I CnAnus II. Cnest Baltimore Gas and Electric Company Vice President Calvert Cliffs Nuclear Power Plant A
I Nuclear Energy 1650 Calvert Cliffs Parkway I,usby, Maryland 20657 410 495-4455 August 12,1998 U. S. Nuclear Regulatory Commission Washington, DC 205i."
ATTENTION:
Document Control Desk
SUBJECT:
Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50-317 & 50-318 Rerponse to Generic Letter 98-01," Year 2000 Readiness of Computer Systems at Nuclear Power Plants" The purpose of this letter is to respond to the Nuclear Regulatory Commission's request for information regarding year 2000 (Y2K) readiness at nuclear power plants. Generic Letter 98-01 requires two responses. The first response was required by August 10,1998, and the second response by July 1,1999.
This letter prov; des the first response. Because of an oversight, our response is late. This delay was discussed with the NRC Project Manager, Mr. G. S. Vissing, on August 11,1998, after the oversight was discovered.
Requirement One:
"Within 90 days of the date of this generic letter, submit a written response indicating whether or not you have pursued and are continuing to pursue a Y2K program such as, or similar to, that ontlined in NEl/NUSMG 97-07, [ Nuclear Utility Year 2000 Readiness], augmented appropriately in the areas of risk management, contingency planning, and remediation of embedded systems.
If your program significantly differs from the NEI/NUSMG guidance, present a brief description of the programs that have already been completed, are being conducted, or are planned to ensure Year 2000 readiness of the computer systems at your facility (ies). This response must address the program's scope, assessment pmcess, plans for corrective actions (ir.cluding testing and schedules), QA [ quality assurance] measures, contingency plans, and regulatory compliance."
Response One:
Baltimore Gas and Electric Company has pursued and is continuing to pursue a Y2K readiness program similar to that outlined in NEI/NUSMG 97-07. The program addresses potential Y2K problems that impact safety-related systems and other systems required by nuclear power plant license or NRC regulations. The facility program includes identifying and where appropriate, remediating embedded systems. The program provides for risk management efTorts and :he development of contingency plans i
prior to critical dates.
9800170040 980812 f
PDR ADOCK 05000317
( g_/ f p,
p PDR
Docum:nt Control Desk August 12,1998 Page 2 m
Requirement Two:
"Upon completing your Y2K program or, in any event, no later than July 1,1999, submit a written response confirming that your facility is Y2K ready, or will be Y2K ready, by the year 2000 with regard to compliance with the terms and conditions of your license (s) and NRC regulations. If your program is i
. incomplete as of that date, your response must contain a status report, including completion schedules, of I
work remaining to be done to confirm your facility is/will be Y2K ready by the year 2000."
Response Two will be submitted by July 1,1999.
j Should you have questions regarding this matter, we will be pleased to discuss them with you.
Very truly yours, i
aY fn +
STATE OF MARYLAND
- TO WIT:
l COUNTY OF CALVERT I, Charles II. Cruse, being duly sworn, state that I am Vice President, Nuclear Energy Division, Baltimore Gas and Electric Coriipany (BGE), and that I am duly authorized to execute and file this response on behalf of BGE. To the best of my knowledge and belief, the statements contained in this document are true and correct. To the extent that these statements are not based on my personal l
knowledge, they are based upon information provided by other BGE employees and/or consultants. Such j
information has been reviewed in accordance with company practice and I believ to be reliable.
// -rarv l
/
l Supscrjbed and sworn before me, a Notary p(ublic in and for the State of Maryland and Cou L2LtlRettl
. this l'A day of [ UAGAL 1998.
i I
WITNESS my liand and Notarial Seal:
M31)
O 11 l
Notary Public i
My Commission Expires:
b I
/fD 1 Dale CliC/TER/bjd cc: