Responds to Violations Noted in Insp Rept 50-267/87-02. Corrective Actions:Programmatic Procedure Will Be Written Re Plant Nuclear Matl Control Sys & Training Requirements Will Be Either Included or Referred to in Procedure
ML20235U107
Person / Time
Site: Fort Saint Vrain 
Issue date: 10/05/1987
From: Robert Williams
PUBLIC SERVICE CO. OF COLORADO
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
P-87352, NUDOCS 8710130363
Download: ML20235U107 (2)


Text

,

9 5,_

Oeubiicservice-

===. -

16805 WCR 19 1/2, Platteville, Colorado 80651 1

l October 5, 1987 Fort St. Vrain i

Unit No. 1 P-87352 I

U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Docket No. 50-267 I

I

SUBJECT:

RESPONSE TO IE INSPECTION NOTICE 87-02 (G-87039)

I

Dear Sirs:

The following is a response to observations and recommendations made during your January, 1987, Material Control and Accounting audit.

ITEM 1: A programmatic type procedure will be written covering the l

Fort St. Vrain nuclear material control system.

This procedure will refer to existing implementing procedures as described by ANSI N15.8.

ITEM 2: Training requirements will be either included or referred to in the programmatic procedure.

ITEM 3: A nuclear material internal control system description will be either included or referred to in the programmatic procedure.

ITEM 4: A Health Physics sealed source inventory procedure will be referenced by the programmatic procedure cod will be performed concurrent with other inventories.. A commitment to promptly report the results of sealed source inventories to the Nuclear Materials Manager will be included in.the appropriate procedures as well as proper inventory 1

documentation.

The inventory schedule will be changed from

)

bimonthly to quarterly, as suggested.

1 df 8710130363 871005 PDR ADOCK 05000267 i

G PDR /

' O g

.d P-87352 October 5, 1987 1

ITEM 5: All procedures requiring the application or destruction of tamper-indicating seals for the control of nuclear material will be revised as necessary to include the requirement that l

persons who apply or destroy such seals initial the i

associated documentation.

ITEM 6: QA auditing procedures will be referenced by the l

programmatic procedure.

ITEM 7: All identified 741 and 742 form discrepancies will be corrected by October 30, 1987.

]

If you have any questions concerning this matter, please contact l

Mr. M. H. Holmes at (303) 480-6960.

Sincerely, R. O. Williams, Jr.

l Vice President Nuclear Operations l

1 R0W:MGB:djm cc:

Regional Administrator, Region IV ATTN:

Mr. J. E. Gagliardo, Chief Reactor Projects Branch Mr. RtSert Farrell Senior Resident Inspector Fort St. Vrain l