Similar Documents at Fermi |
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217N4261999-10-25025 October 1999 Forwards Amend 17 to License DPR-9 & Safety Evaluation. Amend Revises TS by Deleting SR D.3.c,which Required Weekly Observation of Nitrogen Cover Gas Pressure within Sodium Storage Tanks Located in Sodium Building NRC-99-0085, Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl1999-10-22022 October 1999 Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl NRC-99-0094, Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed1999-10-22022 October 1999 Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed ML20217P1661999-10-21021 October 1999 Forwards Insp Rept 50-341/99-17 on 990927-1005.No Violations Noted ML20217M0771999-10-19019 October 1999 Confirms Discussion Between GL Shear,M Mitchell,E Kosky, D Williams,B Rumins,D Harmon & W Rutenberg in Public Meeting on 990923.Purpose of Meeting Was to Discuss Current Status RP Program at Enrico Fermi 2 ML20217N9231999-10-15015 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 40 ML20217E5671999-10-14014 October 1999 First Partial Response to FOIA Request for Documents.Records in App a Already Available in Pdr.App B Records Encl & Being Released in Entirety NRC-99-0087, Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons1999-10-12012 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons NRC-99-0083, Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-10-0707 October 1999 Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal ML20217D5331999-10-0707 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 39 ML20217F5931999-10-0707 October 1999 Forwards Insp Rept 50-341/99-11 on 990724-0908.Two Violations Re Failure to Follow Procedures While Sampling Standby Liquid Control Tank & Wear Dosimetry Properly Being Treated as Noncited Violations ML20217B8261999-10-0404 October 1999 Forwards Summary of Decommissioning Insp Plan for Fy 2000. Plan Will Be Updated Annually & May Be Revised at Any Time Based Upon Future Insp Findings,Events & Resource Availability ML20212J8121999-10-0101 October 1999 Discusses Plant,Unit 2 Completion of Licensing Action for GL 98-01 & Suppl 1, Y2K Readiness of Computer Sys at Npps. Ack Efforts That Licensee Have Completed to Date in Preparing Plant for Y2K Transition ML20212K8881999-09-30030 September 1999 Refers to 990928 Meeting Conducted at Fermi Unit 2 to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PSA Staff ML20217A3261999-09-30030 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 38 NRC-99-0091, Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations1999-09-27027 September 1999 Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations ML20212J8331999-09-27027 September 1999 Responds to Licensee 990924 Request That NRC Exercise Discretion Not to Enforce Compliance with Actions Required in TS 3/4.6.1.8.Ltr Documents 990923 Telcon with Util in Which NRC Orally Issued NOED ML20216G9791999-09-24024 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 37 NRC-99-0092, Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys1999-09-24024 September 1999 Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys ML20216H3561999-09-23023 September 1999 Informs That During 990914 Telcon,L Sanders & M Bielby Made Arrangements with NRC to Inspect Licensed Operator Requalification Program at Fermi Nuclear Station for Week of 991129 Which Coincides with Util Regularly Scheduled Exam ML20216H4541999-09-23023 September 1999 Informs That During 990914 Telcon L Sanders & M Bielby Made Arrangements for Administration of Licensing Exams at Fermi Nuclear Station for Week of Jan 31,2000.NRC Will Make Exam Validation Visit to Facility During Week of Jan 10,2000 ML20212F3241999-09-20020 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 36 NRC-99-0081, Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public1999-09-17017 September 1999 Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public ML20217A9421999-09-0909 September 1999 Informs That NRC Plan to Conduct Addl Resident Insps Beyond Core Insp Program Over Next 6 Months to Assess Improvements in Areas of Procedural Compliance & Quality of Work. Historical Listing of Plant Issues Encl NRC-99-0079, Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-09-0808 September 1999 Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20211Q0991999-09-0303 September 1999 Forwards Rev 35 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0090, Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld1999-09-0303 September 1999 Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld NRC-99-0066, Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d)1999-08-30030 August 1999 Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d) ML20211G4951999-08-24024 August 1999 Forwards Rev 34 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0055, Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval1999-08-19019 August 1999 Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval IR 05000341/19990131999-08-19019 August 1999 Discusses Insp Rept 50-341/99-13 & OI Rept 3-98-039 Conducted Into Potential Misconduct of Operator Formerly Employed by De.Nrc Determined That Violation of NRC Regulations Occurred.Synopsis of IO Rept Encl NRC-99-0056, Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation1999-08-19019 August 1999 Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation ML20211C0521999-08-17017 August 1999 Forwards Tables for Sections 3.6 & 3.7 of Draft Safety Evaluation of Proposed Conversion of Current TS to Improved Standard TS NRC-99-0089, Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-08-17017 August 1999 Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20217E6181999-08-13013 August 1999 FOIA Request for Documents Re Implementing Regulations in 10CFR & Requesting That Region III Task Interface Agreement (TIA) Related to Fermi 2 Plant Be Made Available IR 05000341/19990011999-08-10010 August 1999 Forwards Insp Rept 50-341/99-01 on 990619-0723 & Nov. Violation of Concern Because Operators Did Not Understand License Requirements & Placed Plant in Configuration Where EDG 11 Was Removed from Service IR 05000341/19990121999-08-0606 August 1999 Forwards Insp Rept 50-341/99-12 on 990712-0716.No Violations Noted.Insp Focused on Implementation of Plant Chemistry & Radiological Environ Monitoring Programs & Operation of post-accident Sampling Sys ML20211C4761999-08-0606 August 1999 Forwards Draft Safety Evaluation Re Proposed Conversion of Current TS to Improved Standard TS NRC-99-0057, Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS1999-08-0404 August 1999 Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS ML20210N5451999-08-0303 August 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 33 NRC-99-0077, Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS1999-07-26026 July 1999 Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS ML20210J2121999-07-23023 July 1999 Discusses NRC OI Investigation Rept 3-98-039 Completed on 990524 & Forwards Notice of Violation NRC-99-0053, Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl1999-07-15015 July 1999 Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl ML20209H7211999-07-14014 July 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 32 NRC-99-0054, Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal1999-07-13013 July 1999 Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal ML20209F6571999-07-12012 July 1999 Forwards Insp Rept 50-341/99-09 on 990516-0618.No Violations Noted.Weak Procedural Guidance,Communications Issues & Configuration Control Weaknessess Were Evident NRC-99-0052, Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions1999-07-0707 July 1999 Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions ML20196J5511999-07-0202 July 1999 Discusses GL 92-01,Rev 1,Supp 1, Rv Integrity, Issued by NRC on 950519 & DE Responses & 980729 for Fermi 2.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 as Result of Review of Responses ML20209C6141999-07-0101 July 1999 Rev 31 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0076, Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included1999-06-30030 June 1999 Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARNRC-99-0094, Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed1999-10-22022 October 1999 Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed NRC-99-0085, Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl1999-10-22022 October 1999 Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl ML20217N9231999-10-15015 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 40 NRC-99-0087, Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons1999-10-12012 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons NRC-99-0083, Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-10-0707 October 1999 Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal ML20217D5331999-10-0707 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 39 ML20217A3261999-09-30030 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 38 NRC-99-0091, Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations1999-09-27027 September 1999 Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations ML20216G9791999-09-24024 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 37 NRC-99-0092, Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys1999-09-24024 September 1999 Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys ML20212F3241999-09-20020 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 36 NRC-99-0081, Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public1999-09-17017 September 1999 Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public NRC-99-0079, Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-09-0808 September 1999 Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev NRC-99-0090, Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld1999-09-0303 September 1999 Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld ML20211Q0991999-09-0303 September 1999 Forwards Rev 35 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0066, Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d)1999-08-30030 August 1999 Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d) ML20211G4951999-08-24024 August 1999 Forwards Rev 34 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0056, Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation1999-08-19019 August 1999 Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation NRC-99-0055, Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval1999-08-19019 August 1999 Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval NRC-99-0089, Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-08-17017 August 1999 Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20217E6181999-08-13013 August 1999 FOIA Request for Documents Re Implementing Regulations in 10CFR & Requesting That Region III Task Interface Agreement (TIA) Related to Fermi 2 Plant Be Made Available NRC-99-0057, Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS1999-08-0404 August 1999 Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS ML20210N5451999-08-0303 August 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 33 NRC-99-0077, Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS1999-07-26026 July 1999 Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS NRC-99-0053, Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl1999-07-15015 July 1999 Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl ML20209H7211999-07-14014 July 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 32 NRC-99-0054, Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal1999-07-13013 July 1999 Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal NRC-99-0052, Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions1999-07-0707 July 1999 Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions ML20209C6141999-07-0101 July 1999 Rev 31 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0049, Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Disclosure Encl1999-06-30030 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Disclosure Encl NRC-99-0076, Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included1999-06-30030 June 1999 Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included ML20209C1081999-06-29029 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 30 NRC-99-0050, Forwards Rev 7 to ITS Submittal of 980403,to Provide Remaining Responses to NRC RAIs Re ITS Sections 3.5 & 3.8. Revision Instructions Included1999-06-24024 June 1999 Forwards Rev 7 to ITS Submittal of 980403,to Provide Remaining Responses to NRC RAIs Re ITS Sections 3.5 & 3.8. Revision Instructions Included NRC-99-0075, Forwards Operator License Renewal Application,Nrc Forms 398 & 396 for CR Effan,License SOP-30186-3.Encl Withheld1999-06-22022 June 1999 Forwards Operator License Renewal Application,Nrc Forms 398 & 396 for CR Effan,License SOP-30186-3.Encl Withheld ML20212J3861999-06-18018 June 1999 Forwards Rev 29 to Approved UFSAR LCR That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0047, Responds to NRC 990513 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Revised Design Calculation DC-5957, GL 96-06 Calculations, Encl1999-06-0909 June 1999 Responds to NRC 990513 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Revised Design Calculation DC-5957, GL 96-06 Calculations, Encl ML20195G2001999-06-0808 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 28 ML20195E7391999-06-0303 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 27 NRC-99-0046, Forwards Rev 6 to Fermi 2 ITS Submittal ,to Provide Remaining Responses to NRC RAI Re ITS Section 3.3, & Update ITS Submittal to Reflect Responses.Brief Abstract of Changes Contained in Attachment 11999-06-0202 June 1999 Forwards Rev 6 to Fermi 2 ITS Submittal ,to Provide Remaining Responses to NRC RAI Re ITS Section 3.3, & Update ITS Submittal to Reflect Responses.Brief Abstract of Changes Contained in Attachment 1 ML20207D9631999-05-26026 May 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section) ML20195B3381999-05-19019 May 1999 Forwards Rev 25 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section) NRC-99-0040, Requests NRC Approval of Revs to Weld Tables of Encl Relief Requests RR-A21,rev 1 & RR-A22,rev 1.Revs Do Not Impact Basis for Original Requests for Relief Because There Is No Change to Technical Basis or Proposed Alternative1999-05-14014 May 1999 Requests NRC Approval of Revs to Weld Tables of Encl Relief Requests RR-A21,rev 1 & RR-A22,rev 1.Revs Do Not Impact Basis for Original Requests for Relief Because There Is No Change to Technical Basis or Proposed Alternative NRC-99-0039, Requests Relief from ASME Section XI Requirement to Examine Essentially 100% of Selected Category B-J Pipe Welds,Per 10CFR50.55a(g)(5)(iii).Relief Request RR-A23,encl1999-05-14014 May 1999 Requests Relief from ASME Section XI Requirement to Examine Essentially 100% of Selected Category B-J Pipe Welds,Per 10CFR50.55a(g)(5)(iii).Relief Request RR-A23,encl NRC-99-0041, Requests Relief from ASME Section XI Requirements to Examine Essentially 100% of Accessible Category B-D Nozzle Welds,Per 10CFR50.55a(g)(5)(iii).Rev 1 to Relief Request RR-A6,encl1999-05-14014 May 1999 Requests Relief from ASME Section XI Requirements to Examine Essentially 100% of Accessible Category B-D Nozzle Welds,Per 10CFR50.55a(g)(5)(iii).Rev 1 to Relief Request RR-A6,encl NRC-99-0038, Requests Relief from ASME Section XI 1980 Requirement to Examine Essentially 100% If Category B-A RPV Shell Weld Lengths,Per 10CFR50.55a(g)(5)(iii)1999-05-14014 May 1999 Requests Relief from ASME Section XI 1980 Requirement to Examine Essentially 100% If Category B-A RPV Shell Weld Lengths,Per 10CFR50.55a(g)(5)(iii) NRC-99-0045, Forwards Rev 5a to Fermi 980403 Submittal,Converting TS to Its.Encl Rev Provides Remaining Responses to NRC RAIs Re ITS Section 3.6 Contained in NRC 990211 Rai.Brief Abstract of Changes & Responses to Rai,Encl1999-05-0707 May 1999 Forwards Rev 5a to Fermi 980403 Submittal,Converting TS to Its.Encl Rev Provides Remaining Responses to NRC RAIs Re ITS Section 3.6 Contained in NRC 990211 Rai.Brief Abstract of Changes & Responses to Rai,Encl NRC-99-0044, Forwards Rev 5 to ITS to Provide Responses to RAI Re ITS Section 3.6 (Except ITS Section 3.6.1.3) Contained in & Update in ITS Submittal to Reflect Responses1999-04-30030 April 1999 Forwards Rev 5 to ITS to Provide Responses to RAI Re ITS Section 3.6 (Except ITS Section 3.6.1.3) Contained in & Update in ITS Submittal to Reflect Responses NRC-99-0059, Provides Notification Required by 10CFR50.82(a)(7) of Changes to Fermi 1 Decommissioning Cost Estimate1999-04-29029 April 1999 Provides Notification Required by 10CFR50.82(a)(7) of Changes to Fermi 1 Decommissioning Cost Estimate ML20206E2941999-04-28028 April 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 24 NRC-99-0037, Forwards Rev 9 to Fermi 2 Ufsar,Per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of Changes to QA Program & Vol 1 of Technical Requirements Manual,Encl1999-04-26026 April 1999 Forwards Rev 9 to Fermi 2 Ufsar,Per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of Changes to QA Program & Vol 1 of Technical Requirements Manual,Encl 1999-09-08
[Table view] |
Text
_-
Paul Fessler Plant Managei I Fermi 2 e
- 6400 North I)ixie liwy, Nesport, MI 48166 Tel: 734.586.5325 Detroit Edison W \
July 27,1998 NRC 98-0116 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555 1
References; 1) Fermi 2 i NRC Docket No. 50-341 l
NRC License No. NPF-43 i
- 2) Detroit Edison Letter to the NRC, " Relief Request Update for the First Ten-Year Interval Inservice Inspection (ISI)
Nondestructive Examination (NDE) Program", NRC-98-0060, i dated April 16,1998
- 3) NRC Letter to Detroit Edison," Request for Additional Information (RAI) Regarding the Proposed Requests for Relief for the first 10-Year Interval Inservice Inspection (ISI)
Nondestructive Examination (NDE) Program at Fermi 2 (TAC No. MA1570)", dated May 28,1998
- 4) Detroit Edison Letter to the NRC, " Response to Request for Additional Information Relief Request Update for the if First Ten Year ISI NDE Program", NRC-98-0093, dated June 19,1998 i
Subject:
Clarification of the Requirements for Alternative Visual Examination Specified in RR-A21 and RR-A22 O w , wwa Requests for relief from the American Society ofMechanical Engineers (ASME)
Code,Section XI requirements were submitted to the Nuclear Regulatory Commission
.(NRC) for the Fermi 2 Nuclear Power Plant First Ten-Year Interval ISI NDE Program l
9000070258 900727 PDR ADOCK 05000461 G PDR A DTE Energy Company
(
USNRC-
, NRC-98-0116 Pa, ge 2 in Reference 2. This submittal was followed by a Request for Additional Information (RAI) in Reference 3. Detroit Edison responded to the RAI in Reference 4. In a conference call on July 15,1998, the NRC staffindicated that review of the RAI submittal (Reference 3) had been performed, and clarification of requirements for the.
alternative visual examination specified in Relief Requests RR-A21 and RR-A22 was requested.
RR-A21 and RR-A22 have been revised to include this information and are enclosed.
Also discussed was Relief Request RR-Al for ultrasonic examination coverage of reactor pressure vessel shell welds. The NRC reviewers indicated that they would prefer that these examinations be completed prior to approving this relief request and -
would likely defer its approval. 'Accordingly, Detroit Edison is requesting that RR-Al be withdrawn. RR-Al will be resubmitted following the RF-06 refueling and inspection outage.
If you have any questions or requests for additional information, please contact Mr.
Norman K. Peterson at (734) 586-4258.
Sincerely ,
j
. uLd L~~
Enclosures I
-cc: B. L. Burgess G. A. Harris
- A. J. Kugler M. T. Anderson (INEEL)
Regional Administrator, Region III
- Supervisor, Electric Operators,
! Michigan Public Service Commission L -
r
- Enclosure to
, NRC-98-0116 oi -
9 J
.1 1
ENCLOSURE 1~
+-
FERMI 2 NRC DOCKET NO. 50-341 NRC LICENSE NO. NPF-43 RELIEF REQUEST RR-A21 4 PAGES =
I i-I i-I f l 1
l
. -g ;
i RELIEF REQUEST RR-A21 l
COMPONENT FUNCT!ON/ DESCRIPTION:
Piping Integral Attachment Welds (see attached Table I for identification)
SYSTEMS:
Main Steam (B21)
Reactor Recirculation (B31) l Residual Heat Removal (El1)
Core Spray (E21)
Feedwater (N21)
ASME CODE CLASS:
Class 1 ASME SECTION XI REQUIREMENTS:
ASME Section XI,1980 Edition including the Winter 1981 Addenda, Subsection IWB, Table IWB-2500-1, Category B-K-1, item B10.10 requires surface examination of all integrally welded piping attachments that have a base meul design thickness of 5/8" or greater.
' e BASIS FOR RELIEF:
Pursuant to 10 CFR 50.55a(a)(3)(i) Detroit Edison is requesting relief from ASME Section XI requirements to perform complete (> 90% coverage) surface examination of all integrally welded piping attachments that have a base metal design thickness of 5/8" or greater.
The proposed alternative is partial nondestructive examination supplemented by visual ;
examination. Technicaljustification for the adequacy of the alternative is substantiated i by changes in the ASME Code. )
I The relief request also identifies burdens associated with engineering resource impacts, clamp removal, location restoration, which would represent a burden to existing ;
resources. Identification of these burdens are provided only in support of the need for an I alternative. The engineering impacts mentioned are incurred in diverting limited l engineering resources away from other tasks. I L The structural integrity of the piping pressure boundary including welded attachments was originally demonstrated during construction by meeting the requirements of ASME j Section III. Design, fabrication, installation, inspection, and examination satisfied the appropriate Code requirements. Construction examinations used techniques similar to those used for inservice examinations (surface NDE methods). During the Fermi l Preservice Inspection volumetric examinations were also performed. The construction I and preservice examinations were usuali :ompleted prior to installation of the support Pageiof4 l
L________-______________. L
l l
f me,mbers.. Therefore the extent of accessibility is not specifically know until the first ,
inservice examination is completed. Integral attachment locations remaining to be -
examined were compared to locations similar in design and any expected limitations are
]
listed in the table.
l The pressure boundary passed the required preservice hydrostatic test and all subsequent l pressure tests through the fifth refueling and inspection outage (RF-05).
l Complete examinations meeting the coverage requirements of ASME Code Section XI j are performed on welds of similar configurations which utilized the same weld techniques, procedures and materials. The welds with complete examinations are spread throughout the Class I systems and subject to similar operating and environmental
_ conditions as the partially examined welds. No service related discontinuities have been discovered on welds fully examined or those partially examined. Additionally, there is no industry history of ASME Class I service induced attachment weld failures. It is reasonable to expect that the unexamined portions are also acceptable, The absence of significant ;ntegral attachment weld problems is further evidenced by ASME Code Case N-509 which allows a reduced sample size of only 10% of all integral attaclunents. This Code Case has been approved at other nuclear facilities (e. g., Duane Arnold) and was incorporated into the 1995 Addenda of ASME Section XI. Detroit
!- Edison has not requested to implement this Code Case, which would reduce the l inspection population to approximately 10 locations, during our first inspection interval.
We are only requesting partial relief of coverage on specific locations included in the 29 l locations where examinations can be performed.
The average surface coverage for the incomplete examinations completed and listed in Table 1 is 73%. To obtain complete Code coverage at each location, the component support would have to be disassembled and the pipe clamp assembly removed.
l Temporary line support would have to be evaluated by engineering and installed as j necessary. The additional engineering resources, time, field personnel, and radiation j exposure required to attain full coverage is not consistent with the minimal risk l associated with these items, as reflected by plant and industry experience as well as current Code requirements.
Radiation exposure for a best case location assuming a conservative effective (averaged) dose rate of Smr/hr and a minimum of 16 manhours to remove and reinstall the clamp assembly and inspect the location would result in at least 80mr additional exposure per location (approximately 1.7R minimum accumulated dose). Note that this assumption uses an effective averaged dose rate, and actual dose on a pipe and is often much higher.
Removal of the clamps could actually increase the possibility of damaging other components such as nozzles and penetrations due to additional line stress. Additionally, the time for disassembly and reassembly does not assume mechanical difficulties such as temporary line support, seized bolts, and removal and reinstallation of welded lug retainers from the clamps, that will greatly increase the time and dose impacts.
Page 2 of 4
ALTERNATIVE EXAMINATION:
Detroit Edison proposes that in addition to the surface examination of the exposed portion oflug welds and required base metal volume, that a supplemental visual examination to the extent practical by the examiner be performed. Additionally, leakage inspections are performed at the completion of each refueling outage per Category B-P.
The supplemental visual examinations for partial exams previously performed were conducted in a manner similar to ASME Section XI, VT-1. The purpose of the supplemental visual exam is to additionally determine the condition of the integral attachment, weld, or required base metal volume in the areas with surface examination limitations. The visual examination is performed to identify conditions that would indicate impaired structural integrity such as cracks, evidence ofleakage, abnormal wear, corrosion / erosion, or physical damage on the accessible surfaces of the component. The visual examinations are performed within 24 inches of the component surface. Mirrors and artificial lighting are used as determined to be necessary by the examiner. Previous examinations were performed by qualified and certified nondestructive examination personnel, knowledgeable of welding, material processing, and service induced defects, no defects were reported. This is consistent with the results of all nondestructive surface examinations compW :d to date for ASME Class 1 and 2 integral attachments and the VT-3 of ASME Class 3 miegral attachments. All supplemental visual exams beginning at RF-06 will be performed by ASME Section XI certified VT examiners. Any of the conditions listed above will be reported on the data s'neet required by the surface examination procedure and as required by the Fermi corrective action program. If any of the above conditions are reported, clamp disassembly will be performed as necessary to allow performance of a full surface examination.
Based on the coverage achievable, physical limitations, comparison of Fermi ISI Program scope as compared to current Code requirements, and low empirical probability of weld failure, Detroit Edison considers the proposed alternative examination to provide an acceptable level of quality and safety.
APPLICABLE TIME PERIOD:
Reliefis requested for tie first 10-year inspection interval, l
l l
l Page 3 of 4 l '
RR-A21 Table 1 Limited Examinations Category Weld Percentage Limitation Alternate
/ Item Identification Complete Description Examination )
B-K 1/B10.10 FW-PS-2-B2- 70 % Clamp at spring B21-5353- Supplemental i AAl-AA4 Expected 1181 Visual B-K-l/B 10.10 FW-PS-2-D2- 70 % Clamp at spring B21-5355- Supplemental I AAl-AA4 IIDI Visual B-K-l/B 10.10 FW-RD-2-A2- 68% Clamp at spring B31-5357- Supplemental All AL4 HA2 Visual B-K-1/B 10.10 FW-RD-2-B2- 68% Clamp at spring B31-5359- Supplemental All-AL4 Expected 11B2 Visual B-K-1/B 10.10 SW-RS-2-A2-W4- 68 % Clamp at spring B31-5357- Supplemental W7 Expected liAl Visual B-K-1/B 10.10 SW-RS-2-B2- 68% Clamp at spring B31-5359- Supplemental W6A-W9A HB1 Visual B-K-1/B10.10 PSFW-El 1-2298- 69% per lug Clamp at rigid support Supplemental 833A-F El 1-2298-G04 Visual B-K-1/B 10.10 PSFW-El 1-2299- 50% per lug Clamp at spring El1-2299- Supplemental 836A-F Expected G03 Visual B-K-1/B 10.10 PSFW-El1-2299- 50% per lug Clamp at spring EIl-2299- Supplemental 781A-D G01 Visual B-K-1/B 10.10 SW.El 1 2327- 90% per lug Clamp at restraint ElI- Supplemental 2WD-2WJ 2327-G03 Visual B-K-1/B 10.10 SW-E21-3052- 88% per lug Clamp at spring E21-3052- Supplemental 2WN2WR G02 Visual B-K-1/B l0.10 PSFW-E21-3052- 84% per lug Clamp at spring E21-3052- Supplemental 803A-D G04 Visual B-K-l/B 10.10 SW-E21-3053- 86% per lug Clamp at spring E21-3053- Supplemental 2WN-2WR G02 Visual B-K-1/B10.10 SW-E21-3052- 88% per lug Clamp at spring E21-3052- Supplemental 2WS-2WV Expected G09 Visual B-K-1/B l 0.10 SW-E21-3053- 69% per lug Clamp at spring E21-3053 Supplemental 2WS-2WV G10 Visual B-K 1/B10.10 SW-E21-3053- 88% per lug Clamp at spring E21-3053- Supplemental 795A-795D G08 Visual B-K 1/B10.10 SW-N21-2336- 86% per lug Clamp Limitation Supplemental 12WC-12Wii Visual B-K-1/B 10.10 SW-N21-2336- 66% per lug Clamp Limitation Supplemental 12WJ-12WP Visual B-K-1/B 10.10 SW-N21-2336- 0% per lug inaccessible for .MT due to Supplemental 19WB-19WE lug retainers at N213537- Visual G29 B-K-1/B10.10 SW-N21-2336- 90% per lug Clamp at snubber Supplemental
( 9WB-9WE N21-3536-G29 Visual l
B-K l/810.10 SW-N21-2336- 90% per lug Clamp at spring N21-3537- Supplemental 2WC-2WN G26 Visual 1
f l Page4 # 4
Enclosure to l
, NRC-98-0116 ENCLOSURE 2 FERMI 2 NRC DOCKET NO. 50-341 NRC LICENSE NO. NPF-43 RELIEF REQUEST RR-A22 4 PAGES 1
1 i
l
RELIEF REQUEST RR-A22 COMPONENT FUNCTION / DESCRIPTION:
Piping Integral Attachment Welds (see attached Table 1 for identification)
SYSTEMS:
Residual Heat Removal (El1)
High Pressure Coolant Injection (E41)
ASME CODE CLASS:
Class 2 ASME SECTION XI REQUIREMENTS:
ASME Section XI,1980 Edition including the Winter 1981 Addenda, Subsection IWC, Table IWC-2500-1, Category C-C, items C3.10 and C3.20 require surface examination of integrally welded piping attachments that have a base metal design thickness of 3/4" or greater.
BASIS FOR RELIEF:
Pursuant to 10 CFR 50.55a(a)(3)(i) Detroit Edison is requesting relief from ASME Section XI requirements to perform complete (> 90% coverage) surface examination of all integrally welded piping attachments that have a base metal design thickness of 3/4" or greater.
The proposed alternative for Fermi is partial nondestructive examination supplemented by visual examination. Technicaljustification for the adequacy of the alternative is substantiated by changes in the ASME Code.
4 This relief request also identifies burdens associated with engineering resource impacts, clamp removal, location restoration, which would represent a burden to existing resources. Identification of these burdens are provided only in support of the need for an alternative. The engineering impacts mentioned are incurred in diverting limited engineering resources away from other tasks.
The structural integrity of the piping pressure boundary including welded attachments was originally demonstrated during construction by meeting the requirements of ASME Section III. Design, fabrication, installation, inspection, and examination satisfied the l appropriate Code requirements. Construction examinations used techniques similar to those used for inservice examinations (surface NDE methods). During the Fermi Preservice Inspection volumetric examinations were also performed. The construction and preservice examinations were usually completed prior to installation of the support members. Therefore the extent of accessibility is not specifically know until the first inservice examination is completed. Integral attachment locations remaining to be Page1of4 L
expmined were compared to locations similar in design and any expected limitations are listed in the table.
The pressure boundary passed the required preservice hydrostatic test and all subsequent pressure tests through the fifth refueling and inspection outage (RF-05).
' Complete examinations meeting the coverage requirements of ASME Code Section XI l are performed on welds of similar configurations which utilized the same weld )
techniques, procedures and materials. The welds with complete examinations are subject i ta similar operating and environmental conditions as the partially examined welds. No service related discontinuities have been discovered on welds fully examined or those j partially examined. Additionally, there is no industry history of ASME Class 2 service induced attachment weld failures. It is reasonable to expect that the unexamined portions are also acceptable.
The absence of significant integral attachment weld problems is further evidenced by ASME Code Case N-509 which allows a reduced sample size of only 10% of all integral <
attachments. This Code Case has been approved at other nuclear facilities (e. g., Duane Arnold) and was incorporated into the 1995 Addenda of ASME Section XI. Fermi has not requested to implement this Code Case, which would reduce the inspection population to approximately 19 locations, during the first inspection interval. We are l asking for partial relief of coverage on specific locations included in the 39 locations f where examinations can be performed. l The average surface coverage for the incomplete examinations completed and listed in Table 1 is 87%. To obtain complete Code coverage at each location, the component support would have to be disassembled and the pipe clamp assembly removed.
Temporary line support would have to be evaluated by engineering and installed as necessary. The additional engineering resources, time, field personnel, and radiation exposure required to attain full coverage is not consistent with the minimal risk associated with these items, as reflected by plant and industry experience as well as current Code requirements.
Radiation exposure for a best case location assuming a conservative effective (averaged) l dose rate of Smr/hr and a minimum of 16 manhours to remove and reinstall the clamp assembly and inspect the location would result in at least 80mr additional exposure per
- location (approximately 640mr minimum accumulated dose). Note that this assumption uses an effective averaged dose rate, and actual dose on a pipe and is often much higher.
- l. Removal of the clamps could actually increase the possibility of damaging other components such as nozzles and penetrations due to additional line stress. Additionally, the time for disassembly and reassembly does not assume mechanical difficulties such as temporary line support, seized bolts, and removal and reinstallation of welded lug retainers from the clamps, that will greatly increase the time and dose impacts.
Page 2 of 4
r 4 .
ALTERNATIVE EXAMINATION:
Detroit Edison proposes that in addition to the partial surface examination of the exposed portion oflug welds and required base metal volume, that a supplemental visual examination to the extent practical by the examiner be performed. Additionally, leakage inspections are performed each inspection period per Category C-H.
The supplemental visual examinations for partial exams previously performed were conducted in a manner similar to ASME Section XI, VT-1. The purpose of the supplemental visual exam is to additionally determine the condition of the integral attachment, weld, or required base metal volume in the areas with surface examination limitations. The visual examination is performed to identify conditions that would indicate impaired structural integrity such as cracks, evidence ofleakage, abnormal wear, corrosion / erosion, or physical damage on the accessible surfaces of the component. The visual examinations are performed within 24 inches of the component surface. Mirrors and artificial lighting are used as determined to be necessary by the examiner. Previous examinations were performed by qualified and certified nondestructive examination personnel, knowledgeable of welding, material processing, and service induced defects, no defects were reported. This is consistent with the results of all nondestructive surface examinations completed to date for ASME Class 1 and 2 integral attachments and the VT-3 of ASME Class 3 integral attachments. All supplemental visual exams beginning at RF-06 will be performed by ASME Section XI certified VT examiners. Any of the conditions listed above will be reported on the data sheet required by the surface examination procedure and as required by the Fermi corrective action program. If any of the above conditions are reported, clamp disassembly will be performed as necessary to allow performance of a full surface examination.
Based on the coverage achievable, physical limitations, comparison of the Fermi ISI NDE Program scope as compared to current Code requirements, and low empirical probability of weld failure, Detroit Edison considers the proposed attemative examination to provide an acceptable level of quality and safety.
APPLICABLE TIME PERIOD:
Reliefis requested for the first 10-year inspection interval.
I l
l Page 3 of 4 L__._._ - ._m._.m. _ _ _ . _ . . _ _ . _ - ,_. . _.
RR-A22 Table 1 Limited Examinations Category W eld Percentage Limitation Alternate
/ Item Identification Complete Description Examination C-C/C3.20 PSFW-El 1 3146- 83% perlug Clamp at restraint Ell- supplemental 606A-L 3146-G24 visual C-C/C3.20 PSFW-El 1-3146- 100% per lug Clamp at restraint El1- supplemental 952A-L for lugs 3146-G36 visual B,E,H,K,50%
for others C-C/C3.20 SW-El 1-3151 ~90% per lug Clamp at spring supplemental 4WE-4WK expected El 1-3151-G05 visual C-C/C3.20 SW-E l 1-3151- ~90% per lug Clamp at spring supplemental 10WC-10WH expected Ell-3151-G01 visual C-C/C3.20 SW El1-3158- 87% per lug Lugs A,C,D, & F supplemental 583A-583F lugs B & E inaccessible due to lug visual retainers on restraint ElI-3158-G52 C-C/C3.20 SW-El 1-3158- 85% per lug Clamp at spring El1-3158- supplemental 7WC-7WH G51 visual C-C/C3.20 PSFW-E41-3162- 90 % Clamp at snubber E41- supplemental 583A F 3162-G20 visual C-C/C3.20 PSFW E41-3172 90 % Clamp at snubber E41- supplemental 592A-D 3172-Gl9 visual C-C/C3.20 PSFW-E41-3172- 80% per lug lug retainers at E41-3172- supplemental 625A-625D expected G14 visual l
l I
i Page 4 of 4
_ _ _ _ _ _ - _ - _ _ - _ _ _ ___A