Text

'

50-217/- 978 i'

=ii8" L

PECO NUCLEAR ramo. C-aev Nuclear Group Headquarters

.A UNIT Or PECO ENtecy 965 Chesterbrook Boulevard Wayne, PA 19087-5691 10 CFR 72.140 (d)

June 9,1998 Director Office of Nuclear Material and Safeguards U.S. Nuclear Regulatory Commission i

Washington, DC 20555

Subject:

Quality Assurance Requirements for Peach Bottom Atomic Power Station, Units 2 and 3 Independent Spent Fuel Storage Installation i

Dear Sir:

l The purpose of this letter is to inform you of our intent to apply the Quality i

Assurance Program of Peach Bottom Atomic Power Station (PBAPS), Units 2

)

l and 3, to independent Spent Fuel Storage ! installation (ISFSI) activities prior to l

first use. The PBAPS Quality Assurance Program, which satisfies the criteria of 10CFR50 Appendix B, is maintained in Appendix D of the PBAPS Updated Final Safety Analysis Report (UFSAR). The latest PBAPS UFSAR revision, including i

Appendix D, was submitted on May 8,1998 on Docket Nos. 50-277 and 50-278.

If you have any questions or require further information, please contact us.

l V ry truly yours,

} b 1

rrett D. Edwards Director-Licensing GDE: dim 0Y l

uG3n 9907160040 980609 l

[

PDR ADOCK 0S000277f' i

P PDR t,

_ _.