ML20235G655
| ML20235G655 | |
| Person / Time | |
|---|---|
| Site: | Fort Saint Vrain |
| Issue date: | 09/23/1987 |
| From: | Robert Williams PUBLIC SERVICE CO. OF COLORADO |
| To: | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
| References | |
| P-87329, NUDOCS 8709300140 | |
| Download: ML20235G655 (2) | |
Text
- - _ _ _ _ _ _ _ _ _ _ _ _ _ _
l l
O rubiic service-
- ='.
P.O. Box 840 l
Denver, CO 80201- 0840 September 23, 1987 R.O. WILUAMS, JR.
Fort St. Vrain VICE PRESIDENT Unit No. 1 NUCLEAR OPERATIONS P-87329 U. S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, D.C.
20555 Docket No. 50-267 i
SUBJECT:
Temporary Configuration Report commitments prior to exceeding 35% power.
Gentlemen:
This letter summarizes Public Service Company's (PSC) commitments to support _ continued operation of Fort St. Vrain (FSV), with respect to items discussed at the September 10, 1987 Enforcement Conference. At this conference PSC committed to limit reactor power to 35% pending completion of the following items:
1.
Prepare a Justification for Continued Operation (JCO) for all outstanding Safety Related Temporary Configuration Reports (TCRs) and obtain concurrence of the Senior Resident Inspector.
2.
Provide PSC's classification / evaluation of all non-safety related TCR's to the Senior Resident Inspector for review.
3.
Flag special handling documents (E-1203, PI, IB and IC) in the control room and shift supervisor's office to indicate TCR l
involvement.
i l
Dahff{}EA' 3 l po\\ l 9 l t i
( .j. P-87329 September.23, 1987 We are proceeding on the basis that once we have completed the above items we wil1 be released by the Senior Resident Inspector to exceed 35%. power. Other details. of the TCR program such as the root cause associated with the long term use of TCRs, PSC's schedule 'for closecut of existing TCR's, Quality Assurance involvement in the TCR process and the' interim and long term procedural controls that were discussed at the September 10, 1987 Enforcement Conference will be handled in our-response'to the forthcoming Notice of Violation associated with Inspection Report 87-17. If you have any questions concerning this letter, please contact Mr. M. H. Holmes at (303) 480-6960. Very truly yours, s x R. O. Williams, Jr. Vice President Nuclear Operations R0W/ BAS /imb cc: Regional Administrator, Region IV ATTN: Mr. J. E. Gagliardo, Chief Reactor Projects Branch i l Mr. R.E. Farrell { Senior Resident Inspector i Fort St. Vrain 1 l I l l E____ l}}