PRELIMINARY NOTIFICATION - NOT FOR PUBLIC DISCLOSURE July 10, 1975 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE -PN-75-49 This preliminary notification constitutes EARLY notice of events of l
POSSIBLE safety or public interest significance. The information presented is as initially received without verification or evaluation and is basically all that is known by OIE staff as of 12:30 p.m. on the date of this notification.
IT SHOULD BE SPECIFICALLY NOTED THAT THIS i
l NOTIFICATION MAY CONTAIN INFORMATION THAT LATER MAY BE DETERMINED TO BE INACCURATE OR INCONSISTENT. AN OFFICE OF INSPECTION AND ENFORCEMENT
~
NOTIFICATION OF AN INCIDENT OR OCCURRENCE (BLUE SHEET) SUBSEQUENTLY RILL BE ISSUED IF WARRANTED.
l
- ~
Jacility:
Davis-Besse Unit 1
Subject:
EXPECTED PRESS COVERAGE CONCERNING IDENTIFIED ELECTRICAL DEFICIENCIES AT DAVIS-BESSE UNIT 1.
Considerable news media and public interest in the Cleveland, Ohio, area are expected to result from a news story scheduled to appear Sunday, July 13, in the Cleveland Plain-Dealer on quality assurance and installation problems with electrical work at the Davis-Besse construction site.
The problems were identified by Region III inspectors during a May 19-22 inspection. Using a sample 'of 51 safety-g related cables,.the inspectors found one or more problems associated with 15 of them.
These problems inqlude failure to meet physical separation and seismic design criteria, improper routing, incomplete
=
('
testing, and damage to insulation. Region III personnel have met with licensee top management to discuss the problems, and the licensee has_ committed to reinspect all safety-related electrical work already installed and correct any deficiencies found. An Immediate Action Letter confirming the commitment was issued May 30.
Copies of the Imed1 ate Action Letter and the Inspection Report are in the Public Document Room. Thomas Quinn, a reporter for the Cleveland newspaper, has made inquiries to Region III and Toledo Edison for his story.
Contact:
RFWarnick, IE x7261 HDThornburg, IE x7353 JGDavis, IE x7541 6
/
l Distribution:
/
l Chairman Anders Commissioner Mason S. J. Chilk, SECY l
Commissioner Gilinsky Commissioner Rowden G. F. Murphy, JCAE Commissioner Kennedy C. C. Kammerer, CA F
L. V. Gossick, EDO D.F.KnutE,IE J. A. Harris, PA O.
B. C. Rusche, NRR H. H. Brcan, ISP T. J. McTiernan, AIA 7
K. R. Chaproan, NHSS H. K. Shapar, ELD Transmitted: P Bldg l p;
H St /
- MNBB /
p ;
Luge pt [
PRELIMINARY NOTIFICATION - NOT FOR PUBLIC DISCLOSURE k.
t 9807300091 750710 PDR I&E PN-75-049 PDR 1
4 k-
%