Forwards Power Ascension Program, Per 870903 Discussions, for Review & Approval.Program Includes Description of Logic Plan for Power Ascension,Util Assessment Points,Proposed NRC Approval Points & Startup Organization
ML20235X231
Person / Time
Site: Pilgrim
Issue date: 10/15/1987
From: Bird R
BOSTON EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
Shared Package
ML20235X235 List:
References
87-163, NUDOCS 8710190263
Download: ML20235X231 (2)


Text

-__...

?'

USMi10-D3 8 " 8""

Executive Offices 800 Boylston Street M OCT 19 A 10- l2 Boston, Massachusetts 02199 Ralph G. Bird Senior Vice President - Nuclear October 15, 1987 BECO Ltr. #87-163 l

U.

S.

Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 License No:

DRP-35 Docket No:

50-293

Subject:

Pilgrim Nuclear Power Station l

Power Ascension Program

Dear Sir:

In accordance with the discussions between Boston Edison and l

the NRC Staff on September 3,

1987, this letter transmits for l

information a description of the Power Ascension Program and l

associated Boston Edison processes for assessment of performance l

during power ascension.

The Power Ascension Program is submitted for information and review.

Three NRC approval points are sub-mitted for NRC review and approval.

1 Boston Edison has determined that the description of the Power Ascension Program and associated Boston Edison process for assessment of performance during power ascension should be expanded beyond the level of detail contemplated in the Restart Plan Volume 1,

Chapter IV and Volume 2,

Appendix 13.

Accordingly, Boston Edison will not submit Volume 2,

Appendix 13 to the NRC, but is providing an expanded description of the Power Ascension Program and associated process for management assessment as an attachment to this letter.

The Power Ascension Program includes a description of the logic plan for power ascension, Boston Edison's assessment points, the proposed NRC approval points, the startup organization and the management assessment process.

As the final phase of the Restart Plan, the Power Ascension Program is the mechanism by which Boston Edison will demonstrate the effectiveness of its programs, plans and actions to assure safe and reliable restart and continued operation.

l 8710190263 071015 h

PDR ADOCK 05000293 p

PDR l l

f-c.

i I

U.

S. Nuclear Regulatory Commission October 15, 1987 Document Control Desk Page:

2 l

Please' contact me, or R.A.

Ledgett of my staff, if you have questions or need. additional information concerning the PNPS Power Ascension Program.

L 1

I Nhi l

R.

G.

Bird

\\

i Attachment cc:

U.S.N.R.C.

- Region I 631 Park Avenue King of Prussia, PA 19406 William T. Russell, Regional Administrator U.

S.

Nuclear Regulatory Commission - Region I 631 Park Avenue King of Prussia, PA 19406 R. H. Wessman, Project Manager Division of Reactor Projects I/II office of Nuclear Reactor Regulation U.

S.

Nuclear Regulatory Commission 7920 Norfolk Ave.

Bethesda, MD 20814 Senior NRC Resident Inspector Pilgrim Nuclear Power Station

_