Esq.

G. Dana Bisbee, Esq.

Assistant Attorney General Ropes and Gray-225 Franklin Street Office of Attorney General

. Boston,. Massachusetts 02110 208 State House Annex Concord New Pampshire Mr. Bruce Beckley, Project Menager Public Service Company of New Hampshire Resident Inspector Post Office Box 330 Seabrook Nuclear Power Station Manchester, New Hampshire 03105 c/o U.S. Nuclear Regulatory Comm.

Post Office Box 700 Dr. Murray Tye, President Seabrook, New Hampshire 03874 Sun Valley Association 209 Summer St/eet Mr. John DeVincentis. Ofrector Haverhill, Massachusetts 08139 Engineering and licensing Yankee Atomic Electric Company Robert A..Backus, Esq.

1671 Worchester Road O'Neil, Backus and Spielman Framingham, Massachusetts 01701 116'Lowell Street Manchester, New Hampshire 03105 Mr. A.M. Ebner, Project Manager United Engineers & Constructors Mr. Phillip Ahrens, Esq.

30 South 17th Street Assistant Attorney General Post Office Box 8223 State House Station #6 Philadelphia, Pennsylvania 19101 Augusta, Maine 04333 William S. Jordan, III

{

Mr. Warren Hall Diane Curran Public Service Company of Harmon, Weiss & Jordan 20001 S. street, NW New Hampshire Post Office Box 300 Suite 430 Seabrook, New Hampshire 03874 Washington, D.C. 20009 q

Seacoast Anti-Pollution League Jo Ann Shotwell, Esq.

Office of the Assistant Attorney Ms. Jane Doughty General 5 Market Street Portsmouth, New Hampshire 03801 Environmental Protection Division One Ashburton Place Ms. Diana P. Randall Boston, Massachusetts 02108 70 Collins Street Seabrook, New Hampshire 03874

0. Pierre G. Cameron, Jr., Esq.

General Counsel Public Service Company of New Richard Hampe, Esq.

New Hampshire Civil Defense Agency Pampshire a

i Post Office Box 330 107 Pleasant Street Manchester, New Hampshire 03105 Concord, New Hampshire 03301 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 l

1

'Public Service Company of Seabrook Nuclear Power Station New Hampshire i

CC:

Mr. Calvin A. Canney, City Manager Mr. Alfred V. Sargent.

City Hall Chairman 126 Daniel Street Board of Selectmen Portsmouth, New Hampshire 03801 Town of Salisbury, MA 01950 Senator Gordon J. Humphrey Ms. I.etty Hett ATTN: Tom Burack Town of Brentwood RFD Dalton Road U. S. Senate Brentwood, New Hampshire Washington, D.C. 20510 Hs. Roberta C. Pevear Town of Hampton Falls, New Hampshire Drinkwater Road Hampton Falls,' New Hampshire 03844 Ms. Sandra Gavutis Mr. Owen B. Durgin Chairman Town of Mensington, New Hampshire Durham Board of Selectmen RDF 1 Town of Durham East Kingston, New Hampshire 03827 Durham, New Hampshire 03824 Chairman, Board of Selectmen Charles Cross, Esq.

RFD 2 Shaines, Hardrigan and South Hampton, New Hampshire 03827 McEaschern 25 Maplewood Avenue Mr. Angie Machiros, Chairman Post Office Box 366 Board of Selectmen Portsmouth, New Hampshire 03801 for the Town of Newbury Newbury, Massachusetts 01950 Mr. Guy Chichester, Chairman Rye Nuclear Intervention Committee Ms. Rosemary Cashman, Chairman c/o Rye Town Hall Board of Selectmen 10 Central Road Town of Amesbury Rye, New Hampshire 03870 Town Hall Amesbury, Massachusetts 01913 Jane Spector Federal Energy Regulatory Honorable Peter J. Matthews Commission Mayor, City of Newburyport 825 North Capitol Street, N.E.

Office of the Mayor Room 8105 City Hall Washington, D.C. 204P6 Newburyport, Massachusetts 01950 Mr. R. Sweeney Mr. Donald E. Chick, Town Manager New Hamphire Yankee Division Town of Exeter Public Service Company of New 10 Front Street Hampshire Exeter, New Hampshire 03823 7910 Woodmont Avenue Bethesda, Maryland 20814 Mr. William B. Derrickson Senior Vice President Public Service Company of New Hampshire Post Office Box 700, Route 1 Seabrook, New Hampshire 03874

I v

l ATTENDANCE LIST NAME COMPANY POSITION W. J. Cloutier YAEC

. Lead Systems M. Trojovsky INEL/ EGG Engineer V. Nerses NRC Project Manager D. M..Beahm INEL/EG&G Engineer A. C. Cerne NRC SRI D. Ruscitto NRC RI R. Barkley.

NRC RI J. Warnock NHY Nuc. Qual. Mgr.

.A. R. Sullivan NHY Nuc. Qual. Engineer D. R. Jaquette YAEC Licensing.

G. Kingston NHY Compliance Mgr.

G. F. Mcdonald' NHY Const. QA Mgr.

I David A Maidrand YNSD Asst. Proj. Mngr.

Bai Poi UE&C Engineer Stacey YNStl Proj. Engr. Mgr.

J. M. Salvo YAEC Sr. Mech. Engineer R. Bergeron NHY Lead I&C Engineer R.-J. Deloach YNSD Project Manager H. Walker' NRC Engineer 4

i i

I I

h

v o

1-i l

Qual:fied Time post-required accident to perform EQ file operating safety Number of number.

Description time funct:en items 246-36-01 Borg-Warner feedwater 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Approx:-

4 isolation valves mately 1 minute 113-03-01 okenite 600-V power 30 days 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> N/A cable

  • 113-17-01 Anaconda 600-V control 30 days 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> N/A cable
  • 113-16-01 Anacenda 300-V instru-30 days 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> N/A mentation cable
  • 113-20-01

!TT Suprenant 300-V 30 days 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> N/A instrumentation cable

  • 172-01-01 General Atomic Radi-7 hours Approxi-2 ation Monitors and mately Detectors (inside 2 minutos containment) 174-00-01 Fox' boro Transm :ters 100 days 90 days 13 252-38-01 ASCO Temperature 160 days 30 days 4

Switches 600-01-04 Raychem 8 KV Motor 100 days 30 days 13 173-05-03 Maisoneilan E/P 204 days 100 days 4

Converter m

600-06-01 h.co EO 210 Series 318 days 30 drys 16 Conduit Seals

  • 0nly the cable that is subject to submergence is limited to 30 days' qualificatzen.

7 o