|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARNPL-99-0564, Forwards Response to NRC Request During 990720 Meeting,To Provide Addl Details to Several Questions Re Amend Currently Under Review by Staff Pertaining to CR Habitability1999-10-19019 October 1999 Forwards Response to NRC Request During 990720 Meeting,To Provide Addl Details to Several Questions Re Amend Currently Under Review by Staff Pertaining to CR Habitability ML20217A5911999-09-30030 September 1999 Advises of NRC Plans for Future Insp Activities at Facility for Licensee to Have Opportunity to Prepare for Insps & to Provide NRC with Feedback on Any Planned Insps Which May Conflict with Plant Activities.Plant Issues Matrix Encl 05000266/LER-1999-007, Forwards LER 99-007-00 for Point Beach Nuclear Plant,Unit 1. Condition Would Be Outside App R Design Basis for Plant.New Commitments within Rept Indicated in Italics1999-09-30030 September 1999 Forwards LER 99-007-00 for Point Beach Nuclear Plant,Unit 1. Condition Would Be Outside App R Design Basis for Plant.New Commitments within Rept Indicated in Italics ML20212J7431999-09-30030 September 1999 Forwards Insp Repts 50-266/99-15 & 50-301/99-15 on 990830- 0903.No Violations Noted.Inspectors Concluded That Util Licensed Operator Requalification Training Program Satisfactorily Implemented NPL-99-0555, Discusses Rev 1,suppl 1 to GL 92-01, Reactor Vessel Structural Integrity. Calculation That Provides Evaluation of New Surveillance Data for Assessing Integrity of Unit 1 Reactor Vessel1999-09-29029 September 1999 Discusses Rev 1,suppl 1 to GL 92-01, Reactor Vessel Structural Integrity. Calculation That Provides Evaluation of New Surveillance Data for Assessing Integrity of Unit 1 Reactor Vessel ML20212K7651999-09-29029 September 1999 Forwards Insp Repts 50-266/99-13 & 50-301/99-13 on 990714-0830.No Violations Noted.Operators Responded Well to Problems with Unit 1 Instrument Air Leak & Unit 2 Turbine Governor Valve Position Fluctuation ML20212D5771999-09-15015 September 1999 Discusses Review of Response to GL 88-20,suppl 4,requesting All Licensees to Perform Ipeee.Ser,Ter & Supplemental TER Encl ML20211Q6451999-09-0808 September 1999 Forwards Operator Licensing Exam Repts 50-266/99-301OL & 50-301/99-301OL for Exams Conducted on 990726-0802 at Point Beach Npp.All Nine Applicants Passed All Sections of Exam ML20211Q4171999-09-0606 September 1999 Responds to VA Kaminskas by Informing That NRC Tentatively Scheduled Initial Licensing Exam for Operator License Applicants During Weeks of 001016 & 23.Validation of Exam Will Occur at Station During Wk of 000925 05000266/LER-1999-004, Forwards LER 99-004-01,re Fuel Oil Transfer Pump Cable in AFW Pump Room Being Outside App R Design Basis.Suppl to LER Provides Corrective Actions to Address Concerns Re Fire Disrupting Electrical Power to Fuel Oil Transfer Pump1999-09-0202 September 1999 Forwards LER 99-004-01,re Fuel Oil Transfer Pump Cable in AFW Pump Room Being Outside App R Design Basis.Suppl to LER Provides Corrective Actions to Address Concerns Re Fire Disrupting Electrical Power to Fuel Oil Transfer Pump ML20211K5261999-08-31031 August 1999 Forwards Insp Repts 50-266/99-14 & 50-301/99-14 on 990726- 30.Areas Examined within Secutity Program Identified in Rept.No Violations Noted ML20211F6941999-08-27027 August 1999 Provides Individual Exam Results for Applicants That Took Initial License Exam in July & August of 1999.Completed ES-501-2,copy of Each Individual License,Ol Exam Rept, ES-303-1,ES-303-2 & ES-401-8 Encl.Without Encl NPL-99-0473, Informs of Change Being Made to Plan Third 10-year Interval ISI Long Term Plan.Change Extends Interval from Current End Date of 001130 to 020831,due to Operating Cycle Being Increased from 12 to 18 Months1999-08-27027 August 1999 Informs of Change Being Made to Plan Third 10-year Interval ISI Long Term Plan.Change Extends Interval from Current End Date of 001130 to 020831,due to Operating Cycle Being Increased from 12 to 18 Months ML20211E8791999-08-24024 August 1999 Discusses Completion of Licensing Action for GL 96-01, Testing of Safety-Related Logic Circuits, for Point Beach Nuclear Power Plant,Units 1 & 2.Licensees Provided Requested Info & Responses Required by GL 96-01 ML20211F1501999-08-24024 August 1999 Submits Summary of Meeting Held on 990729,in Region III Office with Util Re Proposed Revs to Plant Emergency Action Level Criteria Used in Classifying Emergencies & Results of Recent Improvement Initiatives in Emergency Preparedness 05000266/LER-1999-006, Forwards LER 99-006-00 Which Describes Discovery That Postulated Fire in Central Zone of Primary Auxiliary Bldg Could Result in Spurious Operation of Pressurizer Porv. New Commitments within Rept Are Indicated in Italics1999-08-19019 August 1999 Forwards LER 99-006-00 Which Describes Discovery That Postulated Fire in Central Zone of Primary Auxiliary Bldg Could Result in Spurious Operation of Pressurizer Porv. New Commitments within Rept Are Indicated in Italics NPL-99-0477, Forwards Revised Procedures to Point Beach Nuclear Plant Epips.Revised Procedures Dtd 990723,should Be Filed in NRC Copies of Manual IAW Attached Instructions1999-08-18018 August 1999 Forwards Revised Procedures to Point Beach Nuclear Plant Epips.Revised Procedures Dtd 990723,should Be Filed in NRC Copies of Manual IAW Attached Instructions NPL-99-0426, Requests Relief from Section II of ASME B&PV Code, Nuclear Vessels, 1965 Edition,No Addenda.Detailed Info Attached1999-08-16016 August 1999 Requests Relief from Section II of ASME B&PV Code, Nuclear Vessels, 1965 Edition,No Addenda.Detailed Info Attached ML20210L9141999-08-0404 August 1999 Informs That Versions of Info Re WCAP-14787,submitted in 990622 Application for Amend,Marked Proprietary,Will Be Withheld from Public Disclosure,Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954,as Amended ML20210K5221999-08-0404 August 1999 Discusses Point Beach Nuclear Plant,Units 1 & 2 Response to Request for Info in GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity NPL-99-0436, Forwards fitness-for-duty Performance Data for six-month Period Ending 9906301999-08-0202 August 1999 Forwards fitness-for-duty Performance Data for six-month Period Ending 990630 ML20210G6011999-07-30030 July 1999 Discusses 990415 Complaint OSHA Received from Employee of Wisconsin Electric Power Co Alleging That Employee Received Lower Performance Appraisal for 1998 Because Employee Raised Safety Concerns While Performing Duties at Point Beach NPL-99-0406, Provides Response to NRC GL 99-02, Lab Testing of Nuclear- Grade Activated Charcoal1999-07-29029 July 1999 Provides Response to NRC GL 99-02, Lab Testing of Nuclear- Grade Activated Charcoal ML20210H0211999-07-28028 July 1999 Forwards Insp Repts 50-266/99-09 & 50-301/99-09 on 990528-0713.Two Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20210G2441999-07-26026 July 1999 Discusses 990714 Meeting with PRA Staff to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PRA Staff NPL-99-0408, Forwards Pbnps,Units 1 & 2 Plant Simulation Four-Yr Rept, IAW 10CFR55.45(b)(5)(ii).Rept Describes Certification Program Tests Conducted from 1996-1999,identifies Test Discrepancies Still Outstanding & Schedules for 2000-20031999-07-15015 July 1999 Forwards Pbnps,Units 1 & 2 Plant Simulation Four-Yr Rept, IAW 10CFR55.45(b)(5)(ii).Rept Describes Certification Program Tests Conducted from 1996-1999,identifies Test Discrepancies Still Outstanding & Schedules for 2000-2003 ML20209H5471999-07-14014 July 1999 Forwards Insp Repts 50-266/99-12 & 50-301/99-12 on 990614-18.One Violation Noted,But Being Treated as non-cited violation.Long-term MOV Program Not Sufficiently Established to close-out NRC Review of Program,Per GL 89-10 NPL-99-0395, Forwards Partial Response to NRC 990512 RAI Re TS Change 204 Re Control Room Habitability.Meeting Is Planned with NRC to Discuss Issues Related to Control Room & Primary Auxiliary Bldg Ventilation Sys Modifications1999-07-12012 July 1999 Forwards Partial Response to NRC 990512 RAI Re TS Change 204 Re Control Room Habitability.Meeting Is Planned with NRC to Discuss Issues Related to Control Room & Primary Auxiliary Bldg Ventilation Sys Modifications NPL-99-0390, Projects Listed Major near-term License Amend Requests That Could Be Expected to Impact Staff Resources Into Fiscal Years 2000 & 2001,in Response to Administrative Ltr 99-021999-07-0808 July 1999 Projects Listed Major near-term License Amend Requests That Could Be Expected to Impact Staff Resources Into Fiscal Years 2000 & 2001,in Response to Administrative Ltr 99-02 NPL-99-0388, Forwards MORs for June 1999 & Revised MORs for May 1999 for Pbnps,Units 1 & 21999-07-0707 July 1999 Forwards MORs for June 1999 & Revised MORs for May 1999 for Pbnps,Units 1 & 2 NPL-99-0381, Submits Response to NRC GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants. GL 98-01 Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl1999-06-30030 June 1999 Submits Response to NRC GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants. GL 98-01 Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl ML20196J4161999-06-30030 June 1999 Discusses Relief Requests Submitted by Wisconsin Electric on 980930 for Pump & Valve Inservice Testing Program,Rev 5. Safety Evaluation Authorizing Relief Requests VRR-01,VRR-02, PRR-01 & ROJ-16 Encl NPL-99-0379, Documents Telcon with Hg Ashar of NRC Re Licensee Intentions & Basis for Reselection of Control Tendons in Pbnps Containment Structures.Plants Are Currently Completing 28th Year Tendon Surveillance During Summer of 19991999-06-29029 June 1999 Documents Telcon with Hg Ashar of NRC Re Licensee Intentions & Basis for Reselection of Control Tendons in Pbnps Containment Structures.Plants Are Currently Completing 28th Year Tendon Surveillance During Summer of 1999 NPL-99-0376, Forwards Errata to Pbnp 1998 Annual Monitoring Rept, Originally Submitted by Ltr Dtd 990427.List of Corrections, Provided1999-06-28028 June 1999 Forwards Errata to Pbnp 1998 Annual Monitoring Rept, Originally Submitted by Ltr Dtd 990427.List of Corrections, Provided NPL-99-0353, Forwards June 1999 Rev to FSAR for Point Beach Nuclear Plant,Units 1 & 2, IAW Requirements of 10CFR50.71(e).Each Package Contains Revised FSAR Pages That Are to Be Inserted IAW Instructions1999-06-23023 June 1999 Forwards June 1999 Rev to FSAR for Point Beach Nuclear Plant,Units 1 & 2, IAW Requirements of 10CFR50.71(e).Each Package Contains Revised FSAR Pages That Are to Be Inserted IAW Instructions ML20196D4931999-06-18018 June 1999 Forwards Insp Repts 50-266/99-08 & 50-301/99-08 on 990411- 0527.No Violations Noted.Operator Crew Response to Equipment Induced Challenges Generally Good.Handling of Steam Plume in Unit 1 Turbine Bldg Particularly Good ML20195J9471999-06-16016 June 1999 Discusses Ltr from NRC ,re Arrangements Made to Finalized Initial Licensed Operator Exam to Be Administered at Point Beach Nuclear Plant During Week of 990726 ML20196A2931999-06-16016 June 1999 Ack Receipt of Transmitting Changes to Listed Sections of Point Beach Nuclear Plant Security Plan & ISFSI Security Plan,Submitted IAW 10CFR50.54(p).No NRC Approval Is Required Since Changes Do Not Decrease Effectiveness ML20195J9251999-06-14014 June 1999 Discusses 990610 Telcon Between Wp Walker & D Mcneil Re Arrangements for NRC to Inspect Licensed Operator Requalification Program at Point Beach Nuclear Power Plant for Week of 990816 05000266/LER-1999-005, Forwards LER 99-005-00,re Failure of Shell of 4B FW Heater Which Resulted in Significant Steam Leak & Manual Trip. New Commitments within Rept Are Indicated in Italics1999-06-11011 June 1999 Forwards LER 99-005-00,re Failure of Shell of 4B FW Heater Which Resulted in Significant Steam Leak & Manual Trip. New Commitments within Rept Are Indicated in Italics NPL-99-0336, Forwards Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1, IAW ASME Section Xi,Subsection IWA-62301999-06-10010 June 1999 Forwards Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1, IAW ASME Section Xi,Subsection IWA-6230 NPL-99-0330, Forwards Revs to Pbnp Security Plan Sections 2.1,2.4,3.1, Figures A,D & T & Pbnp ISFSI Security Plan Section 2.0, Dtd 990604.Plans Withheld1999-06-0404 June 1999 Forwards Revs to Pbnp Security Plan Sections 2.1,2.4,3.1, Figures A,D & T & Pbnp ISFSI Security Plan Section 2.0, Dtd 990604.Plans Withheld 05000301/LER-1999-003, Forwards LER 99-003-00 for Point Beach Nuclear Plant,Unit 2. Rept Is Provided in Accordance with 10CFR50.73(a)(2)(i)(B), as Any Operation or Condition Prohibited by Plant Tech Specs1999-05-28028 May 1999 Forwards LER 99-003-00 for Point Beach Nuclear Plant,Unit 2. Rept Is Provided in Accordance with 10CFR50.73(a)(2)(i)(B), as Any Operation or Condition Prohibited by Plant Tech Specs NPL-99-0319, Provides Main Control Board Wiring Separation Project Status Update Rept for Pbnps,Units 1 & 21999-05-28028 May 1999 Provides Main Control Board Wiring Separation Project Status Update Rept for Pbnps,Units 1 & 2 ML20206T3691999-05-17017 May 1999 Ltr Contract,Task Order 242 Entitled, Review Point Beach 1 & 2 Conversion of Current TS for Electrical Power Systems to Improved TS Based on Standard TS, Under Contract NRC-03-95-026 ML20206N5561999-05-13013 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Cm Craig Will Be Section Chief for Point Beach Npp.Organization Chart Encl ML20206P2551999-05-12012 May 1999 Forwards Handout Provided to NRC by Wisconsin Electric at 990504 Meeting Which Discussed Several Recent Operational Issues & Results of Recent Improvement Initiatives in Engineering ML20206N5331999-05-12012 May 1999 Forwards RAI Re & Suppl by Oral Presentation During 980604 Meeting,Requesting Amend for Plant,Units 1 & 2 to Revise TSs 15.3.12 & 15.4.11 ML20196F3211999-05-11011 May 1999 Requests Proprietary WCAP-14787, W Revised Thermal Design Procedure Instrument Uncertainty Methodology for Wepc Point Beach Units 1 & 2 (Fuel Upgrade & Uprate to 1656 Mwt-NSSS Power), Be Withheld from Public Disclosure ML20206K0391999-05-0707 May 1999 Forwards Insp Repts 50-266/99-06 & 50-301/99-06 on 990223- 0410.Ten Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARNPL-99-0564, Forwards Response to NRC Request During 990720 Meeting,To Provide Addl Details to Several Questions Re Amend Currently Under Review by Staff Pertaining to CR Habitability1999-10-19019 October 1999 Forwards Response to NRC Request During 990720 Meeting,To Provide Addl Details to Several Questions Re Amend Currently Under Review by Staff Pertaining to CR Habitability 05000266/LER-1999-007, Forwards LER 99-007-00 for Point Beach Nuclear Plant,Unit 1. Condition Would Be Outside App R Design Basis for Plant.New Commitments within Rept Indicated in Italics1999-09-30030 September 1999 Forwards LER 99-007-00 for Point Beach Nuclear Plant,Unit 1. Condition Would Be Outside App R Design Basis for Plant.New Commitments within Rept Indicated in Italics NPL-99-0555, Discusses Rev 1,suppl 1 to GL 92-01, Reactor Vessel Structural Integrity. Calculation That Provides Evaluation of New Surveillance Data for Assessing Integrity of Unit 1 Reactor Vessel1999-09-29029 September 1999 Discusses Rev 1,suppl 1 to GL 92-01, Reactor Vessel Structural Integrity. Calculation That Provides Evaluation of New Surveillance Data for Assessing Integrity of Unit 1 Reactor Vessel 05000266/LER-1999-004, Forwards LER 99-004-01,re Fuel Oil Transfer Pump Cable in AFW Pump Room Being Outside App R Design Basis.Suppl to LER Provides Corrective Actions to Address Concerns Re Fire Disrupting Electrical Power to Fuel Oil Transfer Pump1999-09-0202 September 1999 Forwards LER 99-004-01,re Fuel Oil Transfer Pump Cable in AFW Pump Room Being Outside App R Design Basis.Suppl to LER Provides Corrective Actions to Address Concerns Re Fire Disrupting Electrical Power to Fuel Oil Transfer Pump NPL-99-0473, Informs of Change Being Made to Plan Third 10-year Interval ISI Long Term Plan.Change Extends Interval from Current End Date of 001130 to 020831,due to Operating Cycle Being Increased from 12 to 18 Months1999-08-27027 August 1999 Informs of Change Being Made to Plan Third 10-year Interval ISI Long Term Plan.Change Extends Interval from Current End Date of 001130 to 020831,due to Operating Cycle Being Increased from 12 to 18 Months 05000266/LER-1999-006, Forwards LER 99-006-00 Which Describes Discovery That Postulated Fire in Central Zone of Primary Auxiliary Bldg Could Result in Spurious Operation of Pressurizer Porv. New Commitments within Rept Are Indicated in Italics1999-08-19019 August 1999 Forwards LER 99-006-00 Which Describes Discovery That Postulated Fire in Central Zone of Primary Auxiliary Bldg Could Result in Spurious Operation of Pressurizer Porv. New Commitments within Rept Are Indicated in Italics NPL-99-0477, Forwards Revised Procedures to Point Beach Nuclear Plant Epips.Revised Procedures Dtd 990723,should Be Filed in NRC Copies of Manual IAW Attached Instructions1999-08-18018 August 1999 Forwards Revised Procedures to Point Beach Nuclear Plant Epips.Revised Procedures Dtd 990723,should Be Filed in NRC Copies of Manual IAW Attached Instructions NPL-99-0426, Requests Relief from Section II of ASME B&PV Code, Nuclear Vessels, 1965 Edition,No Addenda.Detailed Info Attached1999-08-16016 August 1999 Requests Relief from Section II of ASME B&PV Code, Nuclear Vessels, 1965 Edition,No Addenda.Detailed Info Attached NPL-99-0436, Forwards fitness-for-duty Performance Data for six-month Period Ending 9906301999-08-0202 August 1999 Forwards fitness-for-duty Performance Data for six-month Period Ending 990630 NPL-99-0406, Provides Response to NRC GL 99-02, Lab Testing of Nuclear- Grade Activated Charcoal1999-07-29029 July 1999 Provides Response to NRC GL 99-02, Lab Testing of Nuclear- Grade Activated Charcoal NPL-99-0408, Forwards Pbnps,Units 1 & 2 Plant Simulation Four-Yr Rept, IAW 10CFR55.45(b)(5)(ii).Rept Describes Certification Program Tests Conducted from 1996-1999,identifies Test Discrepancies Still Outstanding & Schedules for 2000-20031999-07-15015 July 1999 Forwards Pbnps,Units 1 & 2 Plant Simulation Four-Yr Rept, IAW 10CFR55.45(b)(5)(ii).Rept Describes Certification Program Tests Conducted from 1996-1999,identifies Test Discrepancies Still Outstanding & Schedules for 2000-2003 NPL-99-0395, Forwards Partial Response to NRC 990512 RAI Re TS Change 204 Re Control Room Habitability.Meeting Is Planned with NRC to Discuss Issues Related to Control Room & Primary Auxiliary Bldg Ventilation Sys Modifications1999-07-12012 July 1999 Forwards Partial Response to NRC 990512 RAI Re TS Change 204 Re Control Room Habitability.Meeting Is Planned with NRC to Discuss Issues Related to Control Room & Primary Auxiliary Bldg Ventilation Sys Modifications NPL-99-0390, Projects Listed Major near-term License Amend Requests That Could Be Expected to Impact Staff Resources Into Fiscal Years 2000 & 2001,in Response to Administrative Ltr 99-021999-07-0808 July 1999 Projects Listed Major near-term License Amend Requests That Could Be Expected to Impact Staff Resources Into Fiscal Years 2000 & 2001,in Response to Administrative Ltr 99-02 NPL-99-0388, Forwards MORs for June 1999 & Revised MORs for May 1999 for Pbnps,Units 1 & 21999-07-0707 July 1999 Forwards MORs for June 1999 & Revised MORs for May 1999 for Pbnps,Units 1 & 2 NPL-99-0381, Submits Response to NRC GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants. GL 98-01 Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl1999-06-30030 June 1999 Submits Response to NRC GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants. GL 98-01 Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl NPL-99-0379, Documents Telcon with Hg Ashar of NRC Re Licensee Intentions & Basis for Reselection of Control Tendons in Pbnps Containment Structures.Plants Are Currently Completing 28th Year Tendon Surveillance During Summer of 19991999-06-29029 June 1999 Documents Telcon with Hg Ashar of NRC Re Licensee Intentions & Basis for Reselection of Control Tendons in Pbnps Containment Structures.Plants Are Currently Completing 28th Year Tendon Surveillance During Summer of 1999 NPL-99-0376, Forwards Errata to Pbnp 1998 Annual Monitoring Rept, Originally Submitted by Ltr Dtd 990427.List of Corrections, Provided1999-06-28028 June 1999 Forwards Errata to Pbnp 1998 Annual Monitoring Rept, Originally Submitted by Ltr Dtd 990427.List of Corrections, Provided NPL-99-0353, Forwards June 1999 Rev to FSAR for Point Beach Nuclear Plant,Units 1 & 2, IAW Requirements of 10CFR50.71(e).Each Package Contains Revised FSAR Pages That Are to Be Inserted IAW Instructions1999-06-23023 June 1999 Forwards June 1999 Rev to FSAR for Point Beach Nuclear Plant,Units 1 & 2, IAW Requirements of 10CFR50.71(e).Each Package Contains Revised FSAR Pages That Are to Be Inserted IAW Instructions 05000266/LER-1999-005, Forwards LER 99-005-00,re Failure of Shell of 4B FW Heater Which Resulted in Significant Steam Leak & Manual Trip. New Commitments within Rept Are Indicated in Italics1999-06-11011 June 1999 Forwards LER 99-005-00,re Failure of Shell of 4B FW Heater Which Resulted in Significant Steam Leak & Manual Trip. New Commitments within Rept Are Indicated in Italics NPL-99-0336, Forwards Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1, IAW ASME Section Xi,Subsection IWA-62301999-06-10010 June 1999 Forwards Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1, IAW ASME Section Xi,Subsection IWA-6230 NPL-99-0330, Forwards Revs to Pbnp Security Plan Sections 2.1,2.4,3.1, Figures A,D & T & Pbnp ISFSI Security Plan Section 2.0, Dtd 990604.Plans Withheld1999-06-0404 June 1999 Forwards Revs to Pbnp Security Plan Sections 2.1,2.4,3.1, Figures A,D & T & Pbnp ISFSI Security Plan Section 2.0, Dtd 990604.Plans Withheld NPL-99-0319, Provides Main Control Board Wiring Separation Project Status Update Rept for Pbnps,Units 1 & 21999-05-28028 May 1999 Provides Main Control Board Wiring Separation Project Status Update Rept for Pbnps,Units 1 & 2 05000301/LER-1999-003, Forwards LER 99-003-00 for Point Beach Nuclear Plant,Unit 2. Rept Is Provided in Accordance with 10CFR50.73(a)(2)(i)(B), as Any Operation or Condition Prohibited by Plant Tech Specs1999-05-28028 May 1999 Forwards LER 99-003-00 for Point Beach Nuclear Plant,Unit 2. Rept Is Provided in Accordance with 10CFR50.73(a)(2)(i)(B), as Any Operation or Condition Prohibited by Plant Tech Specs ML20196F3211999-05-11011 May 1999 Requests Proprietary WCAP-14787, W Revised Thermal Design Procedure Instrument Uncertainty Methodology for Wepc Point Beach Units 1 & 2 (Fuel Upgrade & Uprate to 1656 Mwt-NSSS Power), Be Withheld from Public Disclosure NPL-99-0242, Submits Commitment Schedule Update,Per GL 95-07 Re Pressure Locking & Thermal Binding of safety-related power-operated Gate Valves.Unit 1 Block Valve Replacement Will Be Performed During Upcoming 1999 U1R25 Outage1999-04-27027 April 1999 Submits Commitment Schedule Update,Per GL 95-07 Re Pressure Locking & Thermal Binding of safety-related power-operated Gate Valves.Unit 1 Block Valve Replacement Will Be Performed During Upcoming 1999 U1R25 Outage NPL-99-0246, Forwards 1998 Annual Monitoring Rept, for Pbnps Units 1 & 2.Revised ODCM & Environ Manual Are Encl1999-04-27027 April 1999 Forwards 1998 Annual Monitoring Rept, for Pbnps Units 1 & 2.Revised ODCM & Environ Manual Are Encl ML20206C2361999-04-22022 April 1999 Forwards 1998 Annual Rept to Stockholders of Wepc Which Includes Certified Financial Statements,Per 10CFR50.71 NPL-99-0230, Submits Clarification of Which Portions of OMa-1988 Parts 6 & 10 Are Being Utilized at Pbnp for IST Program Implementation & Cold SD & RO Justifications,Per 990218 Telcon with NRC1999-04-19019 April 1999 Submits Clarification of Which Portions of OMa-1988 Parts 6 & 10 Are Being Utilized at Pbnp for IST Program Implementation & Cold SD & RO Justifications,Per 990218 Telcon with NRC 05000301/LER-1999-002, Forwards LER 99-002-00 Re Discovery That Cable Necessary to Provide Plant Parameter Required to Be Monitored for App R Safe SD Location Was Not Routed Independent of Appropriate Fire Zone.Commitments in Rept Indicated in Italic1999-04-16016 April 1999 Forwards LER 99-002-00 Re Discovery That Cable Necessary to Provide Plant Parameter Required to Be Monitored for App R Safe SD Location Was Not Routed Independent of Appropriate Fire Zone.Commitments in Rept Indicated in Italics NPL-99-0219, Provides Final Notification of Change to Commitments Documented in LER 266/97-022-00 Re Electrical Short Circuits During CR Fire1999-04-15015 April 1999 Provides Final Notification of Change to Commitments Documented in LER 266/97-022-00 Re Electrical Short Circuits During CR Fire 05000266/LER-1999-001, Forwards LER 99-001-01,describing Discovery That Common Min Recirculation Flow Line Return to RWST for Safety Injection & Containment Spray Pumps Was Partially Frozen & Would Not Pass Flow.New Commitments Indicated in Italics i1999-04-0808 April 1999 Forwards LER 99-001-01,describing Discovery That Common Min Recirculation Flow Line Return to RWST for Safety Injection & Containment Spray Pumps Was Partially Frozen & Would Not Pass Flow.New Commitments Indicated in Italics in Rept NPL-99-0174, Confirms Completion of Requested Actions in Accordance with Required Response of GL 96-01 for Unit 2.Confirmation of Completion for Unit 1 Was Provided in Ltr Npl 98-0591,dtd 9807141999-03-30030 March 1999 Confirms Completion of Requested Actions in Accordance with Required Response of GL 96-01 for Unit 2.Confirmation of Completion for Unit 1 Was Provided in Ltr Npl 98-0591,dtd 980714 ML20206B8231999-03-30030 March 1999 Forwards Final Exercise Rept for Biennial Radiological Emergency Preparedness Exercise Conducted on 981103 for Point Beach Power Plant.One Deficiency Identified for Manitowoc County.County Corrected Deficiency Immediately NPL-99-0177, Forwards Decommissioning Funding Status Info for Pbnp,Units 1 & 2,per 10CFR50.751999-03-30030 March 1999 Forwards Decommissioning Funding Status Info for Pbnp,Units 1 & 2,per 10CFR50.75 05000301/LER-1999-001, Forwards LER 99-001-00,re Loss of Safeguards Electrical Bus During Refueling Surveillance Testing Which Resulted in Temporary Unavailability of One Train of Decay Heat Removal. Commitments Made by Util Are Identified in Italics1999-03-10010 March 1999 Forwards LER 99-001-00,re Loss of Safeguards Electrical Bus During Refueling Surveillance Testing Which Resulted in Temporary Unavailability of One Train of Decay Heat Removal. Commitments Made by Util Are Identified in Italics NPL-99-0122, Forwards Relief Requests RR-1-19 & RR-2-25,requesting Relief from Section XI of ASME B&PV Code, Rules for Inservice Exam of NPP Components, 1986 Edition,No Addenda.Requirements for Relief Apply to Third ten-yr ISI Interval for Units 1 &1999-03-0303 March 1999 Forwards Relief Requests RR-1-19 & RR-2-25,requesting Relief from Section XI of ASME B&PV Code, Rules for Inservice Exam of NPP Components, 1986 Edition,No Addenda.Requirements for Relief Apply to Third ten-yr ISI Interval for Units 1 & 2 NPL-99-0111, Informs NRC That IAW Provisions of ASME Boiler & Pressure Code,Section Xi,Paragraphs IWA-2430(d) & IWA-2430(e),WEPC Has Extended Third 10 Yr Interval for Pressure Testing Program at Pbnp,Unit 1 by 21 Months1999-03-0303 March 1999 Informs NRC That IAW Provisions of ASME Boiler & Pressure Code,Section Xi,Paragraphs IWA-2430(d) & IWA-2430(e),WEPC Has Extended Third 10 Yr Interval for Pressure Testing Program at Pbnp,Unit 1 by 21 Months NPL-99-0116, Forwards Proprietary & non-proprietary Revised Point Beach Nuclear Plant Emergency Plan IAW 10CFR50.54(q).Proprietary Plan Withheld1999-03-0101 March 1999 Forwards Proprietary & non-proprietary Revised Point Beach Nuclear Plant Emergency Plan IAW 10CFR50.54(q).Proprietary Plan Withheld NPL-99-0115, Forwards Proprietary & non-proprietary Revised EPIPs to Point Beach Nuclear Plant,Units 1 & 21999-03-0101 March 1999 Forwards Proprietary & non-proprietary Revised EPIPs to Point Beach Nuclear Plant,Units 1 & 2 NPL-99-0114, Provides Results of Wepcs Insp,Replacement & Mechanical Testing of Reactor Internals Baffle Former Bolts During Recent Point Beach Refueling Outage1999-02-25025 February 1999 Provides Results of Wepcs Insp,Replacement & Mechanical Testing of Reactor Internals Baffle Former Bolts During Recent Point Beach Refueling Outage NPL-99-0086, Documents Commitment Change Which Is to Discontinue Actions Contained in Util Ltr Dtd 970613,after NRC Approval of LAR & Lower Containment Leak Rate Limit Is Implemented. Change Is Acceptable IAW Applicable Plant Procedure1999-02-24024 February 1999 Documents Commitment Change Which Is to Discontinue Actions Contained in Util Ltr Dtd 970613,after NRC Approval of LAR & Lower Containment Leak Rate Limit Is Implemented. Change Is Acceptable IAW Applicable Plant Procedure NPL-99-0101, Forwards Proprietary & non-proprietary Version of Rev 20 to EPIP 3.2, Emergency Response Organization Notification & Revised Index.Proprietary Info Withheld1999-02-19019 February 1999 Forwards Proprietary & non-proprietary Version of Rev 20 to EPIP 3.2, Emergency Response Organization Notification & Revised Index.Proprietary Info Withheld ML20203F7301999-02-10010 February 1999 Forwards Revs to Security Plan Sections 1.2,1.3,1.4,2.1,2.5, 2,6,2.8,6.1,6.4,6.5,B-3.0,B-4.0,B-5.0 & Figure R Dtd 990210. Evaluation & Description of Plan Revs Also Encl to Assist in NRC Review.Encls Withheld NPL-99-0067, Submits 30 Day Rept of Changes & Errors Discovered in ECCS Evaluation Models for Pbnp,Unit 21999-02-0202 February 1999 Submits 30 Day Rept of Changes & Errors Discovered in ECCS Evaluation Models for Pbnp,Unit 2 NPL-99-0064, Forwards Revised TS Bases Page 15.4.4,correcting References to Pbnp FSAR Re Reactor Containment Design.Changes Are Administrative Only & Do Not Alter Facility or Operation,As Described in FSAR or Any TS Requirement1999-02-0202 February 1999 Forwards Revised TS Bases Page 15.4.4,correcting References to Pbnp FSAR Re Reactor Containment Design.Changes Are Administrative Only & Do Not Alter Facility or Operation,As Described in FSAR or Any TS Requirement NPL-98-1032, Forwards Revs to Pbnp Security Plan Sections 1.1,1.2,2.1, 2.6,2.8,6.1 & 6.4 & Revs to Pbnp ISFSI Security Plan Sections 1.0 & 7.0,per 10CFR50.54(p).Encl Withheld1999-01-27027 January 1999 Forwards Revs to Pbnp Security Plan Sections 1.1,1.2,2.1, 2.6,2.8,6.1 & 6.4 & Revs to Pbnp ISFSI Security Plan Sections 1.0 & 7.0,per 10CFR50.54(p).Encl Withheld 05000266/LER-1998-029, Forwards LER 98-029-00,describing Discovery of Isolation of Autostart Feature for Svc Water Pumps from Unit 2,safeguards Buses During Modifications1999-01-26026 January 1999 Forwards LER 98-029-00,describing Discovery of Isolation of Autostart Feature for Svc Water Pumps from Unit 2,safeguards Buses During Modifications NPL-99-0031, Informs That Wepc Reviewed Contents of NEI to NRC & Have Verified Info Provided in Ltr Pertaining to WOG Member Plants Is Applicable to Pbnp.Attachment Responds to NRC Questions by Ref to Info in 981211 NEI Ltr1999-01-15015 January 1999 Informs That Wepc Reviewed Contents of NEI to NRC & Have Verified Info Provided in Ltr Pertaining to WOG Member Plants Is Applicable to Pbnp.Attachment Responds to NRC Questions by Ref to Info in 981211 NEI Ltr NPL-99-0004, Provides Status Update on Program Activities & Schedule for Final Resolution of Items Re Verification of Seismic Piping Class Interfaces for Point Beach Nuclear Plant,Units 1 & 21999-01-11011 January 1999 Provides Status Update on Program Activities & Schedule for Final Resolution of Items Re Verification of Seismic Piping Class Interfaces for Point Beach Nuclear Plant,Units 1 & 2 NPL-99-0012, Forwards Proprietary & Nonproprietary Revs to Epips. Proprietary Version of EPIPs Withheld1999-01-0808 January 1999 Forwards Proprietary & Nonproprietary Revs to Epips. Proprietary Version of EPIPs Withheld 1999-09-30
[Table view] Category:VENDOR/MANUFACTURER TO NRC
MONTHYEARML20042H0101990-04-0404 April 1990 Forwards Special Instructions Forwarded to Utils Re X-SAM Sys for Nuclear safety-related Cranes.Instructions Describe Actions for Making Critical Lifts Before Retrofit of Slide Device ML20196E1621988-11-29029 November 1988 Requests That Proprietary Addendum 2 to Rev 1 to WCAP-10924-P, Westinghouse Large Break LOCA Best Estimate Methodology... Be Withheld from Public Disclosure (Ref 10CFR2.790) ML20206F8811988-11-14014 November 1988 Requests That WCAP-12042 Be Withheld from Public Disclosure Per 10CFR2.790 ML20147C6611987-12-16016 December 1987 Requests That Point Beach Unit 2 Evaluation for Vibration Induced Fatigue Be Withheld from Public Disclosure (Ref 10CFR2.790) ML20236T0011987-11-20020 November 1987 Requests That Proprietary Rept Entitled Point Beach Unit 2 Steam Generator Tube Fatigue Presentation Be Withheld from Public Disclosure (Ref 10CFR2.790(b)(4)).Affidavit Encl ML20237E3721987-10-16016 October 1987 Requests That Proprietary WCAP 11573, Point Beach Unit 2 Steam Generator Sleeving Rept (Mechanical Sleeves) Be Withheld from Public Disclosure,Per 10CFR2.790(b)(4). Affidavit Encl NRC-86-3181, Forwards Listed Nonproprietary Documents Re Rod Cluster Control Assembly Performance,Per Request.Topical Rept WCAP-8183, Operational Experience W/Westinghouse Cores Issued for Input to NRC Annual Fuel Performance Rept1986-11-25025 November 1986 Forwards Listed Nonproprietary Documents Re Rod Cluster Control Assembly Performance,Per Request.Topical Rept WCAP-8183, Operational Experience W/Westinghouse Cores Issued for Input to NRC Annual Fuel Performance Rept ML20116A1481985-04-16016 April 1985 Requests Proprietary Upper Plenum Injection LOCA Program Using SECY-83-472 Methodology Be Withheld (Ref 10CFR2.790) ML20095F3181984-08-0707 August 1984 Requests Proprietary Responses to NRC Questions Re Optimized Fuel Assembly Design Be Withheld (Ref 10CFR2.790).Affidavit Encl ML20073Q2921983-04-27027 April 1983 Authorizes Utilization of Encl Affidavit Supporting Request to Withhold Info Re Steam Generator Repair from Public Disclosure,Per 10CFR2.790 ML20204F8121983-04-13013 April 1983 Forwards Affidavit AW-80-27 in Support of Request to Withhold Proprietary Info Re Effect of Radiation on Insulating Matls in Westinghouse Medium Motor Per 10CFR2.790 Re Encl Util Draft ML20070U7941983-02-0404 February 1983 Memorializes 830131 Telcon Resolving Open Procedural Question Re Inadvertent Use of Proprietary Data in Responding to ASLB & Wi Environ Decade Exam ML20062A7721982-07-15015 July 1982 Submits Application for Withholding Supplemental Info to WCAP-9960, Point Beach Nuclear Plant Steam Generator Sleeving Rept. Affidavit (AW-80-53) Encl ML20054M7641982-07-0707 July 1982 Memorializes 820707 Telcon.Westinghouse Will Require Until 820722 to Provide Info to Be Released Per ASLB 820526 Memorandum & Order ML20054L5151982-06-29029 June 1982 Advises That Westinghouse Will Make Info Available Per ASLB 811221 & 0526 Memoranda & Orders.Discussions on How to Accomplish Task Underway ML20054L2451982-06-28028 June 1982 Requests Withholding Per 10CFR2.790 of Supplementary Info to Steam Generator Sleeve Rept.Pages Withheld (Ref 10CFR2.790) ML20054K4961982-06-23023 June 1982 Informs That Vendor Will Not Appeal from or File Exceptions to ASLB 820517 Memorandum & Order & to Interlocutory Orders Re Vendor Proprietary Info at This Time ML20052D8061982-05-0303 May 1982 Advises That Westinghouse Will Not File Reply Brief in Response to Wi Environ Decade Brief.Svc List Encl ML20054C5791982-04-0606 April 1982 Authorizes Utilization of Affidavit AW-80-53 to Justify Withholding of Reissued Revision 1 to Point Beach Steam Generator Sleeving Rept. ML20050B8911982-03-30030 March 1982 Forwards RA Wiesemann & Ta Christopher 820329 Affidavits Re 820225 & 0323 Testimony.Svc List Encl.Related Correspondence ML20049K1001982-03-23023 March 1982 Forwards RA Wiesemann Supplemental Prefiled Testimony. Related Correspondence ML20042A8411982-03-19019 March 1982 Informs That Westinghouse Rept, Point Beach Steam Generator Sleeving Rept,WCAP-9960,Revision 1 (Proprietary),WCAP-9960, Revision 1, Was Incorrectly Marked.Entire Rept Should Be Considered Proprietary.Corrected Version to Be Sent 820322 ML20042A9481982-03-0404 March 1982 Authorizes Utilization of Affidavits AW-80-32 & AW-80-53 to Justify Withholding of Revision 1 to Point Beach Steam Generator Sleeving Rept. ML20039D7361981-12-28028 December 1981 Confirms 811221,23 & 28 Telcons Re Due Date for Westinghouse Actions Per ASLB 811221 Memorandum & Order.Due to Unavailability of Key People,Date for Westinghouse to Respond to Order Revised Until 811231 ML20039B5381981-12-17017 December 1981 Forwards Westinghouse Reply Brief in Issue of ASLB Jurisdiction to Decline to Afford Proprietary Info Protection from Public Disclosure 1990-04-04
[Table view] |
Text
. . _ - - .. .
N i f '
l l h .
l' November.20,.1987
)
i CAW-87-118'
~Dr. Thomas Murley, Director .
-Office of Nuclear Reactor Regulation
- U.S. Nuclear Regulatory Commission Washington, D.C. 20555 APPLICATION FOR WITHHOLDING PROPRIETARY INFORMATION FROM PUBLIC DISCLOSURE,
Subject:
- Point Beach Unit 2' Steam Generator Tube Fatigue Presentation
Dear Dr. Murley:
The proprietary.information for which withholding is being requested in the enclosed letter by. Wisconsin Electric. Power Company is further identified in an affidavit.
signed by the owner of the proprietary information, Westinghouse Electric Corporation.
' The affidavit, which accompanies this letter, sets forth the basis on which the-information may:be withheld from public disclosure by'the Commission and addresses with specificity the considerations listed in paragraph (b)(4) of' 10CFR Section.2.790
'of the Commission's regulations.
'Ihe. proprietary material for which withholding is being required is of the same
, technical type as that proprietary material previously submitted as Affidavit.
CAW-81-079 Accordingly, this letter authorizes the utilization of the accompanying affidavit by Wisconsin Electric Power Company.
Correspondence with respect to the proprietary aspects of the application for withholding or the Westinghouse affidavit should reference this letter, CAW-87-118, and should be addressed to the undersigned.
Ver ruly yours, ,
ck (MLitt4L Robert A. Wiesemann, Manager j Regulatory & Legislative Affairs Enclosures cc: E. C. Shomaker, Esq.
Office of the General Counsel, NRC W
s, s PROPRIETARY INFORMATION NOTICE TRANSMITTED HEREWITH ARE PROPRIETARY AND/OR NON-PROPRIETARY VERSIONS OF DOCUVENTS FURNISHED TO THE NRC IN CONNECTION WITH REQUESTS FOR GENERIC AND/OR PLANT SPECIFIC REVIEW AND APPROVAL.
IN ORDER TO CONFORM TO THE REQUIREMENTS OF 10CFR2.790 0F THE. COMMISSION'S REGULATIONS CONCERNING THE PROTECTION OF PROPRIETARY INFORMATION SO SUBMITTED TO THE NRC, THE INFORMATION WHICH IS PROPRIETARY IN THE PROPRIETARY VERSIONS IS CONTAINED WITHIN BRACKETS AND WHERE THE PROPRIETARY INFORMATION HAS BEEN DELETED IN THE NON-PROPRIETARY VERSIONS ONLY THE BRACKETS REMAIN, THE INFORMATION THAT WAS CONTAINED WITHIN THE BRACKETS IN THE PROPRIETARY VERSIONS HAVING BEEN
' DELETED. THE JUSTIFICATION FOR ~ CLAIMING THE INFORMATION SO DESIGNATED AS PROPRIETARY IS INDICATED IN BOTH VERSIONS BY MEANS OF LOWER CASE LETTERS (a)
THROUGH (g) CONTAINED.WITHIN PARENTHESES LOCATED AS A SUPERSCRIPT IMMEDIATELY FOLLOWING THE BRACKETS ENCLOSING EACH ITEM OF INFORMATION BEING IDENTIFIED AS PROPRIETARY OR~IN THE MARGIN OPPOSITE SUCH INFORMATION. THESE LOWER CASE LETTERS REFER TO THE TYPES OF INFORMATION WESTINGHOUSE CUSTOMARILY HOLM IN CONFIDENCE IDENTIFIED IN SECTIONS (4)(11)(a) THROUGH (4)(ii)(g) 0F THE AFFIDAVIT ACCOMPANYING THIS TRANSMITTAL PURSUANT TO 10CFB2.790(b)(1).
i
)
i l
l
. _ _ _ 2
CAW-81-79 AFFIDAVIT CO E NWEALTH OF PENNSYLVANIA:
ss COUNTY OF ALLEGHENY:
Before me, the undersigned authority, personally appeared Robert A. Wiesemann, who, being by me duly sworn according to law, deposes and says that he is authorized to execute this Affidavit on behalf of Westinghouse Electric Corporation (" Westinghouse") and that the everments of fact set forth in this Affidavit are true and correct to the best of his knowledge, information, and belief:
644 Robert A. Wiesemann, Manager Regulatory and Legislative Affairs ,
l Sworn to and subscribed !
before me this m day of Dm/m 1981. ;
i l [lL t?a'tb ...L/}b w W+y
- $i,hNotary].PubliE.[
- m -- - . . . - ',
ef , , .,, ,,. ,,
y,,..,.,.e.. *
, ..-;,* . -c
-2 . CAW-81-79 I
- (1) I am Manager. Regulatory and t.egislative Affairs, in the Nuclear -l 1
Technology Division, of Westinghouse Electric Corporation and as such.j! have.been specifically delegated the function of reviewing the. proprietary information sought to be withheld from public dis-closure in connection with nuclear power plant licensing or rule-
- making proceedings, and am authorized to apply for its withholding on behalf of the Westinghouse Water Reactor Divisions. J l
'(2) 'I am making this Affidavit in conformance with the provisions of 10CFR Sectior. 2.790 of the Commission's regulations and in con-junction with the Westinghouse application for withholding ac- .
companying this Affidavit.
(3) I have personal knowledge of the criteria and_ procedures utilized by Westinghouse Nuclear Energy Systems in designating information {
as a trade secret, privileged or as confidential comercial or financial infomation.
(4) Pursuanttotheprovisionsofparagraph(b)(4)ofSection2.790 of the Commission's' regulations, the following is furnished for i consideration by the Comission in detemining whether the in-formation sought to be withheld from public disclosure should be withheld.
)
.(i) The infomation sought to be withheld from public disclosure is owned and has been held in confidence by Westinghouse.
I t
1 1
1
,y,,
.. I CAW-81-79
- r 1
3 (ii)_ The infomation is of a type customarily held in confidence I
by' Westinghouse and not customarily disclosed to the public.
Westinghouse has a rational basis for determining the-types of information customarily held in confidence by it and, in
- I that. connection, utilizes a system to detemine when and l whether to hold certain types of information in confidence.
The. application of that system and the substance of that system constitutes Westinghouse policy and provides the -
rational basis required.
Under that system..information is held in confidence if it falls in~one or more of several types, the release of which .J might result in the loss of an existing or potential com- .l petitive advantage', as follows:
(a) The information reveals the distinguishing aspects of l a process (or component, structure, tool, method, etc.) i where prevention of its use by any of Westinghouse's competitors without license from Westinghouse consti-tutes a competitive economic advantage over other
. companies.
(b) It consists of supporting data, including test data, relativetoaprocess(orcomponent, structure, tool, method, etc.), the application of which data secures a competitive economic advantage, e.g., by optimization or improved marketability.
L 1
CAW-81 -79
. I i
'(c) . _Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product. , ;
(d) It reveals cost or price infomation, production cap-acities, budget levels, or comercial strategies of Westinghouse, its customers or suppliers.
(e) It reveals aspects of past, present, or future West-inghouse or customer funded development plans and pro- j grams _ of potential comercial value to Westinghouse.
(f) It contains patentable ideas, for which patent pro-tection may be desirable. !
(g) It is not the property of Westinghouse, but must be treated as proprietary by Westinghouse according to agreements with the owner.
There are sound policy reasons behind the Westinghouse system which include the following: :
(a) The use of such information by Westinghouse gives Westinghouse a competitive advantage over its com- l petitors. It is, therefore, withheld from disclosure to protect the Westinghouse competitive position.
1 L
i l
3
CAW-81-7g /
,i l
(b) It is. infonnation which is marketable in 'many ways.
The extent to which such infonnation is available to competitors diminishes the Westinghouse ability to sell products and services involving the use of the l infonnation.
i (c) Use by our competitor would put Westinghouse at a competitive disadvantage by reducing his expenditure of resources at our expense.
(d) Each' component of proprietary information pertinent to a particular competitive advantage is potentially as valuable as the total competitive advantage. If competitors acquire components of proprietary infor-mation, any one component may be the key to the entire puzzle thereby depriving Westinghouse of a competitive j advantage. l (e) Unrestricted disclosure would jeopardize the position !
of prominence of Westinghouse in the world market, and thereby give a market advantage to the competition in those countries.
(f) The Westinghouse capacity to invest corporate assets in research and development depends upon the success in obtaining and maintaining a competitive advantage.
l l
I i
S l
l
)
.. o
( ,
CAW-81-79 (iii) The information is being transmitted to the Comission in confidence and, under the provisions of 10CFR Section 2.790, it is to be received in confidence by the Comission.
(iv) The information sought to be protected is not available in public sources or available infonnation has not been pre-viously employed in the same ori.ginal manner or method to the best of our knowledge and belief.
(v) The proprietary information sought to be withheld in this submittal is that which is appropriately marked in " Steam ,
Generator Tube Plugging Margin Analysis" for the Virgil C.
Summer Nuclear Power Plant Unit No.1. WCAP-9912. Revi-sion2(Proprietary)beingtransmittedbySouthCarolina Electric and Gas Company letter Application for Withholding Proprietary Infomation from Public Disclosure. Nichols to Denton, November 1981. The proprietary information as sub-mitted for South Carolina Electric and Gas Company, Virgil C.
Sumer Nuclear Station use is expected to be applicable in-other licensee and applicant submittals in response to cer-tain NRC requirements for jus'tification of the steam generator tube plugging margin.
This infonnation is part of that which will enable Westing-house to:
(a) Provide documentation of the analyses, method and test-ing for determining plugging margin.
1 1
1
O
'. l ..a. ; . .
, CAW-81-79 (b) Establish the minimum wall thickness in compliance with l
Regulatory Guide 1.121.
l (c) Establish the stress limits versus thinning of the l remaining tube wall.
(d) Establish the maximum allowable leakage in support of !
the leak-before-break criteria. i (e) Assist the customer to obtain NRC approval. i Further this information has substantial commercial value as follows:
(a) Westinghouse plans to sell similar information to its customers for purposes of meeting NRC requirements for licensing documentation. i (b) Westinghouse can sell support and defense of the tech-nology to its customers in the licensing process.
Public disclosure of this information is likely to cause substantial harm to the competitive position of Westinghouse because it would enhance the ability of competitors to pro-
- vide similar analytical documentation and licensing defense l services for comercial power reactors without commensurate expenses. Also, public disclosure of the information would enable others to use the information to meet NRC require-ments for licensing documentation without purchasing the l right to use the information. j l !
- 3 h
i 1
. .- -_ m _ . _ _ _ . _ .___
' ~ .. ;.V.,*; >. .. . .j $ gi y l
, , / ;
J
., / )
- [ CAW-81-7g ?.
l ,
i
. .a -
i g- l The development'of the technology described in,part b;' the ,
)
informationf is the result of applying the results'of many '
years of experience in an intensive Westinghouse effort s t 1- 4 and the expenditure of a considerable sum of money. " ]
1
> s I ,4 1 O j ... l .
In order for competitors +f Westinghouse to duplicate this informati'>n, similar technical programs would hs e tp be performed and.E significant manpower effort, havisi; the i j ..t. L.7 '
requisite talent and experience, would have to be expended .s for system design software development. ' n
(
ra Further the deponent sayeth not. 4 -(,
If > ,
- s. -)
'/- te, r, b '
t.
g I'
./
j
' 't x. ;
, . ' ' \'
1 i 'ri
+
\,_
l h.
u 'I
[ 't ..
t' 9
\
l
\ a j' ' .
l l
)
)