Informs of Change in Commitments Re Meteorological & Dose Assessment Software.Change Necessitated by Failure of vendor-supplied Software to Perform Intended Function. Meteorological Hardware Description Encl
ML20236V652
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 11/30/1987
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CON-NRC-87-122 VPNPD-87-516, NUDOCS 8712040439
Download: ML20236V652 (5)


Text

-

3 C

l Wisconsin Electnc eowracouesur 231 W.MICHIG AN,P.O BOX 2046, MILWAUKEE,Wl 53201 (414)277-2345 NRC-87 12 2 VPNPD-8 7-516 November 30, 1987 1

Document Control Desk U.S.

NUCLEAR REGULATORY COMMISSION Washington, D.C.

20555 Gentlemen:

DOCKET NOS. 50-266 AND 50-301 METEOROLOGICAL MONITORING SYSTEM SOFTWARE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 This is to advise you of a change in our commitments regarding meteorological and dose assessment software.

This change'is necessitated by the failure of a vendor-supplied software package to perform its intended function.

The commitments contained herein are intended to replace.in entirety the meteorology-related commitments contained in our letters of December 29,.1981, January 9, 1981, and November 1, 1984.

{The unrelatedievaluation-of control room habitability included in our January 9,

1981, submittal is unaffected by these changes.')

The proposed changes to our commitments regarding meteorological software have been

~

l discussed with Mr.

W.

Snell, in the U.S. NRC Region III Office by telephone several weeks ago.

l l

A.

Historical Development As you are aware, various post-TMI requirements led us to-the procurement of a new plant process computer for Point Beach.

The new computer was to be supplied by' Electronic Associates, l

Inc. (EAI).

While the new computer _ system was being designed, l

We contracted with Energy Impact Associates (EIA) to provide l

Class A meteorological software to be installed on the new computer.

By our. letter dated October 1, 19~84, we informed you that i

I the contract with EAI.for the new plant computer system was l

terminated "because EAI was unable to meet the terms and' conditions of the contract'for re-sons not attributable to Wisconsin Electric."

Work on the meteorological software by.

EIA continued through this period with the expectation that it would be used on a new computer system.

The meteorological software design report prepared by.EIA was submitted to.you by our letter of November 1,

1984,

\\

hfiP' B712040439 871130 g (

PDR ADOCK 05000266 g

PDR g

~

7 1

l Document Control Desk i

November 30, 1987 Page 2 i

i l

i j

l Our letter of January 17, 1985, informed you of a new contract j

with Combustion Engineering for a new plant process computer system and provided a schedule for installation of the com-puter and associated systems.

At this time the EIA meteoro-J logical software was temporarily shelved to await installation on the new computer.

Consistent with the schedule in our January 17, 1985, letter, that installation was tn be complete 3 months after the fall 1987 Unit 2 outage, i.e.,

approxi-'

)

mately February 1988.

)

i Early in in 1987, we began work on the installation of the

]

j meteorological software and encountered serious problems with j

the product.

Resolution was hampered by inadequate documen-I tation.

In a telephone discussjon with EIA, we determined that the principals involved with our' contract were no longer j

with the firm, that EIA was no longer in the Class A meteoro-1 logical software business, and that technical information i

pertaining to our software was likely to havetbeen purged from EIA files.

By late summer, we concluded that further efforts i

l to salvage the package were not warranted.

)

B.

CURRENT STATUS I

j The installation of all meteorological hardware has been l

completed as originally planned.

Three meteorological towers l

are currently in operation:

the main or primary tower, the backup tower and an inland tower.

Data from all three towers is available in the control room and on the plant process computer.

Data is archived for 2 weeks at 10 minute inter-vals, and selected data is saved in the form of strip charts.

A more complete description of the meteorological hardware is provided in Attachment 1.

Offsite dose assessmment at. Point Beach has been provided by our MAD (Meteorological and Dose Assessment) program since 1932.

The MAD program uses manual entry of basic meteoro-logical data and either manual entry of radiological data or uso of internally stored source terms.

In the course of l

emergency exercises and drills at. Point Beach, this program has been shown to be very satisfactory.

It is versatile, fast, and reliable.

Reasonable agreement with both NRC.and State of Wisconsin dose predictions has been demonstrated.

It was originally intended that the dose assessment methodology l

used in MAD was to be used in conjunction with the Class A meteorological model to be developed by EIA.

The meteorological model of the MAD program is a straight line Gaussian function which yields results consistent with acci-dent analyses and other studies performed for Point Beach.

In

4 Document Control Desk November 30, 1987 Page 3 calculatingoff-centeris(e 9ths,.a meander factor of one-half of a 22.5 sector is nserva:tively assumed in either H

direction.

The program runs on a time-based case basis.

Any change in meteorological or radiological conditions constitutes.a new case.

Past cases can be edited to incorporate better data or connections, and predictions incorporate doses received in past cases as well as doses estimated for future times.

When all releases are secured, the. program performs an estimate of population doses received in all sectors.

The MAD program is available on a dedicated IBM PC-AT maintained in our EOF.

A backup is resident on the' corporate mainframe whic^a is also accessible from the EOF.

C.

PROPOSED CHANGES 1.

The existing MAD program will he permanently available at the EOF for use by the Rad Con 9aste Manager or his designated assistant (s) during i.aergencies and emergency l

drills and exercises.

While man 3al entry of meteoro-logical data will be continued,,. t should be noted that both meteorological and radiolog. cal monitoring system data will be available on the dis play screens located in the EOF.

Only field data and laberatory analyses need to i

be transferred to the EOF by telephone or high spred l

telecopier.

The MAD program is already available in the EOF.

Display of radiological monicoring system data is also available in'the EOF.

Display of meteorological data will be available in the EOF by tlm end of February, 1988.

]

2, MADCR (Meteorological And Dose assessment program for Control Room), an abbreviated versinn of the MAD program, will be installed on the plant process computer system to l

facilitate prompt initial emergency classification by l

operating personnel.

The primary dif ferences between l

MADCR and MAD are'as follows:

(a)

MADCR will calculate only~a single case consisting of existing conditions and dose rates as well as a prediction of the estimated 8-hour dose; (b)

By user selection MADCR will be capable of using real-time meteorology; i

(c)

By user selection, MADCR will be capable of using real-time radiological monitoring system data, internally stored source term data, or manually entered radiological data.

1 i

1 l

'l l

u_____-__-___

r, b

Document Control 1 Desk November 30, 1987 Page 4 l

MADCR will be available on the plant process computer system by the end of February 1988.

l 3.

The only unique meteorological characteristic in the vicinity of Point Beach is.the lake breeze phenomenon.

A subroutine is being developed to recognize the occurrence-of a lake breeze and conservatively account for.poten-tially increased concentrations, i.e.,

effectively decreased diffusion,'due to the recirculation associated l

with a lake breeze.

This refinement to the MAD and MADCR programs will be implemented by December 1988.

I With these proposed' changes to our earlier commitments, we expect to be able to meet the milestone'specified in our. January 17, 1985, letter, i.e.,

3 months following completion of the fall.1987-Unit 2 refueling outage (end of February 1988).

The final refine-ment to account for the lake breeze phenomena will be added by the end of December 1988.

J Please feel free to contact us if you need any further information, Very truly yours, QG

/[bd q.-

Faf C.

W.

Vice President Nuclear Power Copies to Resident Inspector Region III i

1 1

1 l

ATTACHMENT I POINT BLACH NUCLEAR PLANT METEOROLOGICAL HARDWARE DESCRIPTION Point Beach Nuclear Plant has three meteorological towers.

Tower 1, a 35 meter tower, is located south of the plant approximately one-half mile.

Tower 2, a 10 meter tower., is located 1/4 mile north and west of the plant.

Tower 3, also a 10 meter tower, is approximately 8 miles inland, west of Point Beach.

The instrumentation on each of hte towers is as follows:

l Tower 1.

(Main)

Wind speed 35 meters 1

Wind direction 35 meters l

Wind speed 10 meters j

Wind direction 10 meters i

Temperature 10 meters

'l Delta T between 10 and 35 meters Sigma Theta 10 meters Tower 2.

(Backup)

Wind speed 10 meters Wind direction 10 meters l

Sigma Theta 10 meters l

Precipitation ground level j

l Tower 3.

(Inland)

Wind speed 10 meters Wind direction 10 meters Sigma Theta 10 meters Ambient temp.

10 meters l

Each of these parameters is transmitted to the control room where it l

is recorded on strip chart recorders.

Most parameters are also sent i

l to the plant process computer.

Real time access is available by specific point identification on the plant process computer.

Those parameters which relate directly to the dispersion of plant gaseous effluent are displayed on a plant process computer screen.