Forwards Insp Rept 50-333/98-02 on 980420-0531 & NOV Re Failure to Adhere to Requirements for Implementing Emergency Operating Procedures During 980501 Manual Reactor Scram
ML20236M306
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 07/02/1998
From: David Lew
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Michael Colomb
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
Shared Package
ML20236M310 List:
References
50-333-98-02, 50-333-98-2, NUDOCS 9807140016
Download: ML20236M306 (3)


See also: IR 05000333/1998002

Text

,

.

'

,

.

.

l

4

l

July 2, 1998

]

'

l

.

Mr. Michael J. Colomb

1

l

Site Executive Officer

.

New York Power Authority.

James A. FitzPatrick Nuclear Power Plant

Post Office Box 41

Lycoming, NY 13093

SUBJECT:

NRC INTEGRATED INSPECTION 50-333/98-02 AND NOTICE OF VIOLATION

Dear Mr. Colomb:

On May 31,1998, the NRC completed an inspection at your FitzPatrick Power Plant. The

enclosed report presents the results of that inspection.

.

j

During the 6-week period covered by this inspection period, performance at the James A.

,

- FitzPatrick reactor facility was mixed. We are concerned with several inadequacies in the

administration of the licensed operator requalification training program. These

1

inadequacies reduced your ability to identify potential operator performance issues and

i

. training needs during requalification examinations, and were identified as three violations of

10 CFR 50.54(i-1) and 55.59. Also, the operators failed to adhere to requirements for

' implementing emergency operating procedures during the May 1,1998 manual reactor

{

scram. This failure was a concern because of a prior similar occurrence in September

.

1996, and was identified as a violation of technical specification 6.8(A)2.

i

t

Three other violations were identified during this inspection period. Two violations concern

inadequate procedures, as required by technical specification 6.8(A)2.; The third violation

I

concerns a self-disclosing transportation event on March 17,1998, when a radioactive

material shipment exceeded package radiation limits.

These violations are cited in the enclosed Notice of Violation, and the circumstances

surrounding the violations are described in detail in the enclosed report. Please note that

you are required to respond to this letter and should follow the instructions speeMied in the

enclosed Notice when preparing your response. The NRC will use your response, in part,

to determine whether further enforcement actions is necessary to ensure compliance with

regulatory requirements.

,

i

-

9007140016 990702

pa ^** **8u

L.

L

\\

.0FFICIAL RECORD COPY-

IE:01

%

i

J

- - _ - _ - _ _ _ _ _ - _ . -__

. _ _ _ _ _

_

__ -_

-- _

_

"

<

l

Michael J. Colomb

2

l

.

j

in accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter

and its enclosures will be placed in the NRC Public Document Room (PDR).

Sincerely,

,

Original Signed by:

David C. Lew, Chief

Projects Branch 2A

Division of Reactor Projects

Docket No.: 50-333 -

License No.: DPR-59

Enclosures:

<

l-

1. Notice of Violation

2. Inspection Report 50-333/98-02

-!

'-

. cc vv/encis:

,

C. D. Rappleyea, Chairman and Chief Executive Officer

l-

E. Zeltmann, President and Chief Operating Officer

l

R. Hiney, Executive Vice President for Project Operations

(

.J. Knubel, Chief Nuclear Officer and Senior Vice President

l

H. P. Salmon, Jr., Vice President of Engineering -

_

l

W.' Josiger, Vice President - Engineering and Project Management -

J. Kelly, Director - Regulatory Affairs and Special Projects

T. Dougherty, Vice President - Nuclear Engineering

R. Deasy, Vice President - Appraisal and Compliance Services

. R. Patch, Director - Quality Assurance

' G. C. Goldstein, Assistant General Counsel

C. D. Falson, Director, Nuclear Licensing, NYPA

K. Peters, Licensing Manager

-T. Morra,' Executive Chair, Four County Nuclear Safety Committee

Supervisor, Town of Scriba

C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law

P. Eddy, Electric Divisio' , Department of Public Service, State of New York

n

G. T., Goering, Consultant, New York Power Authority

.

J. E. Gagliardo, Consultant, New York Power Authority

E. S. Beckbrd, Consultant, New York Power Authority

F. William Valentino, Pr'esident, New York State Energy Research

_

and Development Authority.

J. Spath, Program Director, New York State Energy Research ,

and Development Authority -

l

J

_ ___ _ _ _ _ - _ _ _ _ _

_ _ _ _ . _ _ _ _ _ _ _ _ _ _ _

e

Michael J. Colomb

3

Distribution w/encis:

H. Miller, RA/W. Axelson, DRA (1)

Nuclear Safety Information Center (NSIC)

PUBLIC

NRC Resident inspector

Region i Docket Room (with concurrences)

D. Lew, DRP

J. Rogge, DRP

P. Kaufman, DRP

R.Junod,DRP

Distribution w/encis: (VIA E-MAIL)

B. McCabe, RI EDO Coordinator

S. Bajwa, NRR

J. Williams, NRR

M. Campion, RI

Inspection Program Branch, NRR (IPAS)

R. Correia, NRR

F. Talbot, NRR

DOCDESK

DOCUMENT NAME: G:\\ BRANCH 2A\\FITZ9802. INS

To receive a copy of this document, indicate in the box: "C" = Copy without

attachment / enclosure

"E" = Copy with attachment / enclosure

"N" = No copy

j

OFFICE

Rl/DRP

Rl/DRP

l

,,

NAME

GHunegs Rfg

DLew

f&

DATE

07/ /- /98

07/y98

,

crFICIAL RECORD COPY

-

l

l

J

,