Conference Plan (Oct 20 Prehearing Conference Rescheduled).* Conference Rescheduled for 871116 & 17.Areas for Discussion Listed.Served on 871014
ML20235W198
Person / Time
Site: Comanche Peak  
Issue date: 10/13/1987
From: Bloch P
Atomic Safety and Licensing Board Panel
To:
References
CON-#487-4603 79-430-06OL, 79-430-6OL, OL-2, NUDOCS 8710160051
Download: ML20235W198 (2)


Text

_

fhh )

i 20L KE TEC' U%RC l

UNITED STATES OF AMERICA 17 OCT 14 M2'44 NUCLEAR REGULATORY COMMISSION

)

l

\\

Before Administrative Judges:

(FFILE Jr inr.U A.O I

Peter B. Bloch, Chair MCKEitNG & CERVlfi "A"H Dr. Walter H. Jordan Dr. Kenneth A. McCollom 4

SERVED OCT 1 4 1987 In the Matter of

]

Docket Nos. 50-445-OL2

]

50-446-OL2 Texas Utilities Electric Co.,

at al_ ]

]

ASLBP No. i9-430-060L

]

(Comanche Peak Steam Electric Station,]

October 13, 1987 Units 1 and 2)

]

]

]

CONFCRENCE PLAN (October 20 Prehearins Conference Rescheduled)

The October 20, 1987, prehearing conference, will be rescheduled, at the request of the parties.

The new times are November 16 from 1 pm until 6:30 pm and November 17 from 8:30 am until 12 noon.

Arrangements are still being made and will be announced in the federal register, The Board still expects the parties to discuss, among other things:

What documents do Applicants rely on to establish the adequacy of design and construction?

Whether or not the Board must make factual deter-minations about the extent of the historical breakdown in QA/QC for design and construction.

Discuss the " holding" j

of cases cited as precedent in detail, including the significance of the factual setting.

Should there be a finding of historical inadequacy (breakdown) of QA/QC for design or construction, would Applicants have to show that their "get well' program achieved the same degree of safety as would have been achieved pursuant to adequate initial implementation of Appendix B7 Complete and thoughtful answers to these questions, accompa-nied by a proposed detailed format for the prehearing conference, should be in the hande of the parties and the Board by no later than October 30.

Replies, limited to new arguments that have not previ-ously been made, shall be in the hands of the parties and the Board by no later than November 10.

However, Dr. McCollom will arrive on November 12 at the Atlanta Airport Marriott, 4711 Best Road, College b

8710160051 871013 hb PDR ADOCK 05000445 O

PDR

l 4

l

I Park, Georgia 30337.

Service to him may be made by mailing the response to him on or before November 16 at this address, j

FOR THEgOMICSAFETYANDLICENSINGBOARD:

C Peter B.

Bloch, Chair i

Administrative Judge l'

Bethesda, Maryland 4

_ _ - _ _. _ - _ _ _ _