ML20235K032
| ML20235K032 | |
| Person / Time | |
|---|---|
| Site: | Rancho Seco |
| Issue date: | 07/02/1987 |
| From: | Rood H Office of Nuclear Reactor Regulation |
| To: | Holahan G Office of Nuclear Reactor Regulation |
| References | |
| NUDOCS 8707160116 | |
| Download: ML20235K032 (1) | |
Text
_
1 July 2,
1987 NOTE T0: Gary M. Holahan, Assistant Director DISTRIBUTION for Regions III and V
. Docket;Filea C Division of Reactor Projects - III, NRC & Local PDRs IV, V and Special Projects PDV Reading GMHolahan THRU:
George W. Knighton, Director HRood Project Directorate V RDudley Division of Reactor Projects - III, JLee IV, Y and Special Projects FROM:
Harry Rood, Senior Project Manager Project Directorate V Division of Reactor Projects - III, IV, V and Special Projects
SUBJECT:
IMPENDING SLIP OF SCHEDULE, RANCHO SEC0 RESTART SER Based on recent discussions with the principal reviewers, it appears that most reviewers will not meet the July 7, 1987 date for input to the Rancho Restart SER. As you recall, F. Miraglia, in his memo of June 12, 1987 to R. Starostecki, requested SER input by July 7,1987.
In particular, the SICB input, which constitutes about 40% of the SER, will probably be about a month late.
Since issuing the SER without this input would not achieve the objectives agreed upon in our June 4 meeting with Dr. Murley, we will have to delay the SER issuance until September.
Sincerely, Original s!gacd by; Harry Ecod Harry Rood, Senior Project Manager Project Directorate V Division of Reactor Projects - III, IV, V and Special Projects cc:
D. Crutchfield F. Miraglia R. Starostecki h
f DRSP/PDV DR$ h:PDV M 8/D HRood:cd GWfuPghton GMF ahan 7/ L/07 7/p/87
/
OFFICIAL RECORD COPY B70716011b B70702 DR ADDCK 050003]p p