_ _ _ _ _ _ _ _ _ _ _ _ _ -

MEMORANDUM TO: Thomas H. Essig, Acting Chief Generic issues and Environmental Projects Branch Division of Reactor Program Management Office of Nuclear Reactor Regulation i

FROM:

Peter C. Wen, Project Manager Generic issues and Ersvironmental Projects Branch Division of Reactor Program Management Office of Nuclear Reactor Regulation

SUBJECT:

NOTICE OF MEETING WITH WESTINGHOUSE OWNERS GROUP (WOG)

DATE AND TIME:

September 9,1998 9:00 a.m. - 11:00 a.m.

LOCATION:

U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, Maryland 20852 Room O-6811 PURPOSE:

To discuss issues related to WCAP-14486, Rev 1, "ECCS Hot Leg Recirculation Elimination for Westinghouse 3 and 4 Loop Design NSSS" and WCAP-14404, " Methodology for Incorporating Hot Leg Nozzle Gaps into BASH" PARTICIPANTS:

NBC WOG T. Collins R. Bryan E. Weiss D. Garner W. Lyon T. Andreychek P. Wen, et. al.

K. Vavrek, et. al.

Project No. 694 cc:

See next page Meetings between the NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, interveners, or other parties to attend as observers pursuant to " Commission Policy Statement on Staff Meeting Open to the Public," 59 Federa/ Register 48344,9/20/94. However, portions of the meeting may be closed to protect Westinghouse proprietary information. Members of the public who wish to attend should contact Peter Wen at (301) 415-2832.

Y DISTRIBUTION: Sea next page

//

/ D SC:PGj k OFFICE PM:PGEB NAME PWen:ayw'pcyj FAkethaivicz

})i c 3 DATE 8//9/98 8/p/98 9908260224 980820 ti, PDR TOPRP EMWEST

~

k)

C1-Di?

s C

PDR NBC FU CENTER CDPs

_ weums ww1

p atrug k

'V UNITED STATES f,

j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20066-0001

'+4.... 4 o

MEMORAi4DUM TO: Thomas H. Essig, Acting Chief Generic Issues and Environmental Projects Branch Division of Reactor Program Management Office of Nuclear Reactor Regulation FROM:

Pe ter C. Wen, Project Manager v C.

Generic Issues and Environment Projects Branch Division of Reactor Program Management i

Office of Nuclear Reactor Regulation

SUBJECT:

NOTICE OF MEETING WITH WESTINGHOUSE OWNERS GROUP (WOG)

DATE AND TIME:

September 9,1998 9:00 a.m. - 11:00 a.m.

LOCATION:

U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, Maryland 20852 Room O-0B11 PURPOSE:

To discuss issues related to WCAP-14486, Rev 1, "ECCS Hot Leg Recirculation Elimination for Westinghouse 3 and 4 Loop Design NSSS" and WCAP-14404, " Methodology for incorporating Hot Leg Nozzle Gaps into BASH" PARTICIPANTS:

NBC WOG T. Collins R. Bryan E. Weiss D. Gamer W. Lyon T. Andreychek P. Wen, et. al.

K. Vavrek, et. al.

Project No. 694 cc:

See next page Meetings between the NRC technical staff and applicants or licensees are open for interested l

members of the public, petitioners, interveners, or other parties to attend as observers pursuant i

to " Commission Policy Statement on Staff Meeting Open to the Public," 59 Federal Register 48344,9/20/94. However, portions of the meeting may t'e closed to protect Westinghouse proprietary information. Members of the public who wish to attend should contact Peter Wen at (301) 415-2832.

l l

L.

_ _.i

Westinghouse Owners Group Project No. '694 cc

Mr. Nicholas Liparulo, Manager Equipment Design and Regulatory Engineering Westinghouse Electric Corporation Mail Stop ECE 4-15 P.O. Box 355 Pittsburgh, PA 15230-0355 Mr. Andrew Drake, Project Manager Westinghouse Owners Group Westinghouse Electric Corporation Mail Stop ECE 5-16 P.O. Box 355 Pittsburgh, PA 15230-0355

- Mr. Jack Bastin, Director Regulsiory Affairs Westinghouse Electric Corporation 11921 Rockville Pike

- Suite 107 Rockville, MD 20852 Mr. Hank Sepp, Manager-

' Regulatory and Licensing Engineering Westinghouse Electric Corporation PO Box 355 Pittsburgh, PA 15230-0355 l

L i

o.

@(fl

  • 3,.

l DISTRIBUTION: MTG. NOTICE W/WOG DATED Auaust 20.1998

- Hard Cooy Central File PUBLIC

- PGEB r/f OGC i

ACRS

)

. OWFN Receptionist PWen EMail SCollins i

FMiraglia RZimmerman BBoger BSheron JRoe DMatthews TEssig FAkstulewicz GHolahan SNewberry TCollins EWeiss WLyon PMNS OPA

.