Letter Sequence RAI |
---|
|
|
MONTHYEARML20237E0361998-08-24024 August 1998 Forwards Request for Addl Info Re GL 97-01, Degradation of Crdm/Cedm Nozzle & Other Vessel Closure Head Penetrations Project stage: RAI 1998-08-24
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective ML20207G2611999-06-0707 June 1999 Informs That NRR Has Reorganized,Effective 990328.Forwards Organizational Chart IR 05000412/19980091999-05-26026 May 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-412/98-09 ML20195C4461999-05-21021 May 1999 Forwards Insp Repts 50-334/99-02 & 50-412/99-02 on 990321-0501.No Violations Were Identified.Licensee Conduct of Activities at Beaver Valley Power Station Characterized by Safe Conduct of Activities During Refueling Outage ML20206P1241999-05-14014 May 1999 Refers to Proposed Changes Submitted by Dl on 990316 to BVPS QA Program Described in BVPS-2 Ufsar,Chapter 17.2.Forwards RAI Re Proposed QA Program Changes ML20206N3161999-05-0606 May 1999 Responds to Ltr to NRC on Continued Events Re Transfer of Generation Assets Between Dl & Firstenergy.Info Will Be Considered as NRC Monitor Pending License Transfer Application of Bvps,Units 1 & 2 & Pnpp ML20206H7931999-04-30030 April 1999 Ack Receipt of 990426 Request for Enforcement Discretion & 990427 Withdrawal of Request for Enforcement Discretion. Resolution Documented.Enforcement Discretion Not Necessary ML20206B2751999-04-22022 April 1999 Forwards Insp Repts 50-334/99-01 & 50-412/99-01 on 990207- 0320.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206A8381999-04-20020 April 1999 Forwards Reactor Operator Initial Exam Rept 50-412/99-301 on 990322-25.All Three Reactor Operator Applicants Passed. Initial Written Exam Submittal Was Determined Not to Meet NRC Guidelines in Certain Instances ML20205R9071999-04-20020 April 1999 Forwards Second Request for Addl Info Re Response to GL 95-07, Pressure-Locking & Thermal-Binding of Safety-Related Power-Operated Gate Valves, for Beaver Valley Power Station,Units 1 & 2 ML20205Q8311999-04-14014 April 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/98-11 & 50-412/98-11 Issued on 990225.Actions Will Be Examined During Future Insp of Licensed Program ML20205L0341999-04-0909 April 1999 Forwards SER Accepting Util 971209 & 980729 Submittal of Second 10-year Interval ISI Program Plan & Associated Relief Requests for Beaver Valley Power Station,Unit 2.TER Also Encl ML20205P2431999-04-0909 April 1999 Discusses 990225 PPR & Forwards Plant Issues Matrix & Insp Plan.Ltr Provided to Minimize Resource Impact on Staff & to Allow for Scheduling Conflicts & Personnel Availability to Be Resolved in Advance of Inspector Arrival ML20205K0901999-04-0505 April 1999 Informs of Individual Exam Result on Initial Retake Exam Conducted on 990322-25 at Licensee Facility.Three Individuals Were Administered Exam & All Three Passed. Forwards Encl Re Exam.Without Encl ML20205R1791999-03-30030 March 1999 Responds to Issue Re Generic Implication of part-length Control Rod Drive Mechanism Housing Leak at Praire Island, Unit 2 & Beaver Valley Power Station,Units 1 & 2 ML20205C0301999-03-26026 March 1999 Informs That Util Responses to GL 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling & Containment Heat Removal Pumps Acceptable ML20204D7371999-03-16016 March 1999 Advises That RW Lindsey Authorized to Administer Initial Written Exams to Sh Cencic,Tf Lardin & Ta Pittas on 990322. Region I Operator Licensing Staff Will Administer Operating Tests ML20207E0201999-02-25025 February 1999 Forwards Insp Repts 50-334/98-11 & 50-412/98-11 on 981227- 990206 & Forwards Notice of Violations Re Uncontrolled Reduction of Main Condenser Vacuum ML20203D0691999-02-10010 February 1999 Forwards SE Accepting Approval of Proposed Revs to Plant QA Program Description in Chapter 17.2 of Updated Fsar,Per Util 981224 Submittal ML20206U3011999-02-0505 February 1999 Forwards Insp Repts 50-334/98-09 & 50-412/98-09 on 981116-1217 & Nov.Violation Identified Re Inadequate Design Control in Unit 2 Dc Voltage Drop Calculation ML20203A0811999-02-0404 February 1999 Forwards Request for Addl Info Re Review of Beaver Valley Power Station,Unit 1 License Amend to Allow one-time Extension of Steam Generator Insp Interval ML20199E6681999-01-14014 January 1999 Forwards RAI Re Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, for Plant,Units 1 & 2 ML20199F1961999-01-13013 January 1999 Forwards Insp Repts 50-334/98-10 & 50-412/98-10 on 981115-1226.No Violations Noted.Informs That Overall Fire Protection Program Functioning Well ML20199F5101998-12-29029 December 1998 Discusses Third 10-year Interval ISI Program Plan & Associated Relief Requests for BVPS-1 Submitted by Dlc on 970917 & 980618.Informs That NRC Has Adopted Ineel Recommendations in TER INEEL-98-00893.Forwards SE & TER ML20198K5911998-12-24024 December 1998 Forwards Emergency Response Data Sys Implementation Documents Which Include Data Point Library Updates for Fermi (Number 268),Peach Bottom (Number 269) & Beaver Valley (Number 270).Without Encls ML20198K8251998-12-21021 December 1998 Forwards SER Granting Licensee 980611,as Suppl 981015 Pump Relief Request PRR-5 for Third 10-year IST Interval for Beaver Valley Power Station,Unit 1 Pursuant 10CFR50.55(a)(f)(6)(i) ML20198B1301998-12-0909 December 1998 Advises of Planned Insp Effort Resulting from Beaver Valley Power Station mid-year Insp Resource Planning Meeting Held on 981110.Historical Listing of Plant Issues & Details of Insp Plan for Next 6 Months Encl ML20198A1301998-12-0909 December 1998 Forwards SE Re USI A-46 Program Implentation for Plant Unit 1.Staff Concludes Program Implementation Met Purpose & Intent of Criteria in Generic Implementation Procedure 2 & Suppl SER 2 for Resolution of USI A-46 ML20196J2761998-12-0404 December 1998 Forwards Corrected Pages 17 & 18 of NRC Integrated Insp Repts 50-334/98-06 & 50-412/98-06 for Exercise of Enforcement Discretion ML20196H3051998-12-0202 December 1998 Forwards Insp Repts 50-334/98-06 & 50-412/98-06 on 981004-1114.No Violations Noted.Conduct of Activities at Beaver Valley Power Station Facilities Characterized by Safe Plant Operations ML20196H2781998-12-0202 December 1998 Forwards Insp Repts 50-334/98-08 & 50-412/98-08 on 981026- 30.No Violations Noted.Plant Operations Witnessed by Team Were Conducted in Safe & Controlled Manner ML20196G9921998-12-0101 December 1998 Forwards Ltrs from Fk Koob, to JW Pack & CF Wynne Re Plant Deficiencies Assessed During 981006 Exercise Against Hancock County,Wv & Beaver County,Pa,Respectively ML20196D4371998-11-25025 November 1998 Discusses Concerns Re Announced Asset Transfer Between Firstenergy Corp & Duquesne Light Co ML20196A7101998-11-24024 November 1998 Forwards Notice of Withdrawal of Amend to License NPF-73. Proposed Change Would Have Extended on one-time Only Basis, Surveillance Interval for TSs 4.8.1.1.1.b & 4.8.1.2 Until First Entry Into Mode 4 Following Seventh Refueling Outage ML20195K3331998-11-18018 November 1998 Informs That Effective 981214,DS Collins Will Become Project Manager for Beaver Valley Power Station,Units 1 & 2 IR 05000334/19980041998-11-13013 November 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/98-04 & 50-412/98-04 Issued on 980915.C/As Will Be Examined During Future Insp of Licensed Program ML20195J2941998-11-12012 November 1998 Forwards Safety Evaluation Re First & Second 10-year Interval Inservice Insp Request for Relief ML20155K4041998-11-0505 November 1998 Forwards Insp Repts 50-334/98-07 & 50-412/98-07 on 981006- 07.No Violations Noted.Overall Performance of Emergency Response Organization Was Good 1999-09-08
[Table view] |
Text
..
< y ueg Sh5 $
fp k UNITED STATES j NUCLF.AR REGULATORY COMMISSION
$ WASHINGTON, D.C. 30e06-4001
\*****,/ August 24, 1998 Mr. J. E. Cross President - Generation Group Duquesne Light Company
- Post Office Box 4 Shippingport, PA _15077
SUBJECT:
GENERIC LETTER (GL) 97-01, " DEGRADATION OF CRDM/CEDM NOZZLE AND OTHER VESSEL CLOSURE HEAD PENETRATIONS," RESPONSES FOR BEAVER VALLEY POWER STATION, UNIT NOS.1 AND 2 (TAC NOS. M98545 AND M98546)
Dear Mr. Cross:
On April 1,1997,' the staff issued Generic Letter (GL) 97-O1, " Degradation of CRDM/CEDM Nozzle and Other Vessel Closure Head Penetrations," to the industry requesting in part that adoressees provide a description of the plans to inspect the vessel head penetration nozzles (VHPs) at their respective pressurized water reactor (PWR) designed plants, With respect to the issuance of the GL, the staff required the addressees to submit an initial response within 30 days of issuance informing the staff of the intent to comply with requested information and a follow-up response within 120 days of issuance containing the technical details to the staff's information requests, in the discussion section of the GL, the staff state'.I that "individuallicem,ees may wish
- to determine their inspection activities based on an integrated industry inspection program. . .,"
and indicated that it did not object to individual PWR licensees basing their inspection activities on an integrated industry inspection program.
As a result, the Westinghouse Owners Group (WOG) determined that it was appropriate for its members to develop a cooperative integrated inspection program in response to GL 97-01. The WOG program is documented in two topical reports issued by the Westinghouse Electric ,
Corporation (WEC), WCAP-14901, Revision 0, " Background and Methodology for Evaluation of j
Reactor Vessel Closure Head Penetration Integrity for the Westinghouse owners Group," and l WCAP-14902, Revision 0, " Background Material for Response to NRC Generic Letter 97-01: I Reactor Vessel Closure Head Penetration integrity for the Westinghouse Owners Group."
The WOG submitted the integrated programs described in WCAP-14901 and WCAP-14902 to the staff on July 25,1997.
The staff has determined by letters dated April 30,1997, and July 30,1997, that you were a 1 member of the WOG and a participant in the WOG integrated program that was developed to )
address the staff's requests in GL 97-01. In your letters of April 20,1997, and July 30,1997,
- you also indicated that the information in WEC Topical Report WCAP-14901 is applicable with
- respect to the assessment of VHP nozzles at Beaver Valley Power Station, Unit Nos.1 and 2.
The staff has reviewed your responses to GL 97-01, dated April 30,1997, and July 30,1997, and requires faither information to complete its review of your responses as they relate to the WOG's integrated program for assessing VHP nozzles at WOG member plants, and to the contents of Topical Report No. WCAP-14901. The enclosure to this letter forwards staff's inquiries in the form of a request for additional information (RAl).
e deca @ Ol !
9808290194 990624 NM Wi OM3 MPY PDR. ADOCK 05000334 P PDR t 0 ,
J. Cross The staff requests a response to the RAI within 90 days of the receipt of this letter, it should be noted that similar staff requests have been issued to other WOG member utilities. As was t't staffs position before, the staff encourcges you to address these inquiries in integrated fasli!:,n with the WOG and the Nuclear Energy institute; however, the staff also requests that you identify any deviations from the WOG's integrated program that may be specific to your facilities. The staff appreciates the efforts expended with respect to this matter.
Sincerely, original signed by l Donald S. Brinkman, S.enior Project Manager Project Directorate 1-2 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosure:
RAI 4
cc w/ encl: See next page DISTRIBUTION:
Docket File PUBLIC PDI-2 ReadingF JZwolinski RCapra MO'Brien DBrinkman OGC ACRS MEvans, RGNI EMCB JHarold OFFICE PDI-2/PM A // PDI-2/LA1 PDI-2/D NAME DBrinkman MhBrieh J RCapra RE DATE P /ty/98 h th98 9 f24/98 OFFICIAL RECORD COPY DOCUMENT NAME: A:\bvm98545.LTR l
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ a
J. Cross The staff requests a response to the RAI within 90 days of the receipt of this letter. It should be >
noted that similar staff requests have been issued to other WOG member utilities. As was the staff's position before, the staff encourages you to address these inquiries in integrated fashion with the WOG and the Nuclear Energy Institute; however, the staff also requests that you identify any deviations from the WOG's integrated program that may be specific to your facilities. The staff appreciates the efforts expended with respect to this matter, Sincerely, d a ld. O n Donald S. Brinkman, Senior Project Manager Project Directorate I-2 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 l l
Enclosurc: RAI cc w/ encl: See next page
- l
J. Cross The staff requests a response to the RAI within 90 days of the receipt of this letter. It should be noted that similar staff requests have been issued to other WOG member utilities. As was the staff's position before, the staff encourages you to address these inquiries in integrated fashion with the WOG and the Nuclear Energy Institute; however, the staff also requests that you identify I
any deviations from the WOG's integrated program that may be specific to your facilities. The staff appreciates the efforts expended with respect to this matter.
Sincerely, original signed by Donald S. Brinkman, Senior Project Manager Project Directorate 1-2 Division of Reactor Projects - t/II Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
\
Enclosure:
RAI cc w/ encl: See next page DISTRIBUTION:
Docket File PUBLIC PDI-2 Readingaf JZwolinski RCaora MO'Brien DBrinkman OGC ACRS MEvans, RGNI EMCB JHarold OFFICE PDI-2/PM A // PDl-2/LA/1 PDI-2/D NAME DBrinkman MhENeb RCapra RD
,DATE P /v//96 h /h98 9/$/98 I
( OFFICIAL RECORD COPY I l DOCUMENT NAME: A:\bvm98545.LTR
{
(
I u___ - _ - - - - - - - - - -
i J. E. Cross Beaver Valley Power Station, Units 1 & 2 I
Duquesne Ught Company cc:
i Jay E. Silberg, Esquire Bureau of Radiation Protection Shaw, Pittman, Potts & Trowbridge Pennsylvania Department of 2300 N Street, NW. Environmental Resources Washington, DC 20037 ATTN: Michael P. Murphy {
Post Office Box 2063 l Director-Safety and Ucensing Harrisburg, PA 17120 Department (BV-A)
]
1 Duquesne Ught Company Mayor of the Borough of Beaver Valley Power Station Shippingport )
PO Box 4 Post Office Box 3 Shippingport, PA 15077 Shippingport, PA 15077 Commissioner RoyM. Smith Regional Administrator, Region i I West Virginia Department of Labor U.S. Nuclear Regulatory Commission Building 3, Room 319 475 Allendale Road Capitol Complex King of Prussia, PA 19406 Charleston, WVA 25305 j Resident inspector ;
Director, Utilities Department U.S. Nuclear Regulatory Commission {
Public Utilities Commission Post Office Box 298 l 180 East Broad Street Shippingport, PA 15077 Columbus, OH 43266-0573 Director, Pennsylvania Emergency Duquesne Ught Company Management Agency Beaver Valley Power Station Post Office Box 3321 PO Box 4 Harrisburg, PA 17105-3321 Shippingport, PA 15077 ATTN: S. C. Jain, Senior Vice President Ohio EPA-DERR Nuclear Services (BV-A)
ATTN: Zack A. Clayton Post Office Box 1049 Mr. J. A. Huitz, Manager Columbus, OH 43266-0149 Projects & Support Services First Energy Dr. Judith Johnsrud 76 South Main Street National Energy Committee Akron, OH 44308 Sierra Club 433 Oriando Avenue State College, PA 16803 Duquesne Ught Company
, Beaver Valley Power Station PO Box 4 Shippingport, PA 15077 ATTN: R. D. Brandt, Division Vice President, Nuclear Operations and Plant Manager (BV-SOSB-7) l
1 Request for Additional Information Regarding Utilities Participating in the Westinghouse Owners Group (WOG)
Responses to Generic Letter (GL) 97-01 and
" Background and Methodology for Evaluation of Reactor Vessel Closure Head Penetration Integrity for the Westinghouse Owners Group" i Topical Report No. WCAP-14901, Revision 0 I
i Applicability of Topical Report No. WCAP-14901, Revision 0, to the Plant-specific Responses to GL 97-01 for Participating Member Utilities and Plants in the WOG I
- 1. Relationship and Applicabihty of WCAP-14901, Revision 0, to GL 97-01 and the WOG On April 1,1997, the staff issued Generic. Letter (GL) 97-01, " Degradation of CRDM/CEDM '
Nozzle and Other Vesssi Closure Head Penetrations," to the industry requesting in part that addressees provide a description of the plans to inspect the vessel head penetration nozzles (VHPs) at tneir respective pressurized water reactor (PWR) designed plants. With respect to the issuance of the GL, the staff required the addressees to submit an initial response within 30 days of issuance informing the staff of the intent to comply with requested information and a follow-up response within 120 days of issuance containing the technical details to the staff's information requests. In the discussion section of the GL, the staff stated that "individuallicensees may wish to determine their inspection activities based on an integrated industry inspection program. . ,,"
and indicated that it did not object to individual PWR licensees basing their inspection activities on an integrated industry inspection program.
l l
As a result, the Westinghouse Owners Group (WOG) determined that it was appropriate for its members to develop a cooperative integrated inspection program in response to GL 97-01. The WOG program is documented in two Topical Reports issued by the Westinghouse Electric Corporation (WEC), WCAP-14901, Revision 0, " Background and Methodology for Evaluation of Reactor Vessel Closure Head Penetration Integrity for the Westinghouse Owners Group," and WCAP-14902, Revision 0, " Background Material for Response to NRC Generic Letter 97-01:
Reactor Vessel Closure Head Penetration Integrity for the Westinghouse Owners Group."
The technical content provided in WCAP-14901, Revision 0, is basically the same as that provided in WCAP-14902. The difference with regard to the reports is that WOG member plants subscribing to the content of WCAP-14901 have opted to rank the susceptibility of their vessel head penetrations according to a probabilistic Weibull analysis method that was developed by WEC. In contrast, the WOG member plants subscribing to the content of WCAP-14902, Revision 0, have opted to rank the vessel head penetrations for their facilities according to a probabilistic methodology that was developed by another vendor of choice. The staff has determined by letters dated April 30,1997, and July 30,1997, that you were a member of the WOG and a participant in the WOG integrated program that was developed to address the staff's requests in GL 97-01. In your letters dated April 30,1997, and July 30,1997, you also indicated that the information in WEC Topical Report WCAP-14901 is applicabie with respect to the assessment of VHP nozzles at Beaver Valley Power Station, Unit Nos.1 and 2.
l l
Enclosure b __
1
. ?
l l
2 1
The staff has reviewed your responses to GL 97-01, dated April 30,1997, and July 30,1997, i and requires further information to complete its review of your responses as they relate to the WOG's integrated program for assessing VHP nozzles at WOG member plants, and to the contents of Topical Report No. WCAP-14901, The staff requests the following information with respect to the content of your responses to GL 97-01, dated April 30,1997, and July 30,1997, and to the content of WCAP-14901 as it relates to these responses:
I i
- 1. In WCAP-14901 WEC did not provide any conclusions as to what the probabilistic failure model would lead the WOG to conclude with respect to the assessment of primary l water stress corrosion cracking (PWSCC) in WEC-designed vessel head penetrations. j With respect to the proba'oilistic susceptibility model (e.g., probabilistic failure model) provided in WCAP-14901: !
{
- a. Provide the susceptibility rankings compiled for the WOG member plants for which WCAP-14901 is applicable, in regard to other WOG member plants to which WCAP-14901 is applicable, include the basis for establishing the ranking of your plants relative to the others.
- b. Describe how the probabilistic failure modelin WCAP-14901 for assessing postulated flaws in vessel head penetration nozzles was benchmarked, and provided a list and discussion of the standards the modelwas benchmarked against.
- c. Provide additionalinformation regarding how the probabilistic failure models in WCAP-14901 will be refined to allow the input of plant-specific inspection data into the model's analysis methodology.
- d. Describe how the variability in product forms, material specifications, and heat treatments used to fabricate each control rod drive mechanism (CRDM) penetration nozzle at the WCG member utilities are addressed in the probabilistic crack initiation and growth models described or referenced in Topical Report No WCAP-14901.
- 2. Table 1-2 in WCAP-14901 provides a summary of the key tasks in WEC's vessel head penetration nozzle assessment program. The table indicates that the Tasks for (1)
Evaluation of PWSCC Mitigation Methods, (2) Crack Growth Data and Testing, and (3)
Crack initiation Characterization Studies have not been completed and are still in progress, in light of the fact that the probabilistic susceptibility models appear to be dependent in part on PWSCC crack initiation and growth estimates, provide your best estimate when these tasks will be completed by WEC, and describe how these activities relate to and will be used to update the probabilistic susceptibility assessment of VHP nozzles at your plants.
r !
.a
[ .:..
4
- 3. In the Nuclear Energy Institute (NEI) letters of January 29,1998 (Ref.1), and April 1, (
1998 (Ref. 2), NE! indicated that inspection plans have been developed for the VHP nonles at the Farley Unit 2 plant in the year 2002, and the Diablo Canyon Unit 2 plant in the year 2001, respectively. The staff has noted that although you have endorsed the !
probabilistic susceptibility model described in WCAP-14901, Revision 0, other WOG member licensees hure andorsed a probabilistic susceptibility model developed by an altemate vendor of choice. The WOG's proposal to inspect the VHP nonles at the Farley Unit 2 and Diablo Canyon Unit 2 plants appears to be based on a composite assessment of the VHP noules at all WOG member plants. Verify that such a composite I ranking assessment has been applied to the evaluation of VHP nonles at your plants. If }
composite rankings of the VHP noules at WOG member plants have been obtained from I the composite results of the two models, justify why application of the probabilistic susceptibility model described in WCAP-14901, Revision 0, would yield the same comparable relative rankings of the VHP nonles for your plants as would application of the attemate probabilistic susceptibility model used by the WOG member plants not subscribing to WCAP-14901, Revision O. Comment on the susceptibility rankings of the VHP nonles at your plants relative to the susceptibility rankings of the VHP nonles at the Farley Unit 2 and Diablo Canyon Unit 2 plants.
REFERENCES
- 1. January 19,1998 - Letter from David J. Modeen, Director of Engineering, Nuclear Generation t Division, Nuclear Energy Institute, to Mr. G. C. Lainas, Acting Director, Division of Engineering, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission )
(Untitled).
- 2. April 1,1995 - Letter from David J. Modeen, Director of Engineering, Nuclear Generation Division, Nuclear Energy Institute, to Mr. G. C. Lainas, Acting Director, Division of Engineering, Office of Nuclear Reactor Regulation, U.S. Nuclear Regula"
SUBJECT:
Generic Letter 97-01, ' Degradation of CRDM/CEDM Nonles and Other Vessel Closure Head Penetrations.' "
1