ML20237B480

From kanterella
Jump to navigation Jump to search
Forwards MOR for July 1998 & Corrections Made to Pages 3-6 Re Year to Date & Cumulative Net Electrical Energy Values. Errors Were Made Due to watt-hour Meter Problem That Occurred in Mar 1998
ML20237B480
Person / Time
Site: Byron  Constellation icon.png
Issue date: 08/10/1998
From: Wozniak D
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20237B483 List:
References
BYRON-98-0233, BYRON-98-233, NUDOCS 9808180323
Download: ML20237B480 (1)


Text

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ _ _ _ _ _ _ _ _ _ _ _ _ _

l Commonwealth 1:dison Company

!!)ron Generating Nation 4150 North German (,lturch Hoat!

Il} ron,11. 61010979 n Tel Hl54%5 H I

's August 10,1998 LTR:

BYRON 98-0233 i

FILE:

2.7.200 j

U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 ATTENTION:

Document Control Desk

SUBJECT:

Monthly Operating Report l

Byron Nuclear Power Station, Units 1 and 2

{

NRC Docket Numbers: 50: 454 and 455 Gentlemen:

Enclosed for your information is the Monthly Operating Report covering Byron Nuclear Power Station for the period July 1 through July 31,1998.

Please note that adjustments have been made to previously submitted Year To Date and Cumulative Net Electrical Energy values found on pages 3 and 6 of this month's report. This was due to a watt-hour meter problem that occurred in March of 1998.

Sincerely, D. B. Wozniak Station Manager Byron Nuclear Power Station i

DBW/JWrp

,f cc:

Regional Administrator Rlli Byron Project Manager - NRR Senior Resident inspector - Byron Office of Nuclear Safety - IDNS INPo Records Center l

B. Lewis, McGraw - Hill Nuclear Publications Dept.

I 9808180323 980810 PDR ADOCK 05000454 R

PDR (pa\\98byrltrs\\980233.wpf-1)

A Unicom Company