Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217M8851999-10-0808 October 1999 Informs of Staff Determination That Listed Calculations Should Be Withheld from Public Disclosure,Per 10CFR2.790, as Requested in 990909 Affidavit ML20211J7731999-08-31031 August 1999 Forwards Insp Rept 50-312/99-03 on 990802-06.No Violations Noted.Insp Included Decommissioning & Dismantlement Activities,Verification of Compliance with Selected TS & Review of Completed SEs ML20211H7481999-08-13013 August 1999 Forwards Amend 126 to License DPR-54 & Safety Evaluation. Amend Changes Permanently Defueled Technical Specification (PDTS) D3/4.1, Spent Fuel Pool Level, to Replace Specific Reference to SFP Level Alarm Switches with Generic Ref 3F0799-22, Provides Update & Rev to Submittal Made by Util Ltr with Regard to EAL Classification Methodology for Unit 3.Reponses to NRC Staff Questions Provided as Attachment D to Ltr & Reflects Discussions Held1999-07-13013 July 1999 Provides Update & Rev to Submittal Made by Util Ltr with Regard to EAL Classification Methodology for Unit 3.Reponses to NRC Staff Questions Provided as Attachment D to Ltr & Reflects Discussions Held ML20210H9541999-07-0707 July 1999 Informs NRC of Change to Rancho Seco Decommissioning Schedule,As Described in Licensee Post Shutdown Decommissioning Activities Rept ML20209D2501999-06-24024 June 1999 Informs That Util Has Revised All Sections of Rancho Seco Emergency Plan (Rsep),Change 4,effective 990624 ML20196G0431999-06-22022 June 1999 Forwards Certified Copies of Listed Nuclear Liability Endorsements for Smud Rancho Seco Nuclear Generating Station ML20195D1851999-05-27027 May 1999 Forwards Rancho Seco Annual Rept, IAW Plant Permanently Defueled TS D6.9.4 & D6.9.6b.Rept Contains Shutdown Statistics,Narrative Summary of Shutdown Experience,Er Info & Tabulation of Facility Changes,Tests & Experiments ML20195B8511999-05-27027 May 1999 Forwards Change 4 to Rancho Seco Emergency Plan, Incorporating Commitments Made to NRC as Outlined in NRC .Emergency Plan Includes Two Listed Supporting Documents ML20207E9181999-05-27027 May 1999 Informs That Effective 990328,NRR Underwent Reorganization. within Framework of Reorganization,Div of Licensing Project Mgt Created.Reorganization Chart Encl ML20206U7411999-05-18018 May 1999 Provides Summary of 990217-18 Visit to Rancho Seco Facility to Become Familar with Facility,Including Onsite ISFSI & Meeting with Representatives of Smud to Discuss Issues Re Revised Rancho Seco Ep,Submitted to NRC on 960429 ML20206M1611999-05-10010 May 1999 Forwards Listed Proprietary Calculations to Support Review of Rancho Seco ISFSI Sar.Proprietary Encls Withheld ML20206E8591999-04-12012 April 1999 Provides Info Re High Total Coliform Result in Plant Domestic Sewage Effluent Prior to Confluence with Combined Effluent.Cause of High Total Coliform Result Was Broken Flow Rate Instrument.Instrument Was Repaired on 990318 ML20204H6751999-03-19019 March 1999 Forwards Insp Rept 50-312/99-02 on 990309-11.No Violations Noted.Portions of Physical Security & Access Authorization Programs Were Inspected ML20204E4031999-03-16016 March 1999 Submits Rept of Status of Decommissioning Funding for Rancho Seco,As Required by 10CFR50.75(f)(1).Plant Is Currently in Safstor, with Operating License Scheduled to Expire in Oct 2008 ML20204E6661999-03-11011 March 1999 Forwards Rancho Seco Exposure Rept for Individuals That Received Greater than 100 Mrem During 1998,IAW TS D6.9.2.2 & NRC Regulatory Guide 1.16 ML20204E6441999-03-11011 March 1999 Forwards Individual Monitoring Repts for Personnel That Required Radiation Exposure Monitoring During 1998 ML20207L1711999-03-10010 March 1999 Informs of Staff Determination That Supporting Calculations & Drawings Contained in Rev 2 of Sar, Should Be Withheld from Public Disclosure,Per 10CFR2.790 NL-99-002, Submits Info About Property Insurance for Rancho Seco Nuclear Generating Station,Iaw 10CFR50.54(w)(3)1999-03-10010 March 1999 Submits Info About Property Insurance for Rancho Seco Nuclear Generating Station,Iaw 10CFR50.54(w)(3) ML20207D4431999-03-0101 March 1999 Forwards Annual Radioactive Effluent Release Rept, for Rancho Seco Nuclear Generating Station for 1998 ML20207H6181999-02-18018 February 1999 Provides Attached Metrix & Two Copies of Rancho Seco ISFSI Sar,Rev 2 on Compact Disc,As Requested in 990209 Meeting. First Rounds of RAIs Dealt Primarily with Use of Cask as Storage Cask.Without Compact Disc ML20203D0761999-02-10010 February 1999 Ltr Contract:Task Order 37 Entitled, Technical Assistance in Review of New Safety Analysis Rept for Rancho Seco Spent Fuel Storage Facility, Under Contract NRC-02-95-003 ML20155D4431998-10-27027 October 1998 Forwards Amend 3 to Rancho Seco Dsar,Representing Updated Licensing Basis for Operation of Permanently Shutdown & Defueled Rancho Seco Nuclear Facility During Permanently Defueled Mode.With Instructions & List of Effective Pages NL-98-032, Forwards Certified Copies of Listed Nuclear Liability Endorsements for Util1998-09-30030 September 1998 Forwards Certified Copies of Listed Nuclear Liability Endorsements for Util ML20237A6031998-08-0707 August 1998 Forwards Insp Rept 50-312/98-03 on 980706-09.No Violations Noted ML20237A9481998-08-0303 August 1998 Forwards Smud 1997 Annual Rept, IAW 10CFR50.71(b),which Includes Certified Financial Statements ML20236Q9461998-07-15015 July 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-312/98-02 ML20236J6331998-06-30030 June 1998 Forwards Response to Violations Noted in Insp Rept 50-312/98-02.Corrective Actions:Util Revised RSAP-1003 to Clarify District Security Staff Responsibilities Re Handling & Review of Criminal History Info ML20236E8211998-06-0303 June 1998 Forwards Insp Rept 50-312/98-02 on 980519-21 & NOV Re Failure to Review & Consider All Info Obtained During Background Investigation.Areas Examined During Insp Also Included Portions of Physical Security Program ML20217G8391998-04-20020 April 1998 Forwards Copy of Rancho Seco Monthly Discharger Self-Monitoring Rept for Mar 1998 IR 05000312/19980011998-03-25025 March 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-312/98-01 on 980205 ML20217F1891998-03-18018 March 1998 Forwards Signed Original & Amend 7 to Rancho Seco Long Term Defueled Condition Physical Security Plan & Rev 4 to Long Term Defueled Condition Training & Qualification Plan.Encls Withheld,Per 10CFR2.790 ML20217G6661998-03-18018 March 1998 Forwards Discharge Self Monitoring Rept for Feb 1998, Which Makes Note of One Wastewater Discharge Permit Violation ML20217H0451998-03-18018 March 1998 Submits Rancho Seco Exposure Rept for Individuals Receiving Greater than 100 Mrem During 1997,per TS D6.9.2.2 & Guidance Contained in Reg Guide 1.16.No One Exposed to Greater than 100 Mrem in 1997 ML20216K1091998-03-11011 March 1998 Forwards NRC Form 5 Individual Monitoring Repts for Personnel Who Required Radiation Exposure Monitoring,Per 10CFR20.1502 During 1997.W/o Encl ML20217N9531998-03-0505 March 1998 Responds to Violations Noted in Insp Rept 50-312/98-01. Corrective Actions:Radiation Protection Group Wrote Potential Deviation from Quality (Pdq) 97-0082 & Assigned Radiation Protection Action to Determine Cause & CAs ML20203H7001998-02-25025 February 1998 Forwards Annual Radioactive Effluent Release Rept for Jan- Dec 1997, IAW 10CFR50.36a(a)(2) & TS D6.9.3.Revs to Radiological Environ Monitoring Manual & off-site Dose Calculation Manual,Encl ML20202G0131998-02-12012 February 1998 Forwards Certified Copies of Listed Nuclear Liability Endorsements & Master Worker Policy Certificate of Insurace for Facility NL-98-006, Submits Annual Rept of Property Insurance Levels for Rsngs, IAW 10CFR50.54(w)(3)1998-02-12012 February 1998 Submits Annual Rept of Property Insurance Levels for Rsngs, IAW 10CFR50.54(w)(3) ML20202C4641998-02-0505 February 1998 Forwards Insp Rept 50-312/98-01 on 980105-08 & Notice of Violation.Insp Included Decommissioning & Dismantlement Work Underway,Verification of Compliance W/Selected TS & Main & Surveillance Activities Associated W/Sfp ML20199A5881997-11-10010 November 1997 Responds to NRC Re Violations Noted in Insp Rept 50-312/97-01.Corrective Actions:Reviewed SFP Water Temp & Instrument Calibr Records,Generated Otr 97-001 to Document out-of-tolerance Instrument & Generated Pdq 97-0064 ML20198R9501997-11-0505 November 1997 Requests Interpretation of or Rev to NUREG-1536, Std Review Plan for Dry Cask Storage Sys, Re Compliance W/ 10CFR72.236(e) & 10CFR72.122(h)(4) for Dry Fuel Storage Casks ML20198K5391997-10-21021 October 1997 Forwards Insp Rept 50-312/97-04 on 970922-25 & Notice of Violation.Response Required & Will Be Used to Determine If Further Action Will Be Necessary ML20217D3101997-09-25025 September 1997 Forwards Update of 1995 Decommissioning Evaluation, for Rancho Seco Nuclear Generation Station & Annual Review of Nuclear Decommissioning Trust Fund for Adequacy Re Assumptions for Inflation & Rate of Return ML20211F0991997-09-23023 September 1997 Forwards One Certified Copy of Mutual Atomic Energy Liability Underwriters Nuclear Energy Liability Insurance Endorsement 120 for Policy MF-0075 for Smud Rancho Seco Nuclear Facility ML20198G8141997-08-22022 August 1997 Forwards Amend 125 to License DPR-54 & Safety Evaluation. Amend Permits Smud to Change TS to Incorporate Revised 10CFR20.Amend Also Revises References from NRC Region V to NRC Region IV ML20151L0281997-07-29029 July 1997 Provides Response to NRC Request for Addl Info Re TS Change,Relocating Administrative Controls Related to QA to Ufsar,Per NUREG-0737 ML20149E5031997-07-10010 July 1997 Second Partial Response to FOIA Request for Documents. Forwards Records Listed in App C Being Made Available in Pdr.Records in App D Already Available in PDR ML20148P5161997-06-30030 June 1997 Second Partial Response to FOIA Request for Documents.App B Records Being Made Available in PDR ML20141A1721997-06-17017 June 1997 Forwards Insp Rept 50-312/97-03 on 970603-05.No Violations Noted.Areas Examined During Insp Included Portions of Physical Security Program 1999-08-31
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEAR3F0799-22, Provides Update & Rev to Submittal Made by Util Ltr with Regard to EAL Classification Methodology for Unit 3.Reponses to NRC Staff Questions Provided as Attachment D to Ltr & Reflects Discussions Held1999-07-13013 July 1999 Provides Update & Rev to Submittal Made by Util Ltr with Regard to EAL Classification Methodology for Unit 3.Reponses to NRC Staff Questions Provided as Attachment D to Ltr & Reflects Discussions Held ML20210H9541999-07-0707 July 1999 Informs NRC of Change to Rancho Seco Decommissioning Schedule,As Described in Licensee Post Shutdown Decommissioning Activities Rept ML20209D2501999-06-24024 June 1999 Informs That Util Has Revised All Sections of Rancho Seco Emergency Plan (Rsep),Change 4,effective 990624 ML20196G0431999-06-22022 June 1999 Forwards Certified Copies of Listed Nuclear Liability Endorsements for Smud Rancho Seco Nuclear Generating Station ML20195B8511999-05-27027 May 1999 Forwards Change 4 to Rancho Seco Emergency Plan, Incorporating Commitments Made to NRC as Outlined in NRC .Emergency Plan Includes Two Listed Supporting Documents ML20195D1851999-05-27027 May 1999 Forwards Rancho Seco Annual Rept, IAW Plant Permanently Defueled TS D6.9.4 & D6.9.6b.Rept Contains Shutdown Statistics,Narrative Summary of Shutdown Experience,Er Info & Tabulation of Facility Changes,Tests & Experiments ML20206M1611999-05-10010 May 1999 Forwards Listed Proprietary Calculations to Support Review of Rancho Seco ISFSI Sar.Proprietary Encls Withheld ML20206E8591999-04-12012 April 1999 Provides Info Re High Total Coliform Result in Plant Domestic Sewage Effluent Prior to Confluence with Combined Effluent.Cause of High Total Coliform Result Was Broken Flow Rate Instrument.Instrument Was Repaired on 990318 ML20204E4031999-03-16016 March 1999 Submits Rept of Status of Decommissioning Funding for Rancho Seco,As Required by 10CFR50.75(f)(1).Plant Is Currently in Safstor, with Operating License Scheduled to Expire in Oct 2008 ML20204E6441999-03-11011 March 1999 Forwards Individual Monitoring Repts for Personnel That Required Radiation Exposure Monitoring During 1998 ML20204E6661999-03-11011 March 1999 Forwards Rancho Seco Exposure Rept for Individuals That Received Greater than 100 Mrem During 1998,IAW TS D6.9.2.2 & NRC Regulatory Guide 1.16 NL-99-002, Submits Info About Property Insurance for Rancho Seco Nuclear Generating Station,Iaw 10CFR50.54(w)(3)1999-03-10010 March 1999 Submits Info About Property Insurance for Rancho Seco Nuclear Generating Station,Iaw 10CFR50.54(w)(3) ML20207D4431999-03-0101 March 1999 Forwards Annual Radioactive Effluent Release Rept, for Rancho Seco Nuclear Generating Station for 1998 ML20207H6181999-02-18018 February 1999 Provides Attached Metrix & Two Copies of Rancho Seco ISFSI Sar,Rev 2 on Compact Disc,As Requested in 990209 Meeting. First Rounds of RAIs Dealt Primarily with Use of Cask as Storage Cask.Without Compact Disc ML20155D4431998-10-27027 October 1998 Forwards Amend 3 to Rancho Seco Dsar,Representing Updated Licensing Basis for Operation of Permanently Shutdown & Defueled Rancho Seco Nuclear Facility During Permanently Defueled Mode.With Instructions & List of Effective Pages NL-98-032, Forwards Certified Copies of Listed Nuclear Liability Endorsements for Util1998-09-30030 September 1998 Forwards Certified Copies of Listed Nuclear Liability Endorsements for Util ML20237A9481998-08-0303 August 1998 Forwards Smud 1997 Annual Rept, IAW 10CFR50.71(b),which Includes Certified Financial Statements ML20236J6331998-06-30030 June 1998 Forwards Response to Violations Noted in Insp Rept 50-312/98-02.Corrective Actions:Util Revised RSAP-1003 to Clarify District Security Staff Responsibilities Re Handling & Review of Criminal History Info ML20217G8391998-04-20020 April 1998 Forwards Copy of Rancho Seco Monthly Discharger Self-Monitoring Rept for Mar 1998 ML20217H0451998-03-18018 March 1998 Submits Rancho Seco Exposure Rept for Individuals Receiving Greater than 100 Mrem During 1997,per TS D6.9.2.2 & Guidance Contained in Reg Guide 1.16.No One Exposed to Greater than 100 Mrem in 1997 ML20217F1891998-03-18018 March 1998 Forwards Signed Original & Amend 7 to Rancho Seco Long Term Defueled Condition Physical Security Plan & Rev 4 to Long Term Defueled Condition Training & Qualification Plan.Encls Withheld,Per 10CFR2.790 ML20217G6661998-03-18018 March 1998 Forwards Discharge Self Monitoring Rept for Feb 1998, Which Makes Note of One Wastewater Discharge Permit Violation ML20216K1091998-03-11011 March 1998 Forwards NRC Form 5 Individual Monitoring Repts for Personnel Who Required Radiation Exposure Monitoring,Per 10CFR20.1502 During 1997.W/o Encl ML20217N9531998-03-0505 March 1998 Responds to Violations Noted in Insp Rept 50-312/98-01. Corrective Actions:Radiation Protection Group Wrote Potential Deviation from Quality (Pdq) 97-0082 & Assigned Radiation Protection Action to Determine Cause & CAs ML20203H7001998-02-25025 February 1998 Forwards Annual Radioactive Effluent Release Rept for Jan- Dec 1997, IAW 10CFR50.36a(a)(2) & TS D6.9.3.Revs to Radiological Environ Monitoring Manual & off-site Dose Calculation Manual,Encl NL-98-006, Submits Annual Rept of Property Insurance Levels for Rsngs, IAW 10CFR50.54(w)(3)1998-02-12012 February 1998 Submits Annual Rept of Property Insurance Levels for Rsngs, IAW 10CFR50.54(w)(3) ML20202G0131998-02-12012 February 1998 Forwards Certified Copies of Listed Nuclear Liability Endorsements & Master Worker Policy Certificate of Insurace for Facility ML20199A5881997-11-10010 November 1997 Responds to NRC Re Violations Noted in Insp Rept 50-312/97-01.Corrective Actions:Reviewed SFP Water Temp & Instrument Calibr Records,Generated Otr 97-001 to Document out-of-tolerance Instrument & Generated Pdq 97-0064 ML20198R9501997-11-0505 November 1997 Requests Interpretation of or Rev to NUREG-1536, Std Review Plan for Dry Cask Storage Sys, Re Compliance W/ 10CFR72.236(e) & 10CFR72.122(h)(4) for Dry Fuel Storage Casks ML20217D3101997-09-25025 September 1997 Forwards Update of 1995 Decommissioning Evaluation, for Rancho Seco Nuclear Generation Station & Annual Review of Nuclear Decommissioning Trust Fund for Adequacy Re Assumptions for Inflation & Rate of Return ML20211F0991997-09-23023 September 1997 Forwards One Certified Copy of Mutual Atomic Energy Liability Underwriters Nuclear Energy Liability Insurance Endorsement 120 for Policy MF-0075 for Smud Rancho Seco Nuclear Facility ML20151L0281997-07-29029 July 1997 Provides Response to NRC Request for Addl Info Re TS Change,Relocating Administrative Controls Related to QA to Ufsar,Per NUREG-0737 NL-97-030, Forwards Endorsement 132 to Nelia Policy NF-0212 & Endorsement 118 to Maelu Policy MF-0075 for Smuds Rsngs1997-05-13013 May 1997 Forwards Endorsement 132 to Nelia Policy NF-0212 & Endorsement 118 to Maelu Policy MF-0075 for Smuds Rsngs ML20138F5321997-04-28028 April 1997 Forwards Response to RAI Re License Amend 192,updating Cask Drop Design Basis Analysis,Per NRC 960510 Request for Addl Info on 960318 Application NL-97-027, Forwards Certified Copies of Listed Nuclear Liability Endorsements for Utility1997-04-17017 April 1997 Forwards Certified Copies of Listed Nuclear Liability Endorsements for Utility ML20137W8091997-03-20020 March 1997 Forwards Biennial Update to Rancho Seco Post-Shutdown Decommissioning Activities Rept ML20137S3571997-03-19019 March 1997 Provides Notification of Use of Revised Quality Manual for Activities Re Rancho Seco ISFSI ML20137D0981997-03-18018 March 1997 Submits Rancho Seco Exposure Rept for Individuals Receiving Greater than 100 Mrem During 1996.Provided IAW TS D6.9.2.2 & Guidance Contained in NRC Reg Guide 1.16.No One Exposed to Greater than 100 Mrem in 1996 ML20137D1221997-03-18018 March 1997 Submits,Iaw 10CFR20.2206 & TS D6.9.2.1,1996 NRC Form 5 Individual Monitoring Repts for Personnel Requiring Radiation Exposure Monitoring Per 10CFR20.1502 During 1996. W/O Encl NL-97-012, Submits Rept of Listed Current Levels of Property Insurance for Plant,Iaw 10CFR50.54(w)(3)1997-02-11011 February 1997 Submits Rept of Listed Current Levels of Property Insurance for Plant,Iaw 10CFR50.54(w)(3) ML20138L1091997-01-29029 January 1997 Informs of Schedule Change Re Decommissioning of Rancho Seco.Incremental Decommissioning Action Plan,Encl NL-97-005, Forwards Certified Copies of Listed Nuclear Liability Endorsements for Utility1997-01-22022 January 1997 Forwards Certified Copies of Listed Nuclear Liability Endorsements for Utility NL-96-056, Forwards Certified Copies of Listed Nuclear Liability Endorsements for Util1996-12-16016 December 1996 Forwards Certified Copies of Listed Nuclear Liability Endorsements for Util ML20134E0041996-10-23023 October 1996 Forwards Response to NRC GL 96-04, Boraflex Degradation in Spent Fuel Pool Storage Racks ML18102B6871996-08-0606 August 1996 Informs That Util Will Revise Loading & Unloading Procedures & Operator Training as Necessary ML20149E4491994-05-16016 May 1994 Forwards 1993 Annual Rept of Sacramento Municipal Utility District,For Info ML20149E3971994-05-10010 May 1994 Forwards Re Updated Decommissioning Cost Estimate for Rancho Seco & Attached Rept by Tlg Engineering,Inc. W/Svc List ML20059H6731994-01-20020 January 1994 Forwards Revised Rancho Seco Quality Manual, Reflecting Current Rancho Seco Pol Phase Nuclear Organization Changes ML20059E1221994-01-0303 January 1994 Forwards Amend 7 to Long Term Defueled Condition Physical Security Plan.Encl Withheld (Ref 10CFR73) ML20059C1681993-12-22022 December 1993 Forwards Suppl Info to Support Review & Approval of 930514 Proposed License Amend 186 Re Nuclear Organization Changes, Per NRC Request 1999-07-07
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059L5431990-09-20020 September 1990 Requests Exemptions from Certain Requirements of 10CFR50.47(b) & 50,App E & Proposes New Emergency Plan That Specifically Applies to Long Term Defueled Condition ML20059J9161990-09-13013 September 1990 Notification of Change in Operator/Senior Operator Status for R Groehler,Effective 900907 ML20059J9221990-09-13013 September 1990 Responds to Generic Ltr 90-03, Relaxation of Staff Position in Generic Ltr 83-28,Item 2.2,Part 2, 'Vendor Interface for Safety-Related Components.' No Vendor Interface Exists for Spent Fuel Pool Liner NL-90-442, Forwards Endorsements 13 to Nelia Certificate N-49 & Maelu Certificate M-49,Endorsements 91 & 92 to Maelu Policy MF-75 & Endorsements 103 & 104 to Nelia Policy NF-2121990-09-12012 September 1990 Forwards Endorsements 13 to Nelia Certificate N-49 & Maelu Certificate M-49,Endorsements 91 & 92 to Maelu Policy MF-75 & Endorsements 103 & 104 to Nelia Policy NF-212 ML20059G0791990-09-0606 September 1990 Forwards Supplemental Fitness for Duty Performance Data, Omitted from 900725 Rept Re Random Drug Testing Results ML20059E0031990-08-30030 August 1990 Forwards Semiannual Radioactive Effluent Release Rept,Jan- June 1990, Corrected Repts & Revs to ODCM ML20059C2491990-08-27027 August 1990 Advises That M Foster & B Rausch Leaving Util Effective on 900810 & 17,respectively & Will No Longer Require Active Operator Licenses ML20056B2591990-08-20020 August 1990 Forwards Long-Term Defueled Condition Security Training & Qualification Plan. Encl Withheld (Ref 10CFR2.790) ML20056B2961990-08-10010 August 1990 Discusses 900731 Meeting Re Future of Util & Closure & Decommissioning of Facility.Request for Possession Only License Pending Before Commission ML20058Q2811990-08-0909 August 1990 Forwards Updated Listing of Commitments & long-range Scope List Items Deferred or Closed by Commitment Mgt Review Group Since Last Update ML20058N0911990-08-0707 August 1990 Notifies of Minor Change in List of Tech Specs Applicable in Plant Defueled Condition.Determined That Surveillance Requirements Table 4.1-1,Item 63 Not Required to Be Included in List of Tech Specs Applicable in Defueled Condition ML20056A1131990-07-30030 July 1990 Apprises of Status of Plans to Use 3 of 4 Emergency Diesel Generators as Peaking Power Supplies & Responds to Questions in .Util Obtained Authorization for Operation of Diesel Generators for No More than 90 Days Per Yr ML20056A2041990-07-30030 July 1990 Provides Response to NRC Bulletin 90-001, Loss of Fill Oil in Transmitters Mfg by Rosemount. Pressure & Differential Pressure Transmitters 1153 & 1154 Do Not Perform Any safety-related Function in Current Plant Mode ML20055J0311990-07-25025 July 1990 Forwards fitness-for-duty Performance Data for Facility from 900103-0630 ML20055J0331990-07-25025 July 1990 Notifies of Change in Operator/Senior Operator Status. Operators Terminating Employment & No Longer Require License ML20055H8081990-07-24024 July 1990 Forwards Decommissioning Financial Plan for Plant,Per 10CFR50.33(k)(2) & Requests Interim Exemption Re Requirement to Have Full Decommissioning Funding at Time of Termination of Operation,Per 10CFR50.12 ML20055H7561990-07-24024 July 1990 Requests Exemption from Performing Annual Exercise of Emergency Plan,Activation of Alert & Notification Sys & Distribution of Public Info Brochures,Per 10CFR50.12 Requirements ML20055F8421990-07-13013 July 1990 Forwards Application for Proposed Decommissioning of Plant. Util Needs Relief from Equipment Maint,Surveillance,Staffing & Other Requirements Not Necessary to Protect Public Health & Safety During Defueled Condition ML20055G9821990-07-12012 July 1990 Advises That Environ Exposure Controls Action Plan Will Be Provided by Sept 1990,per Insp Rept 50-312/90-02 ML20055E5111990-07-0606 July 1990 Notifies of Change in Operator/Senior Operator Status for D Rosenbaum & M Cooper,Effective 900622 & 29,respectively ML20055C3541990-02-14014 February 1990 Forwards Updated Response to Insp Rept 50-312/88-30. Calculations for Liquid Effluent Monitors Completed & in Use & Rev to Reg Guide 4.15 in Procedure RSAP-1702 Scheduled to Be Completed & Implemented by Apr 1990 ML20055C3511990-02-14014 February 1990 Forwards Addl Info Re 900306 Response to NRC Bulletin 88-003, Inadequate Latch Engagement in Hfa Type Latching Relays Mfg by Ge. Util Will Replace Only Relays Found Not to Meet Insp Criteria ML20248H2571989-10-0606 October 1989 Responds to NRC Re Addendum to Safety Evaluation Supporting Amend 92 to License DPR-54 Re Reactor Vessel Vent Valve Testing.No Testing of Reactor Vessel Vent Valves Will Be Performed ML20248H2391989-10-0606 October 1989 Requests Exemption from Requirements of 10CFR26 Re Fitness for Duty Programs Based on Present & Future Operational Configuration ML20248A8271989-09-25025 September 1989 Requests Permission to Submit Next Amend to Updated FSAR W/Decommissioning Plan Submittal.Extension Will Allow District to Incorporate Plant Closure Status in SAR Update to Reflect Plant Conditions Accurately ML20248D4611989-09-13013 September 1989 Responds to 890906 Request for Assessment of Util Compliance W/Ol & Associated Programs & Commitments,Per 10CFR50.54(f). Staffing Requirements for Emergency Preparedness Will Not Be Violated & Future Shortfalls Will Be Remedied ML20247G1991989-09-11011 September 1989 Requests Extension for Time Period Equivalent to That of Current Shutdown.Extension Would Result in Revised Final Expiration Date of Not Earlier than 900318.Plant Would Not Be Brought Above Cold Shutdown W/O NRC Prior Concurrence ML20247H3551989-09-0707 September 1989 Informs That Util Stands by Commitments of 890621 & 0829 Re Implementation of Closure Plan in Safe & Deliberate Manner in Compliance W/License & W/All Applicable Laws & Regulations ML20247H5541989-09-0101 September 1989 Responds to Violations Noted in Insp Rept 50-312/89-14. Corrective Actions:Stop Order on Fuel Movement Issued & Action Plan Generated on 890908 to Address Broader Issues 05000312/LER-1988-010, Forwards Rev 1 to LER 88-010,due to Change in Commitment Date for re-evaluating Fire Zones.Date Changed to 901001. Zones re-evaluated in Conjunction W/Mods to Fire Detection Annunciator Sys1989-08-23023 August 1989 Forwards Rev 1 to LER 88-010,due to Change in Commitment Date for re-evaluating Fire Zones.Date Changed to 901001. Zones re-evaluated in Conjunction W/Mods to Fire Detection Annunciator Sys ML20246A4011989-08-16016 August 1989 Forwards Rev 5 to Inservice Testing Program Plan. Changes Identified Consistent W/Guidance Provided by Generic Ltr 89-04 NL-89-593, Forwards Plant Closure Organizational Charts & Administrative Procedure RSAP-0101,per 890802 Request1989-08-15015 August 1989 Forwards Plant Closure Organizational Charts & Administrative Procedure RSAP-0101,per 890802 Request ML20245H4781989-08-10010 August 1989 Requests Exemption from Generic Ltr 89-07, Power Reactor Safeguards Contingency Planning for Surface Vehicle Bombs Because on 890607,util Board of Directors Ordered That Plant Cease Operation ML20245H1781989-08-0909 August 1989 Notifies of Change in Operator/Senior Operator Status. J Dailey & J Reynolds Terminated Employment on 890721 & 890802,respectively ML20245L1831989-08-0808 August 1989 Informs That Official Correspondence Must Be Directed to Listed Individuals Due to Reorganization of Util Following 890606 Election ML20247L9221989-07-26026 July 1989 Provides Revised Response to NRC Re Violations Noted in Insp Rept 50-312/88-33.Corrective Action:Portable Shield Walls Inspected Every 6 Months to Ensure All Safety Factors Met & Area Surveys Conducted on Weekly Basis ML20247M4121989-07-24024 July 1989 Requests Exemption from 10CFR50,App E,Section IV.F.2 to Allow Util Not to Perform Annual Emergency Plan Exercise for 1989.Request Results from Transitional Mode of Plant from Operating Plant to Plant Preparing for Decommissioning NL-89-541, Requests That Completion Date for Addl Training of Personnel Involved in Performing Work on Environ Qualified Equipment Be Extended from 890616 to 8912151989-07-14014 July 1989 Requests That Completion Date for Addl Training of Personnel Involved in Performing Work on Environ Qualified Equipment Be Extended from 890616 to 891215 ML20246P4011989-07-14014 July 1989 Informs That Evaluation of Contracts & Agreements Identified No Restrictions on Employee Ability to Provide Info About Potential Safety Issues to NRC NL-89-547, Forwards Amend 110 to License DPR-54,issued on 890609, Identifying Discrepancy in Tech Spec Page X (Table of Contents) Which Does Not Reflect Changes Approved in Amend 1061989-07-0606 July 1989 Forwards Amend 110 to License DPR-54,issued on 890609, Identifying Discrepancy in Tech Spec Page X (Table of Contents) Which Does Not Reflect Changes Approved in Amend 106 ML20246A9751989-06-30030 June 1989 Advises That Concerns Addressed in Generic Ltr 89-08 Inapplicable,Since Util Intends to Defuel Reactor.Generic Ltr Will Be Reviewed Prior to Placing Facility in heatup-cooldown Operational Mode for Return to Power ML20246A5171989-06-30030 June 1989 Forwards Rancho Seco Closure Plan, Per 890621 Request for Addl Info Re Plan CEO-89-289, Notifies of Change in Operator/Senior Operator Status.Listed Operator/Senior Operator Terminated Employment on Listed Effective Date1989-06-27027 June 1989 Notifies of Change in Operator/Senior Operator Status.Listed Operator/Senior Operator Terminated Employment on Listed Effective Date NL-89-526, Lists Discrepancies Noted in Amend 109 to License DPR-54,per 890615 Discussion W/S Reynolds.Tech Specs Encl1989-06-22022 June 1989 Lists Discrepancies Noted in Amend 109 to License DPR-54,per 890615 Discussion W/S Reynolds.Tech Specs Encl ML20245H4181989-06-21021 June 1989 Discusses Util Plans Re Overall Closure of Plant,Per 890615 Meeting W/Nrc.Util Will Request Appropriate Changes to Tech Specs to Reflect Defueled Mode & Will Evaluate & Request Changes to Emergency Plan ML20245D9281989-06-21021 June 1989 Discusses Activities Underway Re Plan for Closure of Plant Discussed During 890615 Meeting W/Region V.Util Intends to Continue Use of Essential Programs,Such as Preventive Maint Program,For Sys within Scope of Closure Process ML20245A0981989-06-16016 June 1989 Responds to NRC Bulletin 89-001, Failure of Westinghouse Steam Generator Tube Mechanical Plugs. No Westinghouse Plugs Used at Plant ML20248B5751989-06-0202 June 1989 Advises That Util Anticipates That Final Analysis of Thermal Striping Will Conservatively Support Surge Line Lifetime Significantly Longer than June 1994 Date,Per NRC Bulletin 88-011, Pressurizer Surge Line Thermal Stratification NL-89-468, Submits Justification for Absence of Functional Testing Requirement in Proposed Tech Spec 4.14(f) Re Snubber Svc Life Monitoring,Per 890517 Request1989-05-30030 May 1989 Submits Justification for Absence of Functional Testing Requirement in Proposed Tech Spec 4.14(f) Re Snubber Svc Life Monitoring,Per 890517 Request ML20247N2601989-05-25025 May 1989 Requests Guidance Re Whether NRC Concurs W/Arbitrator Order Concerning Employee Access to Plant 1990-09-06
[Table view] |
Text
- -
7 ,
$)SMUDSACRAMENTO MUNICIPAL UTILITY DISTRICT i j 6201 S Street, P.O. Sc= 15830, Sacramento CA 958521830,(916) 452-3211
. AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA GCA 87-032 JUN 2 619irl i
J. B.. Martin, Regional Administrator U.S. Nuclear Regulatory Commission Region V, Office of Inspection & Enforcement 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596 Docket No. 50-312 )
Rancho Seco Nuclear Generating Station !
License No. DPR-54 i
Response to Notice of Violation (NRC Inspection Report No.
50-312/86-22, Revision 1)
Dear Mr. Martin:
By letter dated August 26, 1986, the Sacramento Municipal Utility District was transmitted a Notice of Violation concerning-the retention of routine and special surveillance and calibration test records. As a result of an internal audit of a warehouse used for document storage and the letter from J. E. Ward (SMUD) to J. B. Martin-(NRC) dated April 24, 1987, the District provides the enclosed updated response to the Notice of Violation.
This letter acknowledges the violation cited and describes the District's intended corrective actions for each specific item listed in the Notice of Violation.
If there are any questions concerning this report, please contact Mr. Ron W. Colonbo at (916) 452-3211, extension 4236.
Sincerely, Ca N 22h nini An rwt T c %
G Chief' Exec tive Officer, Nuclear $ ,)'o EES E3 Attachment %
< ) %o cc: A. D'Angelo @
G..Kalman o IMPO
dh0k050 07074 y ,
l jh_ d RANCHO SECO NUCLEAR GENERATING STATION , 14440 Twin Cities head Herald, CA 95638-9799;(209) 333-2935
," DRAFT 8 DATED Jun3 24, 1987, 9 33 AM
{
l ATTACHMENT 1 DISTRICT RESPONSE TO NRC INSPECTION 86-22. REVISION 1 NOTICE OF VIOLATION NF.C Violation As a result of the inspection conducted between June 10 and July 25, 1986, and in accordance with NRC Enforcement Policy, 10 CFR Part 2, Appendix C, the following alleged violation was identified:
10 CFR Part 50, Appendix B, Criterion XVII, " Quality Assurance Records," requires sufficient reccrds shall bc )
maintained to furnish evidence of activities affecting quality such as tests. This criterion further requires the applicant to establish requirements concerning record retention, such as duration, location, and assigned responsibility.
The licensee's Quality Assurance Procedure Number 18, Revision 1, " Quality Assurance Records," requires that
"[t]he provisions of NQA-1, Supplement 17S-1, Requirements for Quality Assurance Records, shall be used for management of plant records."
ANSI /ASME HQA-1, Supplement 17S-1, 4.4.1, " Single Facility,"
requires' that the design and construction of a sir.gle record storage facility shall comply with tha requirement of a minimum two-hour-fire rating, and; 4.4.2 " Alternate Single Facilities: requires that a two-hour fire rated Class b file container meet the requirements of NFPA 232-1975.
Contrary to the above, at the time of the inspection, the records of routine and special surveillance and calibration tests performed during the past two years on safety-related structure, systems and components, as prescribed in the facility's Technical Specifications, were stored in metal file cabinets and on shelves in the Administration Building and the Instrument and Control (I&C) shop. Some of these file cabinets have a fire rating of one hour, while others were not rated. Neither the Administration Building, nor the I&C shop were designed and constructed as record storage facilities'to comply with the requirement of a mininum two-hour-fire rating.
1 This is a Severity Level IV violation.
District Response to Violation
- 1) Admission or denial of the alleged violation.
The District acknowledges and admits that this item I occurred as stated. I
i
- 2) Reasons for the violation In 1982, the District developed a Records Management system which uses microfilm and a computer data base [
for indexing the Quality Assurance records on film.
This system went into operation in 1982. This system meets all of the stated requirements and uses the dual l storage concept for the microfilm aasters. Of the two l rasters that are produced, one is stored at the site l and one is stored at an off-site facility in Tahoe ,
City, California. At the time the system went into l operation, there was a records backlog on-site of approximately ten years. At the end of August 1986, due to inadequate resource allocation for the process, the backlog had grown to approximately 1.7 million pages of records in the syctem. This backlog represents approximately twelve years worth of records.
Although the Training and Records Building vault was l completed in 1985, Records Management did not begin to f occupy the vault until August 1980. Due to the large (
record systems backlog, many records were stored in the non-rated Administration building vault in hard. copy. I Several boxes cf Instrument Maintenance Dtta i remained in the I&C shop vork area during this time !
because the non-rated storage vault did not have I adequate space.
- 3) Corrective actions which have been taken and results achieved.
The subject Instrument Maintenance Data that were located in the I&C Shop work aree during the NRC inspection were transferred to the on-site rated-vault.
They were filmed subsequent to the inspection.
All the Instrument Maintenance Data records were transferred to Records Managemant and stored in the on-site rated-vault until they were filmed. Eight to ten bindere per week of.these records were filmed and returned to the work area subsequent to this violation through December 1986. Now Instrument and Control Testing Data are stored (RE: RSAP-0601) in one-hour-fire rated file cabinets. Copies of the data are kept in binders in the local work area.
__ . . _ . _ _ _ _ _ _ _ _m. _ _ _ _ _ . _ _ _ _ _
4 -
J J
- Surveillance' Procedure (SP) records are transferred l- j from the Technical Support Group to Records Information l
~ Management for filming on a regular basis. .The I associated SP Technical Lead Sheets are prepared . by l Technical Support personnel. Those Technical. Lead l .
Sheets provide the basis of the index for the records. l The indexing of the records allows their retrievabi)ity. l l f
At the time of the NRC inspection, many of the l Surveillance Procedure records observed in the filing l cabinets in the Administration Building were already l microfilmed. There were. approximately two file l cabinets of Surveillance records in the Administration [
Building awaiting transfer to Records Management for l filming, and these cabinets have a one-hour-fire l rating. That arrangement is adequate ' for the current I plant. situation, for the reasons described below. I Subsequent to receiving the notice of violation, the l District attempted to locate two-hour-fire rated filing I cabinets which would meet NQA-1, Supplement 17S-1. l Numerous sources were contacted, including subscribers l to the " NUCLEAR NETWORK." The District learned that [
file cabinet vendors do not make two-hour-fire rated l file cabinets. The only correctly rated units available l are safe-type vaults equipped with drawers. However, l the floor loading requirements for these safes will not i permit their usage in the various work areas at Rancho l Seco. l At a NIRMA (Nuclear Information Records Management Association) meeting in Denver, during the week of September 8, 1986, a District representative' spoke with representative from numerous other utilities who advised us that they have the same problem as the District and have filed for exemption from NQA-1, Supplement 17S-1.
Quality Assurance (QA) revised QAP-18, on records ]
retention, to describe an exception to the two-hour i fire rated cabinet requirement of NQA-1, Supplement j 17S-1 in the local work areas. In addition, QA defined l the term " record" to clarify what is to be processed by l Records Management. Records Management has also revised I its administrative procedure, RSAP-0601, to conform to j the new QAP. The revised administrative procedure l requires the completion of an index sheet for the i filming process, a Records Management transmittal form, I and interim storage of Quality Records in one-hour-fire ]
rated file cabinets until they can be filmed or placed l in the vault. More than 63, one-hour fire rated file I cabinets were ordered for interivt storage of records in work locations.
,' -4
.; l New Quality Records produced after December 1, 1986, are sent with an index sheet and transmittal form to l ;
Records Management for protection, after completion and l authentication, thereby eliminating the development of l I any further backlog. Prior to storage of recorda in l 1 either the on-site or off-site vaults, all records are l !
being indexed for retrievability. I One-hundred twenty days will be the maximum period that Quality Records generated, completed, and authenticated I after December 1, 1986, will be maintained in one-hour- i fire rated cabinets prior to protection. l l 1
The . staff of the Records Management organization was l increased to provide for a microfilm operation on two l shifts instead of one. That, along with a directive I issued by the Deputy General Manger, Nuclear concerning l the forwarding of all quality records to the Records l Information Center (RIC) Files has eli:ainated the l growth in the Rancho Seco backlog of unprocessed l quality records. This was concluded from meetings held l with working level Records Mangement Coordinators !
during June 1987. The District is currently generating l approximately 500,000 new quality records per year and l is microfilming at a rate in excess of 1,300,000 l records per year. !
The District's Quality Assurance audit of a warehouse l in Sacramento being used to store closed engineering l packages revealed that approximately si boxes of closed l Engineering Packages, and 523 boxes of Purchase Orders l are both kept at that warehouce. This warehouse Goes [
not comply with ANSI /ASME NQA-1, Supplement 17S-1. [
That being the case, the District investigated l potential alternatives with action items as described I in the following section. l With RSAP-0601, the District established formal l j administrative door control to maintain fire integrity i of the T&R building vault, among other requirements and l standards for records management at Rancho Seco. l The Records Management Group located an off-site l storage facility that nearly complied with ANSI /ASME l NQA-1, Supplement 17S. After bringing the off-site vaultj fully up to standard, a contract was signed l establishing a second rated-vault for the District to l use. l
- 4) Corrective steps which will be taken to avoid further violations.
The remaining records that have not been filmed or i stored in the on-site record storage vault will be l transferred to this facility by September 1, 1987. I
I ..
High - density storage equipment is l scheduled . to'.' be - l installed' incapacity storage the on-siteover rated vault and will increase:thei 40 percent" for an estimated I capacity . of . 5.2 million pages stored in the : vault.
After
'l -
installation, t h e - 9 1 ;- b o x e s of . engineering l packages this' Records stored in Sacramento Management vault. willi be transferred ' to' l Of the 523 ' ' boxes ! of- l:
Purchase' Orders' stored in Sacramento, 348 have already - I been -retrieved .for protection and processing i'nto the i Records M a n a g e m e n t - s y s t e m'. However, this extra- l capacity necessitates capability for the-vault.
an increased fire suppression l This enhancement would~ allow l the District' to safely store more records in the on- l site rated-vault .while they are awaiting - filming. The l Fire Protection .. Group of the Nuclear. - Engineering 7 l organization.provided recommendations for the. vault i fire suppression system enhancement.
l 1
l l
3 l
l l
-6. )
., . .=
The District will increase the Halon capacity of the l 4 T&R vault fire suppression system by October 15,.1987. l The on-site fire protection group established an l hourly' fire watch patrol for the T&R building vault for l those times that the room surrounding the vault is I unattended. l The revised QA position on the ' two-hour fire rated l cabinet requirement of NQA-1, Supplement 17S-1 will be l formalized by submitting a revision of ' the QA Plan to l Region V of the NRC. l
- 5) Date full compliance will be achieved.
The capacity of the on-site record storage vault will l be expanded by July 1987, so that new quality records j can be stored ~ on-site prior to filming. The I corresponding upgrade to the fire protection capability l provided in the vault will be established prior to l October 15, 1987.. l By September 1, 1987, the entire backlog of quality- l records and all current quality records, as they are l.
turned over to Records Management, will be indexed and l protected in accordance with Rancho Seco . procedures, l (pending the vault fire protection system upgrade) and l fully retrievable. l l
E i